Ordinance No. 14,993 ORDINANCE NO. 14,993 AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS, AUTHORIZING CHANGE ORDER NO. 2, WHICH AMENDS THE CONSTRUCTION MANAGER-AT-RISK CONTRACT FOR THE PUBLIC SAFETY FACILITY PROJECT WITH DUROTECH, INC., IN AN AMOUNT NOT TO EXCEED THIRTEEN MILLION FIVE HUNDRED NINETY-FOUR THOUSAND NINE HUNDRED THIRTY-SEVEN AND N0/100 DOLLARS ($13,594,937.00);AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS: Section 1: That the City Council does hereby authorize Change Order No. 2, which amends the Construction Manager-at-Risk Contract for the Public Safety Facility Project with Durotech, Inc., in an amount not to exceed THIRTEEN MILLION FIVE HUNDRED NINETY- FOUR THOUSAND NINE HUNDRED THIRTY-SEVEN AND NO/100 DOLLARS ($13,594,937.00). A copy of said change order is attached hereto, marked Exhibit "A" and made a part hereof for all intents and purposes. Section 2: This ordinance shall take effect immediately from and after its passage by the City Council of the City of Baytown. INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the City of Baytown this the 131h day of January, 2022. NDON CAPETILL , Mayor ATTEST: O ,,Oa aapyn.� O O J ANGE JACKSON, City Cie a A� .A e APPROVED AS TO FORM: TREVOR FANMNG, Interim City Attorney RAKaren Anderson'•.ORDINANCES\2022\2022.01.13 ChangeOrderNo2-PublicsafetyFacilityProject.docx Exhibit "A" CITY OF BAYTOWN PUBLIC WORKS & ENGINEERING 2123 Market St. E Baytown,Texas 77520 BE TES BAYTOWN CHANGE ORDER For Public Safety Campus: Phase 1B Date of Issuance: 12/21/2021 Change Order No.: 2 Contractor: Durotech Inc. CoB Project No.: FA1901 Designer: BVG4 Architecture P.O.No.: 2103500 Explanation: This change order encompasses the following: The Guaranteed Maximum Price (GMP) for the construction of the Baytown Public Safety—Phase 1B: Vehicle Service Center in the amount of$13,594,937.00 and a duration of seven(7) months. These costs include General Conditions, Bonds&Insurance; General Site Requirements; Existing Conditions,Construction of Pre-Fabricated Metal Buildings (Vehicle Maintenance Building, Special Equipment Storage Buildings,Vehicle Impound Processing Bay), Foundations, Paving,Final Grading, Masonry, Interior Finishes,Fire Protection Systems, HVAC, Electrical, Plumbing,Fencing and Landscaping; and the Construction Manager at Risk Fee of 2.3%. Included in this Change Order are three(3) Cummins Generators for Phase 2 since these are long lead items with volatile pricing. Description of Work Cost Time 1 General Conditions, Bonds&Insurance $644,572.00 2 General Site Requirements $557,942.00 3 Concrete(Building Foundation and Site Paving) $2,200,568.00 4 Masonry $250,000.00 5 Metals (Structural Steel, Rails, and Panels) $387,651.00 6 Woods(Rough Carpentry and Millwork) $66,654.00 7 Thermal and Moisture Protection $339,394.00 8 Openings (Doors and Glazing) $838,769.00 9 Finishes(Gypsum Board,Tiling, Resilient Flooring) $379,862.00 10 Specialties(Signage, Toilet Accessories,Protective Covers) $102,047.00 11 Equipment(Appliances) $1,496.00 12 Furnishings (Window Shades and Floor Mats) $10,060.00 13 Special Constructions(Metal Building Erection) $666,643.00 14 Fire Suppression Systems $105,000.00 15 Plumbing $595,620.00 16 HVAC $1,066,500.00 17 Electrical $2,665,066.00 18 Communications (Structured Cabling and AV System) $108,031.00 19 Electronic Safety and Security $268,635.00 20 Earthwork $153,401.00 21 Exterior Improvements(Fences, Gates,Irrigation,Landscaping $999,544.00 22 Utilities $15,625.00 23 Construction Manager At Risk Fee 2.3% (Phase 1A) $285,731.00 24 Phase 2 Generators By Cummins $886,126.00 $13,594,937.00 213 Days (Change Order Continues on Next Page) Construction 1 of D16 Revised 2020 The additional scope of work and the schedule associated with the same, are attached liereto as Exhibit "A" dated December 17, 2021 and incorporated herein for all intents and purposes. Cost&Time Change Summary Cost Time Original Contract: $ 89,000.00 Days Previous Change Order(s): $ 4,905,614.00 152 Days Contract prior to this cliange order: $ 4,994,614.00 Days Net increase(decrease) from this change order $ 13,594,937.00 213 Days Revised Contract: $ 18,589,551.00 365 Days Finance Approval: Date: RECOMMENDED: RECOMMENDED: 13y: Date: 1-3-2022 ray:� �� - ' Date: 01/04/2022 Delign Architect Director of Public Works&Engineering a:LA,— APPROVED: Date: Oaa By: Date: Contractor City Manager *Contractor agrees to perform change(s)included in this Change Order for the price and time indicated. The prices for changes included all costs associated with this Change Order. No work is to be done until this change order is executed No payment to the Contractm�(or Consultant)shall be nude for work included in the change order until(lie Contractors pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent,this Change Order governs.Upon execution by all parties,the following changes identified for the contract value and/or contract time shown,are made part ofthe contract. Construction 2 of 2 D 16 Revised 2020 DUROTECH BUILDERS OF INTEGRITY Date: December 17, 2021 Ms. Andrea Brinkley Assistant Director— Capital Projects City of Baytown - Public Works & Engineering 2123 Market Street Baytown, TX 77522 Re: Guaranteed Maximum Price for Baytown Public Safety — Phase 1 B — Vehicle Service Center Dear Ms. Brinkley: We wish to inform you that after several months of working together with City of Baytown and BVG4 Architecture LLC on this important facility, we have formally advertised and solicited proposals for the development of the GMP for the Phase 1 B — Vehicle Service Center project. Over 200 proposals were received on November 23rd, 2021. After careful review and compilation of these proposals, Durotech, Inc. is pleased to present a Guaranteed Maximum Price for the construction of the Baytown Public Safety — Phase 1 B —Vehicle Service Center of$13,594,937.00 It is our recommendation that we ask City of Baytown Council to approve the Guaranteed Maximum Price of$13,594,937.00 and to execute the GMP Amendment No. 2 between City of Baytown and Durotech, Inc. We are excited about the potential of entering into the construction phase of this project and want to thank you and your team, BVG4 Architecture and their consultants for a very successful pre-construction phase. Durotech is committed to City of Baytown in the successful delivery of the New Vehicle Service Center project. Thank you and City of Baytown for selecting Durotech as its building partner. It is our goal to meet and exceed your expectations. Should you have any questions please do not hesitate to contact me. Sin rely, avid Rowe CEO 1 1 11931 Wickchester Lane e Suite 205 @ Houston, Texas 77043-4501 Phone 281.558.6892 e Fax: 281.496.5637 a U ROTEC H BUILDERS OF INTEGRITY GMP SUMMARY Project: Baytown Public Safety— Phase 1 B —Vehicle Service Center Location: 3200 N Main St., Baytown, TX 77522 Owner: City of Baytown GMP Proposal Package: The GMP proposal package consists of the following items: 1. Exhibit A — GMP Top Sheet — dated 17 December 2021 2. Exhibit B — Project Manual — dated 18 June 2021 (Reissued for bid — 15 October 2021) 3. Exhibit C — List of Drawings —dated 18 June 2021 (Reissued for bid — 15 October 2021) 4. Exhibit D — List of Addenda 5. Exhibit E — Qualifications & Assumptions 6. Exhibit F —Allowance Schedule 7. Exhibit G — Self Performed Work Items 8. Exhibit H — Unit Prices 9. Exhibit I — Cost Saving Items Scope of Work: A] The Project: The Project consists of the following: 1] Construction of 779 SF prefabricated Detailed Covered Area, Building "S". 