Loading...
Ordinance No. 15,046 ORDINANCE NO. 15,046 AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS, AUTHORIZING CHANGE ORDER NO. 5 TO THE RECONSTRUCTION OF ROLLINGBROOK DRIVE PROJECT FROM GOOSE CREEK TO DECKER DRIVE WITH GULF COAST, CRH, F/K/A ANGEL BROTHERS, LTD, IN AN AMOUNT NOT TO EXCEED TWO HUNDRED THIRTY-SEVEN THOUSAND THREE HUNDRED EIGHTY-TWO AND 50'100 DOLLARS ($237,382.50); AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. ****************************************************************************** BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,TEXAS: Section l: That the City Council does hereby authorize Change Order No. 5 to the Reconstruction of Rollingbrook Drive Project from Goose Creek to Decker Drive with Gulf Coast, CRH,f'k/a Angel Brothers,LTD, in an amount not to exceed TWO HUNDRED THIRTY-SEVEN THOUSAND THREE HUNDRED EIGHTY-TWO AND 50.100 DOLLARS ($237,382.50). A copy of said change order is attached hereto, marked Exhibit "A" and made a part hereof for all intents and purposes. Section 2: This ordinance shall take effect immediately from and after its passage by the City Council of the City of Baytown. INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the City of Baytown this the 10`I' day of March, 2022. RANDON CAPETI LO, Mayor ATTEST: of 5NYTOW � go V o° •O(! o � • • 0 0 ANGELAJACKSON, Cit o •• OF APPROVED AS TO FORM: 4z-- TREVOR FANNING, Interim City Attorney R:%Karen Anderson�ORDINANCES,,2022�2022.03.IOIChangeOrderNo5-ReconstructionofPollingbrookDriveProject.docx EXHIBIT ►►A►► CITY OF BAYTOWN PUBLIC WORKS&ENGINEERING nToE( 2123 Market St. Baytown,Texas 77520 B CHANGE ORDER For Reconstruction of Rollingbrook Drive Date of Issuance: 2/28/2022 Change Order 5 Contractor: Angel Brothers Enterprises,Ltd. CoB Project N4 RW1902 Designer: City of Baytown P.O.No.: 2102261 Explanation: The purpose of this change order is to add work items required to repair the Rollingbrook Bridge over Goose Creek,at the eastern end of the original Reconstruction of Rollingbrook Project. CO 5.01 Item 1 is for additional traffic control device-,required to close 112 of the bridge lanes to traffic and to mobilize demobili. equipment required for the bridge repair work. CO 5.02 Item 2 is to remove and replace the existing western approach slab.The existing approach slab has settled and is failing. CO 5.03 Item 3 is to remove and replace the existing subgrade underneath the approach slab to insure proper support for the new approach slab. CO 5.04 Item 4 is to remove an existing tree that is adjacent to the western bridge approach.This tree could be responsible for the unstable consition of the existing approach slab. CO 5.05 Item 5 is to repair the existing concrete spalls on the bridge deck.Unstable concrete will be removed and replaced. CO 5.06 Item 6 is to cover existing open joints on the bridge sidewalk with steel plates.Required for ADA compliance. CO 5.07 Item 7 is to clean out and reseal existing bridge deck joints.This is required to allow the joints to function as designed. CO 5.08 Item 8 is to fill an existing void underneath the abutment wingwall. Filling this void will help maintain wall stability. CO 5.09 Item 9 is to Remove and replace a section of settled concrete sidewalk at the NE corner of the bridge. Replacing the existing sidewalk is required for ADA compliance. CO 5.10 Item 10 is to have a method available to fill unknown voids or replace additional unsuitable material should any be encountered during the removal of the western bridge approach. Description of Work Unit Quantity Unit Price Total Time 1 Remobilization/TCP LS 1 $ 24,000.00 $ 24,000.00 45 Days 2 Rem. and Replace Western Bridge Approach SY 123 $ 483.00 $ 59,409.00 0 Days 3 Rem. Exist. 