2] Construction of 28,798 SF of air-conditioned, hurricane resistant prefabricated steel Vehicle Maintenance Building "T" and 5,192 SF of non-conditioned space. 3] Construction of 975 SF of air-conditioned, hurricane resistant prefabricated steel Vehicle Storage Building "U" and 7,373 of non-conditioned space. 4] Construction of 557 SF of air-conditioned, hurricane resistant prefabricated steel Vehicle Storage Building "V" and 2, 595 SF of non-conditioned space. 5] Construction of 804 SF prefabricated steel Impound Covered Area Building "W". 6] Construction of 720 SF of air-conditioned, prefabricated Impound Vehicle Building "X", with 2,560 of covered parking. 7] Balance of Associated Site Work including Paving, Sidewalks, and Foundations 8] Final Grading and Spread & Grade Spoils 9] All Masonry Work 10] Windstorm Inspections and Field Engineering 16] All Rough Carpentry, Millwork and Solid Surfaces 11] All Thermal & Moisture Protection 12] All Openings and Doors 13] All Interior Finishes 14] All Fire Protection Systems 15] All Plumbing Work 16] All HVAC Systems 2 11931 Wickchester Lane o Suite 205 • Houston, Texas 77043-4501 Phone; 281.558.6892 r Fax. 281.496.5637 DUROTECH BUILDERS OF INTEGRITY 17] All Electrical Work, including Site Electrical Work and Cummins Generator 18] All Fences and Gates 191 All Concrete Screen Walls 201 All Landscaping and Irrigation B] Included in this Phase 1 B proposal are the Cummins Generators (3) for Phase 2. These generators are long lead items with volatile pricing which must be secured. 3 11931 Wickchester Lane • Suite 205 • Houston, Texas 77043-4501 Phone: 281.558.6892 • Fax: 281.496.5637 EXHIBIT'A' PROJECT: Baytown Public Safety-Phase 1 B _ _ _ LOCATION: 3200 North Main St.,Baytown,TX 77521 D U ROT E C H OWNER: City of Baytown BUILDERS OF INTEGRITY ARCHITECT. BVG4 Architecture _-_- DATE: 12N7/2021 BAYTOWN PUBLIC SAFETY-PHASE 1B SECTION _ _ DESCRIPTION __ PHASE 1B _ REMARKS LABOR MATERIAL SUB-BIDS TOTAL 01 1000 SUPERVISION 223,344 - 223,344 01 1500 TEMPORARY/GENERAL CONDITIONS 6,062 112,266 - 118,328 01 1940 ADVERTISEMENTS - - 630 630 01 2000 EQUIPMENT 7,375 - 7,375 01 4220 AGC FEES - 14,604 14,604 01 4225 BUILDER'S RISK INSURANCE 82,547 82,547 01 4230 GL INSURANCE 98,493 98,493 01 4240 IPAYMENT&PERFORMANCE BOND I - 99,251 99,251 SUB TOTAL-DIV 00 GENERAL CONDITIONS 229,406 119,641 295,526 644,572 01 21 00 QUANTITY ALLOWANCE 0 0 NONE 01 21 05 CONSTRUCTION CONTINGENCY ALLOWANCE 300,000 300,000 01 21 15 SITE ELECTRICAL CONDUIT ALLOWANCE 0 0 IN PHASE 1A 01 21 20 COURTS DRAINAGE ALLOWANCE 0 0 IN PHASE 1A 01 21 21 PHASE 16:BREAKROOM LOCKERS&APPLIANCES 0 0 BY OWNER 01 21 22 PHASE 1B:VEHICLE LIFTS&FLUID DISTRIBUTION 0 0 BY OWNER 01 21 23 PHASE 1B:SHOP EQUIPMENT 0 0 BY OWNER 01 21 24 IPHASE 113:MAINTENANCE EQUIPMENT 0 0 BY OWNER 01 21 25 PHASE 1B:BUILDING'U'WORKROOM EQUIPMENT 0 0 BY OWNER 01 21 26 PHASE 113:BUILDING'X'RELOCATION OF LIFT 0 0 BY OWNER 01 21 27 PHASE 2:HIGH DENSITY STORAGE SHELVING 0 0 BY OWNER 01 21 28 PHASE 2:CRIME SCENE LAB EQUIPMENT 0 0 BY OWNER 01 21 29 PHASE 2:FITNESS EQUIPMENT&WRESTLING MATS 0 0 BY OWNER 01 21 30 PHASE 2:BRK ROOM/KITCHEN/FA KITCHEN APPLIANCES 0 0 BY OWNER 01 21 31 PHASE 2:SWAT ARMORY STORAGE CABINETS 0 0 BY OWNER 01 21 32 PHASE 2:FARADAY ROOM ALLOWANCE 0 0 BY OWNER 01 21 33 PHASE 2:POLICE&FIRE DEPT SHIELDS/MONUMENT SIGN 0 0 ALLOWANCE 01 21 34 PHASE 3:BUILDING D RENOVATIONS 0 0 ALLOWANCE 01 21 35 EXISTING SOIL CONDITIONS ALLOWANCE 0 0 ALLOWANCE 01 4339 MOCKUP PANEL 7,500 7,500 01 4533 WINDSTORM INSPECTIONS 17,000 17,000 015113 TEMPORARY POWER 3,250 3,250 01 51 19 EQUIPMENT FUEL&FUEL TANK 1,674 1,674 01 51 36 TEMPORARY WATER 2,025 2,025 01 5370 QMS/SAFETY 40,668 40,668 01 54 16 IMATERIAL HANDLING&HOISTING 52,612 52,612 01 5423 TEMPORARY SCAFFOLDING 11,922 11,922 01 5523 TEMPORARY ROADS 0 0 IN PHASE 1A 01 5526 TRAFFIC CONTROL 0 0 IN PHASE 1A 01 5626 TEMPORARY FENCING 0 0 IN PHASE 1A 01 56 39 TEMPORARY TREE&PLANT PROTECTION - - 01 0 IN PHASE 1A 01 5700 EROSION&SEDIMENT CONTROL 2,850 2,000 4,850 01 5800 TEMPORARY PROJECT SIGNAGE 0 0 IN PHASE 1A 016400 OFCI ITEMS 1,625 1,625 01 71 23 FIELD ENGINEERING&LAYOUT 36,080 7,075 43,155 01 7416 SITE MAINTENANCE/CLEAN STREETS 1,543 3,520 5,063 4 EXHIBIT'A' SECTION _ DESCRIPTION PHASE 1B REMARKS LABOR MATERIAL SUB-BIDS TOTAL 01 74 19 CONSTRUCTION WASTE MANAGEMENT - 9,743 9,743 01 7423 FINAL CLEANING - - 12,855 12,855 019100 lCOMMISSIONING 44,000 - - 44,000 SUB TOTAL-DIV 01 GENERAL REQUIREMENTS 86,098 12,595 459,249 557,942 02 21 00 SURVEYS - 0 0 1 02 41 13 SITE DEMOLITION - 0 0 IN PHASE 1A 02 61 00 REMOVAL&DISPOSAL OF CONTAMINATED SOILS ol 0 IN PHASE 2&3 02 65 00 ]PUMP UNDERGROUND STORAGE TANK REMOVAL 0 0 IN PHASE 2&3 02 65 10PLUG&ABANDON WATER WELL&MONITORING WELLS 0 0 IN PHASE 2&3 02 70 00 &DEWATER - ol 0 1 IN PHASE 1A SUB TOTAL-DIV 02 EXISTING CONDITIONS 0 03 20 00 CONCRETE REINFORCING - 0 0 IN 03 30 00 03 30 00 SITE&BUILDING CONCRETE 2,149.346 2.149,346 03 35 10 ICONCRETE FLOOR SEALER 33,030 33,030 03 35 43 POLISHED CONCRETE 18,192 18,192 03 40 50 CONCRETE TILT UP PANELS 0 0 IN PHASE 2&3 03 40 55 CONCRETE TILT UP PANELS ERECTION - 0 0 IN PHASE 2&3 03 40 60 CONCRETE TILT UP PANELS ACCESSORIES - 0 0 IN PHASE 2&3 SUB TOTAL-DIV 03 CONCRETE 2,200,568 2,200,568 04 05 19 MASONRY REBAR - 0 0 04 20 00 MASONRY 250,000 250,000 SUB TOTAL-DIV 04 MASONRY 250,000 250,000 �rA�s. - ..._..-...... - "gym 05 12 00 STRUCTURAL STEEL FRAMING - 227.952 227,952 05 12 50 STRUCTURAL STEEL ERECTION - 0 0 IN 13 34 20 05 37 00 PREPARE EXPOSED STEEL STRUCTURE 22,435 22,435 - 44,870 05 50 00 MISCELLANEOUS STEEL 53,658 4,400 58,058 05 50 10 TIMBER MATS 14,809 16,750 31.559 05 50 20 SAFETY RAILS 1,928 1,354 3,282 05 53 00 METAL GRATINGS 713 5.235 5,948 05 55 00 METAL NOSINGS - - 0 0 IN PHASE 2&3 05 58 05 DOWNSPOUT BOOTS 4,916 11,066 15,982 05 73 00 DECORATIVE METAL RAILINGS - - 0 01 IN PHASE 2&3 05 75 10 PERFORATED METAL PANELS 01 0 IN PHASE 2&3 SUB TOTAL-DIV 05 METALS 98,459 61,240 227,952 387,651 06 10 00 ROUGH CARPENTRY 9,931 24,970 - 34,901 06 22 00 MILLWORK - - 31,753 31.753 0661 16 SOLID SURFACING FABRICATIONS - 01 01 IN 06 22 00 06 64 00 IPLASTIC PANELING - ol 0 1 IN PHASE 2&3 SUB TOTAL-DIV 06 WOOD,PLASTICS&COMPOSITES 24 970 71 751 66,654 071100 DAMPPROOFING - 76,251 76,251 07 18 00 TRAFFIC COATINGS - 0 0 IN PHASE 2&3 07 19 00 WATER REPELLENTS - 0 0 1 IN PHASE 2&3 07 21 00 THERMAL INSULATION - 127,803 127,803 07 41 00 METAL ROOF INSULATION&UNDERLAYMENT - 96,670 96,670 07 42 00 METAL WALL PANELS - 0 0 IN PHASE 2&3 5 EXHIBIT'A' SECTION DESCRIPTION PHASE IB _ REMARKS LABOR MATERIAL SUB-BIDS TOTAL 076200 MODIFIED BITUMINOUS MEMBRANE ROOFING 0 0 IN PHASE 2&3 07 72 00 ROOF ACCESSORIES 0 0 IN PHASE 2&3 0781 00 JAPPLIED FIREPROOFING 0 0 IN PHASE 2&3 07 84 00 FIRESTOPPING 10,234 10,234 07 92 00 JOINT SEALANTS 28,436 28,436 07 95 00 EXPANSION CONTROL 0 0 IN PHASE 2&3 SUB TOTAL-DIV 07 THERMAL&MOISTURE PROTECTION 339,394 339,394 08 08 00 DOOR&HARDWARE INSTALLATION 15,642 - 15,642 0811 00 METAL DOORS&FRAMES 11,012 146,000 157,012 081423 PLASTIC LAMINATE FACED WOOD DOORS - 0 0 IN PHASE 2&3 0831 00 ACCESS DOORS AND PANELS 428 600A464,955 1,028 08 33 00 COILING DOORS&GRILLES - 464,955 084229 SLIDING AUTOMATIC ENTRANCES 0 IN PHASE 2&3 084500 INSULATED TRANSLUCENT WALL PANELS 94,140 085653 SECURITY WINDOWS 0 IN PHASE 2&3 08 62 23 ITUBULAR DAYLIGHTING DEVICES - 0 0 IN PHASE 2&3 0871 00 DOOR HARDWARE 3,206 3,206 08 80 00 GLAZING - 73,860 73,860 08 80 10 TEMPORARY ENCLOSURES 5,274 3,700 - 8,974 0880 15 CLEAN GLASS 1,389 975 2,364 0891 00 LOUVERS 2,138 15,450 17,588 y� SUB TOTAL-DIV 08 OPENINGS 39,089 166,725 632,95t Y 09 24 00 CEMENT PLASTERING 0 0 IN PHASE 2&3 09 29 00 GYPSUM BOARD 186,306 186,306 09 30 00 ITILING 25,723 25,723 0951 00 ACOUSTICAL CEILINGS 9,336 9,336 09 60 00 FLOOR PREPARATION 10,595 4,957 - 15,552 09 60 10 FLOOR PROTECTION 3,532 2,478 - 6,010 09 65 00 RESILIENT FLOORING - - 5,278 5,278 09 65 66 RESILIENT ATHLETIC FLOORING 0 0 IN PHASE 2&3 09 66 00 TERRAZZO FLOORING 0 0 IN PHASE 2&3 09 67 00 FLUID-APPLIED FLOORING 8,750 8,750 09 68 00 CARPETING 0 0 IN PHASE 2&3 09 69 00 ACCESS FLOORING 0 0 IN PHASE 2&3 09 72 00 WALL COVERING 0 0 IN PHASE 2&3 09 77 00 SPECIAL WALL SURFACING 0 0 IN PHASE 2&3 09 84 00 ACOUSTIC WALL PANELS 0 0 IN PHASE 2&3 09 90 00 PAINTING&COATING 122,907 122,907 09 93 33 SILICATE MINERAL STAINS - - 0 0 NONE SUB TOTAL-DIV 09 FINISHES 14,127 7,435 358,300 379,862 10 11 00 VISUAL DISPLAY UNITS - 0 0 IN PHASE 2&3 10 1400 SIGNAGE 25,000 25,000 ALLOWANCE 10 14 26 POST&PANEL/PYLON SIGNAGE - 0 0 IN PHASE 2&3 1021 13 TOILET COMPARTMENTS 0 0 IN PHASE 2&3 10 22 39 FOLDING PANEL PARTITIONS 0 0 IN PHASE 2&3 10 26 00 WALL&DOOR PROTECTION - 0 0 IN PHASE 2&3 10 28 13 TOILET ACCESSORIES 9,695 9,695 10 44 00 FIRE PROTECTION SPECIALTIES 1,887 1,887 1044 15 KNOX BOX 0 0 IN PHASE 2&3 1051 13 METAL LOCKERS 0 0 BY OWNER 10 73 00 PROTECTIVE COVERS 65,465 65,465 10 75 00 FLAGPOLES - 0 0 IN PHASE 2&3 EXHIBIT'A' SECTION _ DESCRIPTION PHASE I REMARKS LABOR MATERIAL SUB43IDS TOTAL SUB TOTAL-DIV 10 SPECIALTIES 0 0 i.i ,1 11 31 00 RESIDENTIAL APPLIANCES 1,496 1,496 11 52 00 AUDIO-VISUAL EQUIPMENT - 0 0 IN PHASE 2&3 115300 LABORATORY EQUIPMENT 0 0 NONE 11 53 13 LABORATORY FUME HOODS 0 0 NONE SUB TOTAL-DIV 11 EQUIPMENT 0 1,496 12 24 00 WINDOW SHADES 6,879 6,879 12 36 61 SIMULATED STONE COUNTERTOPS 0 0 IN 06 22 00 12 48 13 JENTRANCE FLOOR MATS 3,181 3,181 12 93 00 ISITE FURNISHINGS 0 0 IN PHASE 2&3 12 93 13 JBICYCLE RACKS 0 0 IN PHASE 2&3 SUB TOTAL-DIV 12 FURNISHINGS 10,060 10,060 1334 19 METAL BUILDING SYSTEMS 0 0 IN PHASE 1A 13 34 20 METAL BUILDING ERECTION 666,643 666,643 SUB TOTAL-DIV 13 SPECIAL CONSTRUCTION 666,643 666,643 14 21 00 ELECTRIC TRACTION ELEVATORS 0 0 IN PHASE 2&3 SUB TOTAL-DIV 14 CONVEYING EQUIPMENT 0 0 21 1000 FIRE SUPPRESSION SYSTEMS 105,000 105,000 SUB TOTAL-DIV 21 FIRE SUPPRESSION 105,000 105,000 22 00 00 IPLUMBING 595,620 595,620 SUB TOTAL-DIV 22 PLUMBING 595,620 595,620 23 00 00 HVAC 1.055,000 1,055,000 23 00 10 HVAC FILTER CHANGES 2,500 2,500 23 05 00 IMEP COORDINATION 9,000 9,000 SUB TOTAL-DIV 23 HVAC 1,066,500 1,066,500 26 00 00 ELECTRICAL 2,629,498 2,629,498 INCLUDES CUMMINS GENERATOR 26 00 05 ROUGH INIBACK BOXES-LOW VOLTAGE 15,000 15,000 26 00 10 IPERMANENT POWER START UP 20,568 20,568 26 41 00 ILIGHTNING PROTECTION ol 0 1 IN 26 00 00 SUB TOTAL-DIV 26 ELECTRICAL 2,665,066 27 1000 STRUCTURED CABLING 105,875 105,875 2741 16 INTEGRATED AUDIO-VIDEO SYSTEMS&EQUIPMENT 2,156 2,156 2753 19 IDISTRIBUTED ANTENNA SYSTEM(DAS) ol 0 1 NONE IN PHASE 1 SUB TOTAL-DIV 27 COMMUNICATIONS 108,031 108,031 28 13 00 JACCESS CONTROL SYSTEM 232,500 232,500 7 EXHIBIT'A' SECTION _ DESCRIPTION PHASE I _ _REMARKS_ LABOR MATERIAL SUB-BIDS TOTAL 28 16 00 INTRUSION DETECTION SYSTEM 0 0 NONE 28 23 00 VIDEO SURVEILLANCE SYSTEM 0 0 IN 28 13 00 28 31 00 FIRE DETECTION&ALARM SYSTEM 36,135 36,135 SUB TOTAL-DIV 28 ELECTRONIC SAFETY b SECURITY 268,635 268,635 31 2000 EARTHWORK 0 0 IN PHASE 1A 31 2216 FINAL GRADING 37,285 13,082 50,367 31 2310 SPREAD&GRADE SPOILS 58,078 1 40,756 1 - 98,834 31 31 00 SOIL TREATMENT 4,200 4,20011 31 6329 DRILLED CONCRETE PIERS&SHAFTS ol Oil IN 03 30 00 SUB TOTAL-DIV 31 EARTHWORK 95,363 53,55_ 153,401 3201 11 CLEAN PAVING&SIDEWALKS 22,834 22,834 32 12 16 ASPHALT PAVING - - 0 0 IN PHASE 1A 32 13 73 CONCRETE PAVING JOINT SEALANTS 13,776 9,667 23.443 32 1375 REMOVE STRIPICLEAN PAVING JOINTS 20,204 - 20,204 32 14 00 UNIT PAVING - 0 0 IN PHASE 2&3 32 16 15 BACKFILL CURBS 11,623 11,623 32 17 23 PAVEMENT MARKINGS - 21,421 21,421 3231 00 FENCES&GATES 273,475 273,475 3231 15 CONCRETE SCREEN WALLS&FENCES 113,775 113,775 32 80 00 IRRIGATION - - 152,068 152,068 328010 IRRIGATION SLEEVES 6,189 5,103 - 11,292 32 90 00 LANDSCAPING - - 257,837 257,837 32 90 05 CRUSHED GRANITE 67,572 67,572 3290 10 AERATING FOUNTAIN 0 0 NONE 32 92 00 HYDROMULCH&SOD 0 0 IN 32 90 00 32 95 00 LANDSCAPE MAINTENANCE 24,000 24,000 SUB TOTAL-DIV 32 EXTERIOR IMPROVEMENTS 74,626 14,770 910,148 999,544 33 00 00 SITE UTILITIES - - 0 0 35 00 00 PUNCH LIST 13,683 1,942 - 15,625 SUB TOTAL-DIV 33 UTILITIES 13,683 1,942 0 15,625 SUB TOTAL-COST OF WORK ITEMS 662,278 463,156 11,297,647 12,423,080 CM FEE-2.30% 285,731 SUB TOTAL-PHASE 1 B 12,708,811 PHASE 2 GENERATORS BY CUMMINS 886,126 PHASE 2 SUB TOTAL-PHASE 2 CUMMINS GENERATORS 886,126 SUB TOTAL-PHASE 1 B+PHASE 2 LONG LEAD ITEMS 13,594,937 GMP:PHASE 1B 13,594,937 EXHIBIT 'B' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety &Vehicle Service Center Phases IB PROJECT MANUAL TABLE OF CONTENTS Baytown Public Safety—Phase I—Vehicle Service Center Re-Issued October 15, 2021 BVG4 PROJECT 20004: SPECIFICATIONS—CONSTRUCTION DOCUMENTS FOR PERMITTING June 18, 2021 DIVISION 00: PROCUREMENT AND CONTRACTING REQUIREMENTS 0001 00 TABLE OF CONTENTS 0001 03 PROJECT DIRECTORY 0001 07 PROFESSIONAL SEALS PAGES 0001 15 LIST OF DRAWINGS (Revised in Addendum 3) 0011 00 NOTICE FOR SUBCONTRACTORS PROPOSALS (Durotech) 0021 00 INSTRUCTIONS TO SUBCONTRACTORS (Durotech) 00 21 11 SAMPLE CERTIFICATE OF INSURANCE (Durotech) 0031 32 GEOTECHNICAL DATA GEOTECHNICAL REPORT 00 42 00 SUB PROPOSAL FORMS (Durotech)(Revised in Addendum 3) WAGE RATE REQUIREMENTS (City of Baytown) DIVISION 01: GENERAL REQUIREMENTS 01100 Summary of Work (City of Baytown) 01140 Contractor's Use of Premises (City of Baytown) 01200 Measurement and Payment Procedures (City of Baytown) 01290 Change Order Procedures (City of Baytown) 01310 Coordination and Meetings (City of Baytown) 01350 Submittals (City of Baytown) 01380 Construction Photographs (City of Baytown) 01420 Referenced Standards (City of Baytown) 01430 Contractor's Quality Control (City of Baytown) 01440 Observation Services (City of Baytown) 01450 Testing Laboratory Services (City of Baytown) 01500 Temporary Facilities and Controls (City of Baytown) 01505 Mobilization (City of Baytown) 01550 Stabilized Construction Exits (City of Baytown) 01554 Street Signs (City of Baytown) 01555 Traffic Control and Regulation (City of Baytown) 01560 Filter Fabric Fence (City of Baytown) 01561 Reinforced Filter Fabric Barrier(City of Baytown) 01562 Waste Material Disposal (City of Baytown) 01563 Tree and Plant Protection (City of Baytown) 01564 Control of Ground Water and Surface Water(City of Baytown) 01565 TPDES Requirements (City of Baytown) 01566 Source Controls for Erosion and Sedimentation (City of Baytown) 01570 Trench Safety System (City of Baytown) 01580 Project Identification Signs (City of Baytown) 01580a Project Identification Signs Exhibit(Added in Addendum 2) 01600 Materials and Equipment(City of Baytown) 01630 Product Options and Substitutions (City of Baytown) 9 EXHIBIT 'B' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB PROJECT MANUAL 01720 Field Surveying (City of Baytown) 01750 Starting Systems (City of Baytown) 01760 Project Record Documents (City of Baytown) 01770 Contract Closeout (City of Baytown) 01 21 00 ALLOWANCES 01 2200 UNIT PRICES 01 25 00 SUBSTITUTION PROCEDURES 01 3310 BIM COORDINATION (Durotech) 01 45 00 WINDSTORM CONSTRUCTION REQUIREMENTS (Datum Engineers) 01 45 29 TESTING LABORATORY SERVICES (Datum Engineers) 01 80 00 COMCHECK ENVELOPE REPORT 01 91 13 GENERAL COMMISSIONING REQUIREMENTS(McMacCX) 01 91 14 FUNCTIONAL TESTING REQUIREMENTS(McMacCX) 01 91 15 BUILDING ENCLOSURE COMMISSIONING AND TESTING (McMacCX) DIVISION 02: SITE WORK I EXISTING CONDITIONS 02200 Site Preparation (City of Baytown) 02220 Site Demolition (City of Baytown) 