12" subgrade&install 12"CSS TN 82 $ 323.00 $ 26,486.00 0 Days 4 Remove Existing Tree JEA 1 $ 1,500.00 $ 1,500.00 0 Days 5 Repair Existing Deck 380 $ 212.00 $ 80,560.00 0 Days 6 Install Plates over Open Sidewalk Joints 6 $ 2,900.00 $ 17,400.00 0 Days 7 Clean Out and Reseal Deck Joints 330 $ 27.50 $ 9,075.00 0 Days 8 Fill Void Under Abutment Wingwall 0.5 $ 3,525.00 $ 1,762.50 0 Days 9 Rem,.And Replace Settled Sidewalk 100 $ 96.50 $ 9,650.00 0 Days 1 0 Flowable Fill to Replace unsuitable material 20 $ 377.00 $ 7,540.00 1 0 Days TOTAL $ 237,382.50 45 Days Please attach back-up documentation Proposal from Angel Brothers dated March 1, 2022 attached. Construction I of 2 D16 Revised 2020 Cost&Time Change Summary Cost Time Original Contract: $2,256,677.05 427 Days Previous Change Order(s): $ 127,957.25 0 Days Contract prior to this change order: $2,384,634.30 0 Days Net increase(decrease)from this change order $ 237,382.50 45 Days Revised Contract: $ 2,622,016.80 472 Days Finance Approval: Date: RECOMMENDED: By: T*" ' 1 ,A44 Date: 03-1-2022 G �''b�� crJ� —.bate: 03/01/2022 Design Engineer Director of Public Works&Engineering ACCEPTED*: By: -4 ! - Date: 3/1/22 Date: Contracto City Manager *Contractor agrees to perform change(s)included in this Change Order for the price and time indicated. The prices for changes included all costs associated with this Change Order. No work is to be done until this change order is executed.No payment to the Contractor(or Consultant)shall be made for work included in the change order until the Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent,this Change Order governs.Upon execution by all parties,the following changes identified for the contract value and/or contract time shown,are made part of the contract. Construction 2 of 2 D 16 Revised 2020 Angel Brothers Holdings 3003 Kilgore Parkway Building A Baytown,Texas 77522-0570 AngelBrothers Phone 281.421.5721 Fax 281.421.5796 PcongondUfllityControctors www.aneelbrothers.com An Equal Opportunity Employer March 1 st, 2022 Juan Macias, PE, CFM Public Works & Engineering Department City of Baytown 2123 Market Street Baytown, TX 77522 281-420-3 869 Dear Mr. Macias, Angel Brothers Agrees to the attached unit pricing for the Bridge Repair work that is reference in Change Order 5. Please give me a call if you have any questions. Sincerely, v 'Z7 Arley Garza Project Manager 014ROLLICO Bridge Approach Rollmgbook CO Arley Garza 2/25/2022 2 46 PM BID PROPOSAL Biditem Description Quantity Units Unit Price Bid Total 10 Renlobllizatton/TCP 1 000 LS 24.000 00 24,000 00 20 Remove and Replace Bridge Aproach 123 000 SY 48300 59,409 00 25 Remove Existing 12"of Material and Install 12"CSS 82 000 TN 32300 26,486.00 30 Remove Existing Tree 1 000 EA 1,50000 1,500.00 40 Remove and Replace Bridge Deck Repairs 380 000 SF 21200 80,560 00 50 Install Plates Over Joints Sidewalk 6 000 EA 2,90000 17,400 00 60 Clean Out and Reseal Joints 330 000 LF 2750 9,07500 70 Fill Void Under Abutment Wingwall 0 500 CY 3,52500 1,76250 80 Remove and Repalce Settled Existing Sidewalk 100 000 SF 9650 9,65000 90 1Flox%able Fill To Fill Unsuitable Sod 1 200001 CYI 377001 7,54000 Bid Total $237,382.50 1