02252 Cement Stabilized Sand (City of Baytown) 02255 Bedding, Backfill, and Embankment Materials (City of Baytown) 02315 Excavation and Backfill for Detention Ponds (City of Baytown) 02316 Excavation and Backfill for Roadways (City of Baytown) 02317 Excavation and Backfill for Structures (City of Baytown) 02318 Excavation and Backfill for Utilities (City of Baytown) 02330 Embankment (City of Baytown) 02335 Subgrade (City of Baytown) 02370 Geotextile (City of Baytown) 02415 Augering Pipe or Casing for Sewers (City of Baytown) 02417 Augering Pipe or Casing for Water Lines (City of Baytown) 02430 Tunnel Grout (City of Baytown) 02510 Water Mains (City of Baytown) 02511 Water Meters (City of Baytown) 02512 Polyethylene Wrap (City of Baytown) 02513 Steel Pipe and Fittings for Large Diameter Water Lines (City of Baytown) 02514 Fire Hydrant Assembly (City of Baytown) 02515 Water Tap and Service Line Installation (City of Baytown) 02520 Valve Boxes, Meter Boxes, and Meter Vaults (City of Baytown) 02530 Gravity Sanitary Sewers (City of Baytown) 02531 Sanitary Sewer Service Leads or Reconnections (City of Baytown) 02532 High Density Polyethylene (HDPE) Solid Wall Pipe (City of Baytown) 02532W High Density Polyethylene (HDPE) Solid Wall Pipe for Water(City of Baytown) 02533 Sanitary Sewage Force Mains (City of Baytown) 02534 PVC Pipe (City of Baytown) 02540 Tapping Sleeves and Valves (City of Baytown) 02541 Water and Wastewater Line Valves (City of Baytown) 02542 Concrete Manholes and Accessories (City of Baytown) 02582 Thermoplastic Pavement Markings (City of Baytown) 02603 Frames, Grates, Rings, and Covers (City of Baytown) 10 EXHIBITS' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB PROJECT MANUAL 02624 Structural Plate Culvert Structures (City of Baytown) 02628 Jacking Pipe or Box (City of Baytown) 02629 Safety End Treatments (City of Baytown) 02630 Storm Sewers (City of Baytown) 02631 Precast Inlets, Headwalls, and Wingwalls (City of Baytown) 02632 Cast-in-Place Inlets, Headwalls, and Wingwalls (City of Baytown) 02633 Adjusting Manholes, Inlets, and Valve Boxes (City of Baytown) 02634 Ductile Iron Pipe and Fittings (City of Baytown) 02635 Steel Pipe and Fittings (City of Baytown) 02636 Polyurethane Coating on Steel or Ductile Iron Pipe (City of Baytown) 02710 Base Course for Pavement(City of Baytown) 02741 Asphaltic Concrete Pavement(City of Baytown) 02742 Prime Coat(City of Baytown) 02743 Tack Coat(City of Baytown) 02744 Single Course Surface Treatment(City of Baytown) 02751 Concrete Pavement (City of Baytown) 02762 Temporary and Removable Reflectorized Pavement Marking (City of Baytown) 02770 Curb, Curb &Gutter, and Headers (City of Baytown) 02771 Concrete Sidewalks (City of Baytown) 02775 Concrete Driveways (City of Baytown) 02811 Landscape Irrigation (City of Baytown) 02821 Chain Link Fences and Gates (City of Baytown) 02910 Topsoil (City of Baytown) 02921 Hydromulch Seeding (City of Baytown) 02922 Sodding (City of Baytown) 02931 Landscape and Tree Planting (City of Baytown) 02980 Pavement Repair and Resurfacing (City of Baytown) 02981 Blast Cleaning of Pavement(City of Baytown) 02985 Fiber Optics (City of Baytown) Fiber Optics Attachment A DIVISION 03: CONCRETE 03100 Formwork (City of Baytown) 03300 Cast In Place Concrete (City of Baytown) 03310 Structural Concrete (City of Baytown) 03600 Structural Grout(City of Baytown) 03 10 00 CONCRETE FORMING AND ACCESSORIES (Datum Engineers) 03 20 00 CONCRETE REINFORCING (Datum Engineers) 03 30 00 CAST-IN-PLACE CONCRETE (Datum Engineers) 03 35 00 CONCRETE FLOOR FINISHING 03 35 43 GROUND AND POLISHED CONCRETE DIVISION 04: MASONRY 04 20 00 UNIT MASONRY DIVISION 05: METALS 05 12 00 STRUCTURAL STEEL FRAMING (Datum Engineers) 0531 13 STEEL FLOOR DECKING AND SHEAR STUDS (Datum Engineers) 11 EXHIBIT 'B' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB PROJECT MANUAL 05 50 00 METAL FABRICATIONS 05 51 00 METAL STAIRS DIVISION 06: WOOD, PLASTICS, AND COMPOSITES 06 10 00 CARPENTRY 0641 16 PLASTIC-LAMINATE-FACED ARCHITECTURAL CABINETS 0661 16 SOLID SURFACING FABRICATIONS DIVISION 07: THERMAL AND MOISTURE PROTECTION 0721 00 THERMAL INSULATION 07 26 00 VAPOR BARRIER 07 27 00 SHEET AIR AND WATER BARRIERS 0741 13 METAL WALL AND ROOF PANELS 07 62 00 SHEET METAL FLASHING AND TRIM 0771 00 ROOF SPECIALTIES 07 92 00 JOINT SEALANTS DIVISION 08: OPENINGS 08 11 13 HOLLOW METAL DOORS AND FRAMES 0831 13 ACCESS DOORS AND PANELS 08 36 00 OVERHEAD DOORS (Revised in Addendum 4) 0841 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS 08 45 23 INSULATED TRANSLUCENT WALL PANELS 0871 00 FINISH HARDWARE (Revised in Addendum 4) 08 80 00 GLAZING 08 91 19 FIXED LOUVERS DIVISION 09: FINISHES 09 23 00 GYPSUM BOARD AND NON-STRUCTURAL FRAMING 09 30 00 TILING 0951 00 ACOUSTICAL CEILINGS 09 65 13 RESILIENT BASE AND ACCESSORIES 09 65 13.23 RESILIENT RUBBER STAIR TREAD WITH RISERS 09 67 23 RESINOUS FLOORING 09 90 00 PAINTING DIVISION 10: SPECIALTIES 10 00 00 MISCELLANEOUS ACCESSORIES 10 14 00 SIGNAGE 10 14 26 POST AND PANEL PYLON SIGNAGE 10 28 00 TOILET AND SHOWER ACCESSORIES 10 44 16 FIRE EXTINGUISHERS 10 70 00 ALUMINUM CANOPY DIVISION 11: EQUIPMENT 11 5224 FLAT SCREEN TV MOUNTS DIVISION 12: FURNISHINGS 12 EXHIBITS' DURO I 'ECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB PROJECT MANUAL 12 24 00 ROLLER SHADES 12 36 61 SIMULATED STONE COUNTERTOPS 12 48 13 ENTRANCE FLOOR MATS AND FRAMES DIVISION 13: SPECIAL CONSTRUCTION 13 34 19 METAL BUILDING SYSTEMS (Datum Engineers) End of Volume 1 Volume 2 DIVISION 20: MECHANICAL SYSTEMS Not Used DIVISION 21: FIRE SUPPRESSION 21 13 13 WET STANDPIPE AND SPRINKLER SYSTEMS (E & C Engineers) DIVISION 22: PLUMBING 22 00 00 PLUMBING PIPING SYSTEMS (E &C Engineers) 22 05 29 HANGERS &SUPPORTS FOR PLUMBING PIPING EQUIPMENT(E&C Engineers) 22 08 00 COMMISSIONING OF PLUMBING (McMacCX) 22 10 00 PLUMBING PIPING VALVES AND ACCESSORIES (E & C Engineers) 22 10 30 PLUMBING SPECIALTIES (E &C Engineers) 221400 ELECTRIC DOMESTIC WATER HEATERS (POINT OF USE) (E&C Engineers) 22 15 00 PLUMBING PUMPS (E &C Engineers) 22 40 00 PLUMBING FIXTURES (E &C Engineers) 22 45 00 EMERGENCY SHOWER AND EYE WASH (E &C Engineers) DIVISION 23: HVAC SYSTEMS 23 00 00 BASIC MECHANICAL REQUIREMENTS (E&C Engineers) 23 05 13 MOTORS (E &C Engineers) 23 05 29 SLEEVES FLASHINGS SUPPORTS AND ANCHORS (E &C Engineers) 23 05 48 VIBRATION ISOLATION (E &C Engineers) 23 05 53 MECHANICAL IDENTIFICATION (E &C Engineers) 23 05 93 TESTING ADJUSTMENT AND BALANCING—(TAB FIRM) (E &C Engineers) 23 05 94 TESTING ADJUSTING AND BALANCING—(CONTRACTOR)(E &C Engineers) 23 07 13 DUCTWORK INSULATION (E& C Engineers) 23 07 19 PIPING INSULATION (E &C Engineers) 23 08 00 COMMISSIONING OF HVAC (McMacCX) 23 08 01 COMMISSIONING OF BUILDING AUTOMATION SYSTEMS (McMacCX) 23 09 23 DIRECT DIGITAL CONTROL SYSTEMS (E & C Engineers) 23 09 93 SEQUENCE OF OPERATIONS (E &C Engineers)(Revised in Addendum 3) 23 29 23 VARIABLE FREQUENCY DRIVES (E &C Engineers) 2331 00 DUCTWORK(E &C Engineers) 23 33 00 DUCTWORK ACCESSORIES (E& C Engineers) 23 34 00 FANS (E &C Engineers) 23 36 00 AIR TERMINAL UNITS (E &C Engineers) 23 37 00 AIR INLETS AND OUTLETS (E&C Engineers) 2341 00 FILTERS (E &C Engineers) 13 EXHIBIT 'B' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB PROJECT MANUAL 23 62 13 AIR-COOLED SPLIT-SYSTEM AIR CONDITIONING UNITS (E & C Engineers) DIVISION 26: ELECTRICAL 26 00 01 ELECTRICAL GENERAL PROVISIONS (E & C Engineers) 26 00 02 ELECTRICAL SCOPE OF WORK(E & C Engineers) 2601 25 ELECTRICAL TESTING (E & C Engineers) 26 05 01 ELECTRICAL BASIC MATERIALS AND METHODS (E & C Engineers) 26 05 19 LOW VOLTAGE CONDUCTORS AND CABLES (E & C Engineers) 26 05 26 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS (E & C Engineers) 26 05 33 ELECTRICAL RACEWAYS (E & C Engineers) 26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS (E & C Engineers) 26 05 73 SHORT CIRCUIT ANALYSIS-COORDINATION STUDY(E & C Engineers) ?6 08 00 COMMISSIONING OF ELECTRICAL SYSTEMS (McMacCX) 26 09 16 ELECTRICAL CONTROLS AND RELAYS (E & C Engineers) 26 09 26 LOW VOLTAGE LIGHTING CONTROL—DIGITAL SENSORS (E &C Engineers) 26 22 00 LOW VOLTAGE TRANSFORMERS (E & C Engineers) 26 24 16 PANELBOARDS (E & C Engineers) 26 25 50 GENERATOR DOCKING STATION (E & C Engineers) 26 27 01 ELECTRICAL SERVICE ENTRANCE (E & C Engineers) 26 27 17 EQUIPMENT WIRING (E & C Engineers) 26 27 18 MISCELLANEOUS ELECTRICAL CONTRLS & CONTROL WIRING (E&C Engineers) 26 27 21 VOICE-DATA SYSTEM PROVISIONS (E & C Engineers) 26 27 23 AUDIO-VISUAL SYSTEM PROVISIONS (E & C Engineers) 26 27 24 SECURITY SYSTEM PROVISIONS (E & C Engineers) 26 27 26 WIRING DEVICES (E & C Engineers) 26 28 13 LOW VOLTAGE FUSES (E & C Engineers) 2628 17 ENCLOSED CIRCUIT BREAKERS (E & C Engineers) 26 28 18 ENCLOSED SWITCHES (E & C Engineers) 26 29 13 ENCLOSED MOTOR CONTROLLERS (E & C Engineers) 26 32 13 STANDBY GENERATOR SETS (E & C Engineers)(Revised in Addendum 3) 26 36 23 AUTOMATIC TRANSFER SWITCHES (E & C Engineers) 2641 13 LIGHTNING PROTECTION FOR STRUCTURES (E & C Engineers) 26 43 13 THOR SYSTEMS MASTER SPD SPECIFICATIONS (E & C Engineers) 2651 00 INTERIOR LIGHTING (E & C Engineers) 26 56 00 EXTERIOR LIGHTING (E & C Engineers) DIVISION 27: COMMUNICATIONS 27 02 00 BASIC MATERIALS AND METHODS (DBR Engineers) 27 05 26 GROUNDING & BONDING FOR COMMUNICATIONS SYSTEMS (DBR Engineers) 27 05 28 PATHWAYS FOR COMMUNICATIONS SYSTEMS (DBR Engineers) 27 05 43 UNDERGROUND DUCTS & RACEWAYS FOR COMM SYSTEMS (DBR Engineers) 2711 00 COMMUNICATIONS EQUIPMENT ROOM FITTINGS (DBR Engineers) 27 13 00 COMMUNICATIONS BACKBONE CABLING (DBR Engineers) 27 15 00 COMMUNICATIONS HORIZONTAL CABLING (DBR Engineers) DIVISION 28: SECURITY SYSTEMS 28 02 00 BASIC MATERIALS AND METHODS FOR SAFETY AND SECURITY SYSTEMS (DBR) 28 10 00 ACCESS CONTROL SYSTEM (DBR Engineers) 14 EXHIBITS' DURC)TECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB PROJECT MANUAL 28 20 00 VIDEO SURVEILLANCE SYSTEM (DBR Engineers) 28 31 03 ADDRESSABLE FIRE ALARM SYSTEM (E & C Engineers) DIVISION 31: EARTHWORK 31 31 16 TERMITE CONTROL 31 63 29 DRILLED PIERS (Datum Engineers) DIVISION 32: EXTERIOR IMPROVEMENTS 32 31 00 STEEL ROLLING GATE SYSTEM 3231 15 CONCRETE SCREEN WALLS AND FENCES 3231 19 ALUMINUM ORNAMENTAL FENCE SYSTEM DIVISION 33: UTILITIES (Not Used) 15 EXHIBIT `C' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety &Vehicle Service Center Phases IB LIST OF DRAWINGS Baytown Public Safety— Phase I—Vehicle Service Center Re-Issued October 15, 2021 BVG4 PROJECT 20004: SPECIFICATIONS—CONSTRUCTION DOCUMENTS FOR PERMITTING June 18, 2021 Section 00 01 15 LIST OF DRAWINGS General G-000 Cover G-001 Sheet List(Revised in Addendum 3) G-002 Symbols, Abbreviations, General Notes G-003 Accessibility Standards G-100 Code Review Sheet G-201 3-Dimensional Building Isometrics G-202 3-Dimensional Building Isometrics Civil C1 Plat (1 of 2) C2 Plat (2 of 2) C3 Topographic Survey (1 of 4) C4 Topographic Survey (2 of 4) C5 Topographic Survey (3 of 4) C6 Topographic Survey (4 of 4) C7 General Notes C8 Overall Demolition Plan C9 Overall Sanitary Sewer Plan C10 Sanitary Sewer Plan (1 of 3) C11 Sanitary Sewer Plan (2 of 3) C12 Sanitary Sewer Plan (3 of 3) C13 Sanitary Sewer Insets C14 Overall Water Distribution Plan C15 Water Distribution Plan (1 of 2) C16 Water Distribution Plan (2 of 2) C17 Overall Storm Sewer Plan C18 Storm Sewer Plan (1 of 3) C19 Storm Sewer Plan (2 of 3) C20 Storm Sewer Plan (3 of 3) C21 Overall Dimension Control and Paving Plan C22 Dimension Control and Paving Plan (1 of 3) C23 Dimension Control and Paving Plan (2 of 3) C24 Dimension Control and Paving Plan (3of 3) C25 Overall Grading Plan C26 Grading Plan (1 of 3) C27 Grading Plan (2 of 3) C28 Grading Plan (3 of 3) C29 Grading Insets C30 Existing Drainage Area Map C31 Proposed Drainage Area Map 16 EXHIBIT 'C' DURUTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB LIST OF DRAWINGS C32 Storm Sewer Calculations C33 Plan and Profile (1 of 9) C34 Plan and Profile (2 of 9) C35 Plan and Profile (3 of 9) C36 Plan and Profile (4 of 9) C37 Plan and Profile (5 of 9) C38 Plan and Profile (6 of 9) C39 Plan and Profile (7 of 9) C40 Plan and Profile (8 of 9) C41 Plan and Profile (9 of 9) C42 Detention Pond Plan and Calculations C43 Stormwater Pollution Plan C44 Stormwater Pollution Details C45 Traffic Control Details C46 Project Specific Details (1 of 2) C47 Project Specific Details (2 of 2) C48 City of Baytown Standard Details (1 of 6) C49 City of Baytown Standard Details (2 of 6) C50 City of Baytown Standard Details (3 of 6) C51 City of Baytown Standard Details (4 of 6) C52 City of Baytown Standard Details (5 of 6) C53 City of Baytown Standard Details (6 of 6) C54 Proctor Road Plan and Profile C55 Proctor Road Grading Plan and Typical Cross Section C56 Proctor Road Drainage Area Map and Calculations Landscape L1 Overall Landscape Plan L2 Landscape Plan (1 of 4) L3 Landscape Plan (2 of 4) L4 Landscape Plan (3 of 4) L5 Landscape Plan (4 of 4) L6 Amenity Landscape Plan L7 Landscape Schedule and Requirements L8 Landscape Details L9 Landscape Specifications Irrigation IR1 Overall Irrigation Plan IR2 Irrigation Plan (1 of 5) IR3 Irrigation Plan (2 of 5) IR4 Irrigation Plan (3 of 5) IR5 Irrigation Plan (4 of 5) IR6 Irrigation Plan (5 of 5) IR7 Irrigation Details and Specifications Structural 17 EXHIBIT `C' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB LIST OF DRAWINGS S-001 Typical Abbreviations, Symbols and Plan Notes (Revised in Addendum 2) S-002 General Notes S-003 Required Special Inspections S-201 Building S and T S-202 Building U, V, W and X (Revised in Addendum 2) S-301 Typical Expansive Clay Soil and Belled Pier Details S-302 Typical Slab-On-Grade Details (Revised in Addendum 2) S-303 Typical Concrete Foundation Details S-310 Concrete Section and Details 'Revised in Addendum 2) S-401 Simple Beam Connection Details S-402 Composite Steel Beam Details S-403 Typical Steel Details S-501 Typical Masonry Details Architectural A-001 Site Plan—Overall A-011 Site Plan —Phase 1 A-012 Site Plan Details A-013 Site Plan Details A-101 Floor Plans Building T—Maintenance A-102 Floor Plans Storage Buildings U, V, W &X A-141 Wall Types A-161 Reflected Ceiling Plans—Building T A-162 Reflected Ceiling Plans—Buildings U, V, W&X A-181 Roof Plan Buildings S &T A-182 Roof Plan Buildings U, V, W& X A-201 Exterior Building Elevations Buildings S &T A-202 Exterior Elevations Buildings U, V, W &X A-301 Building Sections—Buildings S & T A-302 Building Sections—Buildings U, V, W & X A-401 Wall Sections - Building T A-402 Wall Sections - Buildings U, V, W & X A-403 Stair Section & Details A-451 Section Details A-452 Plan Details A-501 Window & Storefront Elevations A-601 Door Schedule & Details Interior Design ID-101 Finish Floor Plans Building T ID-102 Finish Floor Plans Buildings U, V, W&X ID-161 FF&E Equipment Plan (Revised in Addendum 3) ID-162 FF&E Equipment Plan Buildings U, V,W&X ID-201 Interior Elevations (Revised in Addendum 1) ID-202 Interior Elevations ID-401 Millwork Details (Revised in Addendum 1) 18 EXHIBIT 'C' DURO-FECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB LIST OF DRAWINGS Mechanical M-000 Mechanical Abbreviations and Symbols M-201 Mechanical Floor Plan Level 1 —Buildings U, V, W&X M-202 Mechanical Floor Plan Level 1 —Buildings S &T M-203 Mechanical Floor Plan Level 1 —Building T M-204 Mechanical Floor Plan Mezzanine—Building T M-205 Mechanical Roof Plan Building U,V,W&X M-206 Mechanical Roof Plan Building T M-207 Mechanical Roof Plan Building T M-301 Mechanical Piping Plan Level 1 —Buildings U, V, W& X M-302 Mechanical Piping Plan Level 1 —Buildings S &T M-303 Mechanical Piping Plan Level 1 —Building T M-304 Mechanical Piping Plan Mezzanine—Building T M-501 Mechanical Details M-502 Mechanical Details M-503 Mechanical Details M-701 Mechanical Controls Diagrams M-702 Mechanical Controls Diagrams M-801 Mechanical Schedules M-802 Mechanical Schedules Electrical E-000 Electrical Abbreviations and Symbols E-010 Electrical Site Plan E-201 Electrical Lighting Plan Level 1 —Buildings U, V, W&X E-202 Electrical Lighting Plan Level 1 —Buildings S &T E-203 Electrical Lighting Plan Level 1 —Building T E-204 Electrical Lighting Plan Mezzanine—Building T E-301 Electrical Power Plan Level 1 —Buildings U, V, W&X E-302 Electrical Power Plan Level 1 —Buildings S &T (Revised in Addendum 3) E-303 Electrical Power Plan Level 1 —Building T (Revised in Addendum 3) E-304 Electrical Power Plan Mezzanine—Building T E-401 Electrical Power Mechanical Plan—Building U E-402 Electrical Power Mechanical Roof Plan—Buildings U, V&X E-403 Electrical Power Mechanical Level 1 Plan—Building T E-404 Electrical Power Mechanical Mezzanine Plan—Building T E-405 Electrical Power Mechanical Roof Plan—Building T E-406 Electrical Power Mechanical Roof Plan—Building T E-407 Electrical Power Mechanical Roof Plan—Building T E-501 Electrical Fire Alarm Plan Level 1 —Buildings U, V, W&X E-502 Electrical Fire Alarm Plan Level 1 —Building T E-503 Electrical Fire Alarm Plan Level 1 —Building T E-504 Electrical Fire Alarm Plan Mezzanine—Building T E-701 Electrical Details E-801 Electrical Riser Diagrams (Revised in Addendum 3) E-901 Electrical Schedules E-902 Electrical Schedules (Revised in Addendum 3) E-903 Electrical Schedules (Revised in Addendum 3) 19 EXHIBIT 'C' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB LIST OF DRAWINGS Plumbing P-000 Plumbing Abbreviations and Symbols P-010 Plumbing Overall Site Plan— Natural Gas Distribution P-011 Plumbing Site Plan P-101 Plumbing Underfloor Floor Plan Level 1 — Buildings U, V, W&X P-102 Plumbing Underfloor Floor Plan Level 1 — Buildings S &T (Revised in Addendum 1) P-103 Plumbing Underfloor Floor Plan Level 1 — Building T P-201 Plumbing Floor Plan Level 1 —Buildings U, V& X P-202 Plumbing Floor Plan Level 1 & Mezzanine— Building T P-203 Plumbing Floor Plan Level 1 — Building T P-301 Plumbing Roof Plan— Buildings S & T P-302 Plumbing Roof Plan—Buildings U, V, W&X P-401 Plumbing Enlarged Plans (Revised in Addendum 1) P-501 Plumbing Underfloor Riser Area A P-502 Plumbing Underfloor Riser Area B &C P-503 Plumbing Underfloor Riser Buildings U, V& X P-504 Plumbing Water Riser Buildings U, V & X P-505 Plumbing Water Riser Building T Area A & C P-506 Plumbing Water Riser Building T Area B P-601 Plumbing Details P-701 Plumbing Schedules Technology T-001 Low Voltage Symbol Legend T-101 Technology Site Plan T-111 Composite Level 1 Technology Routing Plan T-201 1st Level Technology Floor Plan—Maintenance Building T T-202 Technology Plans Storage Buildings U, V, W & X, T Mezzanine T-301 Technology Enlarged Plans T-302 Network Enclosure Elevations T-601 Technology Details T-602 Security Details T-603 Security Door Details T-604 Security Door Details T-605 Security Gate Details T-606 Fiber Riser Diagram END OF SECTION 20 EXHIBIT `D' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety & Vehicle Service Center Phases IB LIST OF ADDENDA 1. Addendum No. 1 Issued on October 22, 2021 2. Addendum No. 2 Issued on November 5, 2021 3. Addendum No. 3 Issued on November 12, 2021 4. Addendum No.4 Issued on November 16, 2021 5. Addendum No. 5 Issued on November 22, 2021 21 EXHIBIT 'E' DURUTECH BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS DIVISION 00— PROCUREMENT AND CONTRACTING REQUIREMENTS 1. Excluded is Material Testing. 2. Excluded are Utility Assessment, Inspection Fees, Impact Fees, and Tap Fees. 3. Utility Company agreements (terms and conditions), easements and coordination which will serve as the termination point for Durotech to make connections for building service shall be the responsibility of the Owner and Design Team (Architect/MEP Engineer). Durotech will assist the Owner and Design Team in coordinating the activities with the Utility Company(s). 4. All required utility providers (water, sewer, storm discharge point, electric, gas, fiber, phone lines) are the responsibility of the owner to coordinate and execute necessary agreements so that the utilities are installed per the contractor's schedule for construction usage and systems startup. 5. We assume that there will be adequate water supply with sufficient pressure available for the proper functioning of Fire Sprinkler system and other systems. 6. Excluded are any Building Permit fees. Permit Fee costs to be by Owner. 7. Without regard to any other provision of this Agreement, Owner shall be liable to Contractor for additional costs incurred by Contractor as the result of any applicable state or local sales, excise, or use tax, governmental payroll tax or healthcare tax if the tax is applicable to the Project, the Project is not tax exempt from the specific tax and the tax became effective after the date of execution of the Contract. 8. Electronic Files and CAD Files will be provided by the Architect/Engineer of record for the purpose of preparing shop drawings and 3D models at no cost to the General Contractor and/or Subcontractors. A signed release will be submitted to the Architect/Engineer before electronic files are released by the Architect/Engineer. 9. Excluded are unforeseen underground conditions or obstructions not indicated in contract documents. 10. Owner and Contractor agree that all manufacturer's warranties, and subcontractor's warranties which extend beyond Contractor's warranty period, are hereby assigned to and run directly from the manufacturer to the 22 EXHIBIT 'E' ') U ROTEC H BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS Owner and from the subcontractor to the Owner, respectively. Owner accepts these assignments and warranties, and releases and discharges Contractor from any and all claims, liabilities, damages, costs and expenses arising out of such manufacturer's warranties and any subcontractor's extended warranties. 11. The Contractor's warranty excludes remedy for damage or defect caused by abuse, material alteration to the work not executed by the Contractor, insufficient maintenance, or maintenance not in compliance with manufacturer's written recommendations. 12. Payment and Performance Bonds will be charged to the Owner based on the State of Texas regulated rate. 13. The Guaranteed Maximum Price provided is a not to exceed amount for the Cumulative Baytown Public Safety project. Phase 1A $4,905,614 Phase 1 B & Phase 2 Generators $13,594,937 Total Phase 1 GMP $18,500,551 Individual line items within the project budget and earlier or later phase packages are not individual Guaranteed Maximum Price amounts. 14. The GMP package is valid until January 14, 2022. The Owner will issue a Notice to Proceed and sign the GMP Amendment on or before the stated date. 15. Bids were solicited as a combination package for Phases 113, 2, and 3 to maximize overall cost savings. Therefore, the Guaranteed Maximum Price for Phase 1 B is contingent upon the approval of the Guaranteed Maximum Price for Phases 2 and 3 to be submitted and approved at the January 27tn 2022 City Council meeting. 16. Durotech, Inc reserves the right to review the Issued for Construction documents to confirm that changes to the Contract Documents referenced in this proposal are consistent with the changes proposed during the Cost Savings process. 17. The proposed cost saving recommendations by Durotech, Inc. shall be subject to the review and approval of the Architect, Owner, and the Owner's Professional Consultants. Durotech, Inc. is not required to ascertain that the cost savings are in accordance with applicable laws, statutes, 23 EXHIBIT 'E' DURO' TECH BUILDERS OF INTEGRITY Baytown Public Safety— Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS ordinances, codes, rules and regulations, or lawful orders of public authorities. The Contractors review of the proposed cost savings is in the capacity as a Construction Manager and not as a Design Professional. 18. For any delays caused by events outside of Contractor's control, including but not limited to Acts of God, pandemics, epidemics, acts of governmental authorities, acts of civil authorities, acts of war or terrorism, unanticipated material shortages and price escalations, labor disputes and utilities delays, Owner shall grant additional time extensions and price increases to Contractor when properly documented, substantiated and approved by Owner, subject to Contractor's right to dispute Owner's decision under the claims procedures of the Contract 19. Stipulated Billing Rates: No. Description Rate 1 General Contract amount per Liability/Umbrella thousand x $7.75 Insurance 2 Builder's Risk Contract Insurance amount/hundred x 0.05412 x # of months 3 Project $115.00 per hour Executive 4 Project Manager $76.00 per hour 5 Estimator $55.00 per hour 6 Safety/Field $101.00 per hour Operation Manage 7 Lead $79.00 per hour Su erintendent 8 Assistant $48.00 per hour Superintendent 9 Project Engineer $41.00 per hour 10 Quality Control $69.00 per hour Inspector 11 Contract $33.00 per hour Administrator 24 EXHIBIT 'E' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS &ASSUMPTIONS 12 Preconstruction $97.00 per hour Manager 13 Quality Control $69.00 per hour Manager 14 BIM Coordinator $55.00 per hour 15 IT Coordinator $95.00 per hour 16 Intern $25.00 per hour 17 Labor Burden 42.5% Labor Rates: Per Hour Semi-skilled Labor $27.00 Skilled Labor $30.00 Foreman/Operator $38.00 20. Billable rates will be subject to audit for hours worked only. DIVISION 01 — GENERAL REQUIREMENTS 21. Section 01140 — Contractor's Use of Premises: Excluded is paragraph 1.5.A. 22. Section 01564 — Control of Ground Water and Surface Water: Excluded is any ground water control systems, well-point systems, eductor and ejector- type systems, deep wells, and piezometers or monitoring wells. 23. Section 01 21 00 —Allowances: Excluded are the following: Para 1.05.13 — Entire paragraph Para 1.06.E — Last sentence "These costs include delivery, installation, insurance, equipment rental, and similar costs". 24. Section 01 21 00 — Allowances: The Construction Contingency Allowance will be used jointly for the Owner's and Construction Manager's purposes. DIVISION 02— SITEWORK/EXISTING CONDITIONS DIVISION 03— CONCRETE 25. Section 03100 — Concrete Formwork: Excluded are any corrugated fiberboard carton forms as mentioned in paragraph 2.01.1 and 3.01.J. 25 EXHIBITS D U ROTEC H BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS 26. Section 03300 — Cast-In-Place Concrete: Excluded are any corrugated fiberboard carton forms as mentioned in paragraph 2.06.1 and 3.04.J. 27. Section 03 35 43 — Polished Concrete: Excluded is any `Dye' as mentioned in paragraph 2.03.0 and 3.03.G. DIVISION 04— MASONRY DIVISION 05— METALS 28. Section 05 12 00 — Structural Steel Framing: a] Excluded is any galvanized cooling tower grillage as mentioned in paragraph 1.02.A.1. b] Excluded is any survey work by a licensed professional engineer or public surveyor as mentioned in paragraph 3.02.A. 29. Section 05 31 13 — Steel Floor Decking and Shear Studs: Excluded is paragraph 2.05.A. There is no sprayed fireproofing in this project. 30. Excluded is any galvanizing of structural steel members in enclosed unconditioned space areas of the building. DIVISION 06— WOOD, PLASTICS, AND COMPOSITES 31. Section 06 41 16 — Plastic Laminate-Faced Architectural Cabinets: Excluded is paragraph 1.02.A.4 — Magnetic dry erase plastic laminate panels and paragraph 2.10 — Plastic Laminate Magnetic Marker Board. 32. Section 06 61 16 — Solid Surfacing Fabrications: a] Excluded are any solid surface shower panels as mentioned in paragraph 1.01.A.2 and 2.01.B. b] Excluded are any solid surface shower panels noted as H1, H2 and H3 on the architectural drawings. DIVISION 07— THERMAL AND MOISTURE PROTECTION 33. Section 07 21 00 — Thermal Insulation: a] Excluded is any rigid board insulation or spray-in-place foam insulation. b] Included is the following at Building T, U, V & X Building T Primary Roof Insulation 2 Layer— R-30 (19+11) simple Saver System (6 inches + 3.8 inches) 25,869 SF Primary Wall Insulation 26 EXHIBIT 'E' D U Ro rECH BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS 1 Layer—R-25 Simple Saver System (8 inches) 17,421 SF 1 Layer—R-19 Simple Saver System (6 inches) 7,257 SF Building U Primary Roof Insulation 2 Layer—R-30 (19+11)simple Saver System (6 inches + 3.8 inches) 8,890 SF Primary Wall Insulation 1 Layer— R-25 Simple Saver System (8 inches) 4,107 SF 1 Layer— R-19 Simple Saver System (6 inches) 9,311 SF Building V Primary Roof Insulation 2 Layer— R-30 (19+11)simple Saver System (6 inches + 3.8 inches) 3,410 SF Primary Wall Insulation 1 Layer— R-13 Simple Saver System (4.4 inches) 5,568 SF Building X Primary Roof Insulation 2 Layer—R-30 (19+11)simple Saver System (6 inches +3.8 inches) 788 SF Primary Wall Insulation 1 Layer— R-13 Simple Saver System (4.4 inches) 2,533 SF c] Included is 2" polyisocyanu rate board insulation and dampproofing at exterior sheathing walls in Building T (Grid Line 8-10/13-D and Grid Line 8-10/G-N). 34. Included is the following under the metal roof panels at Building T (Grid Line 8-10/13-1) and Grid Line 8-10/G-N): a] Loose lay 2 layers of 2.6 polyisocyan u rate insulation (R-30) to metal deck. b] Mechanically attach 3/" exterior grade plywood (non-fire rated). c] Fully adhere new self-adhering peel and stick underlayment. 35. Section 07 27 00 — Sheet Air and Water Barriers: Excluded is this section in its entirety. 36. Section 07 41 13 — Metal Roof and Wall Panels: Excluded is this section in its entirety. 27 EXHIBIT 'E' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS DIVISION 08— OPENINGS 37. Section 08 11 13 — Hollow Metal Doors & Frames: Included are Hollow Metal Frames as manufactured by Pearland Industries or Door Pro Systems. 38. Section 08 45 23 — Insulated Translucent Wall Panels: a] Excluded are any requirements related to Texas Department of Insurance. DIVISION 09— FINISHES 39. Section 09 23 00— Gypsum Board and Non-Structural Framing: a] Excluded is paragraph 2.09.0 — Isolation strip at exterior walls. 40. Section 09 30 00 — Tiling: Excluded is epoxy grout. Specifications require standard grout unless otherwise indicated. The drawings do not indicate epoxy grout. 41. Section 09 65 13.23 — Resilient Rubber Stair Treads with Risers: Excluded is this section in its entirety. DIVISION 10— SPECIALTIES 42. Section 10 00 00— Miscellaneous Accessories: Included is the labor only to install the Bulletin Board furnished by the Owner. 43. Section 10 14 00 — Signage: a] Included is an allowance of$25,000 for Signage. b] Excluded is paragraph 3.03.13 — Client Logo Signage. 44. Section 10 14 26 — Post and Panel Pylon Signage: Excluded is this section in its entirety. 45. Excluded are any Knox Boxes in Phase 1 B. 46. Section 10 70 00 — Aluminum Canopy: Included are Aluminum Canopies for Building `S' and Building 'W' as manufactured by Avadek. The finish of the aluminum canopy will be clear anodized. DIVISION 11— EQUIPMENT 47, Section 11 52 24 — Flat Screen TV Mounts: Included is the labor only to install the Flat Screen TV Mounts furnished by the Owner. 28 EXHIBIT 'E' ) UROTECH BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS DIVISION 12— FURNISHINGS DIVISION 13— SPECIAL CONSTRUCTION 48. Section 13 34 19 — Metal Building Systems a] The Pre-Engineered Metal Building will be designed and fabricated by Alliance Steel Building Systems. b] Design Information Building Code: IBC 2015 Collateral Load: Per Drawings Wind Load: 160 MPH Seismic Imp. Factor: 1.50 Live Load (Roof): 20 PSF Deflections: Per Specifications Wind Exp. Factor: C Snow Imp. Factor: 1.20 Reducible Live Load: Yes Snow Load (Ground): 0 PSF Seismic (Ss) 0.070 (SI) 0.040 Wind Imp. Factor: Risk IV c] Roof& Wall Material Finish Profile Roof Panel 24 gauge Fluropon/Kynar Alliance Seam 24 Wall Panel 24 gauge Fluropon/Kynar LT3.3 Wall Liner 26 gauge Std Weather X PBM Trim 26 gauge Fluropon/Kynar Gutter& Downspouts Liner Trim 24 gauge Std Weather X Liner Trim d] Excluded is all ceiling liner panel in Buildings T, U, V and X. e] Included is interior wall liner panel up to a height of 14' 0" AFF in Building T. f] Included is interior wall liner panel up to a height of 8' 0" AFF in Building U, V and X. g] All interior liner panel to be 26 gauge, PBM "WXL" finish. h] All exterior wall liner panel to be 24-gauge, Vertical LT3.3, Kynar finish. 29 EXHIBIT `E' D U ROTEC H BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B — Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS i] Included is partition wall framing above 10' 0" AFF along gridline 15/16 in Building T. j] Furnish 22 ga, PBM, White at roof at Deck of Storage area in building T. k] Remove wall girts and provide wind girt at Breakroom and Storage area in Building T. 1] Roof panels to be 24 gauge, "standard Alliance Kynar colors", UL90 rated, Alliance Seam 24 standing seam panels with concealed clips and fasteners. All roof panels to be "machine seamed" at sidelaps as specified. m] Interior wall liner to be 26 gauge, "standard Alliance Kynar colors", "PBM", single-skin panels with exposed fasteners to be installed at the Apparatus Bays, Storage, Vehicle Bays, Dive / Bomb Team, Trailers, and the Enclosed Bay of the Auto Theft. n] Soffit at the below eave canopies to be 24 gauge, "standard Alliance Kynar colors", "A-12" single-skin panels with concealed fasteners to be installed over pre-engineered framing components as provided by Alliance. o] All standard building trim, eave gutter and downspouts to be 26 gauge, "standard Alliance Kynar colors". p] Alliance to provide metal building column reactions and anchor bolt settings for foundation and footing design by Structural Engineer. q] Welding of shop connections shall be in accordance with the AWS D1.1 standard code for"Structural Welding Code—Steel" (welding in building construction) and AWS D1.3 "Structural Welding Code— Sheet Metal" as directed and certified by AISC and the Alliance Steel Engineering Department requirements. An independent testing laboratory has previously certified welders and the welding process. Alliance is an IAS accredited facility. r] All exposed framing at the Wash Bay, Porch Area of Breakroom, and Auto Theft / Bays are to be hot-dipped galvanized. s] All metal building primary and secondary framing members to be provided with Alliance standard red-oxide primer coating, which meets or exceeds Federal Specification TT-P-636c. t] Included is Alliance Steel standard, 20-year roof weather tightness warranty requirement DIVISION 21 — FIRE SUPPRESSION DIVISION 22— PLUMBING 30 EXHIBIT 'E' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center QUALIFICATIONS & ASSUMPTIONS 49. Section 22 40 00 — Plumbing Fixtures: Included are the Owner requested Water Closets (WC-1) in lieu of specified model. Bowl to be Model #4326- 96 and Tank to be Model #19042-96. 50. Trench Drains: Included are East Jordan Iron Works frame and grate trench drains at Auto Shop in lieu of specified products. Grate to be Model # 6906M2 and Trench Rail to be Model # 6900Z2. DIVISION 23— HVAC 51. Section 23 31 00 — Ductwork: Excluded is paragraph 3.05.A requiring duct cleaning. Duct ends will be covered during construction phase to prevent contamination by dirt and/or debris. DIVISION 26— ELECTRICAL 52. Included are aluminum conductors in lieu of copper conductors for 1/0 and larger feeders. DIVISION 27— COMMUNICATIONS 53. Excluded are any Network Switches or UPS devices. These will be provided by the Owner. DIVISION 28—ELECTRONIC SAFETY& SECURITY DIVISION 31 — EARTHWORK 54. Section 31 63 29 — Drilled Piers: Excluded is any casing or slurry drilling of piers. 55. Excluded is any drying of subgrade by chemical or mechanical means. DIVISION 32— EXTERIOR IMPROVEMENTS 56. Areas that receive Hydromulch will not be warranted for developing full turf grass. Owner understands that Hydromulch is a 2-season maintenance program requiring continuous maintenance including watering and fertilizer by the Owner. Areas that are not irrigated will not be warranted for grass or plant development and sustainability. Any temporary irrigation requirement by the contract will only be warranted to such date the temporary irrigation is removed. DIVISION 33— UTILITIES 31 EXHIBIT `F' DUROTECH BUILDEaRS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center ALLOWANCE SCHEDULE 1. Construction Contingency Allowance $300,000 2. Signage $25,000 32 EXHIBIT `G' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety— Phase 1 B —Vehicle Service Center SELF PERFORMED WORK ITEMS The following scope items will be self-performed by Durotech, Inc. and will be billed against the contract based upon the proposal submitted to and accepted by the owner and will be treated as a lump sum sub- contract amount. No. Description of Scope Amount 1 OFCI Items (L) $1,625 2 Miscellaneous Steel (L) $58,058 3 Safety Rails (L &M) $3,282 4 Rough Carpentry(L & M) $34,901 5 Unload &distribute Metal Doors & Frames (L) $11,012 6 Unload &distribute PLAM Doors (L) N/A 7 Install Access Doors (L& M) $1,028 8 Unload &distribute Door Hardware(L) $3,206 9 Install Louvers (L) $2,138 10 Floor Preparation (L & M) $15,552 11 Floor Protection (L& M) $6,010 12 Install Knox Box (L & M) N/A 13 Install Residential Appliances (L) $1,496 14 Final Grading (L) $50,367 15 Haul off spoils (L) $98,834 16 Remove strip/clean paving joints (L) $20,204 17 Backfill curbs (L) $11,623 18 Install Irrigation Sleeves (L & M) $11,292 TOTAL $330,627 33 EXHIBIT 'H' DURO' TEC BUILDERS OF INTEGRITY Baytown Public Safety — Phase 1 B —Vehicle Service Center UNIT PRICES A] UNIT PRICE NO. 1: N/A B] UNIT PRICE NO. 2: N/A C] UNIT PRICE NO. 3: Unit Price per linear foot for piers longer or shorter than base lengths Pier P1: 24/72 Add: $60.00/LF Deduct: $51.00/1-F Pier P2: 30/90 Add: $93.92/LF Deduct: $79.83/1-F Pier P3: 18/48 Add: $33.69/1-F Deduct: $28.63/LF Description: Unit prices shall include all labor, materials, equipment, overhead and fee for drilled piers complete. Adjustments to Contract shall be based on total linear feet of each pier size greater than or less than the sum of base lengths of each size. C] UNIT PRICE NO. 4: Unit Price per linear foot for Casing of Piers Pier P1: 24" Add: $27.10/1-F Pier P2: 30" Add: $37.60/1-F Pier P3: 18" Add: $17.20/1-F Description: Unit prices shall include all labor, materials, equipment, overhead and fee for casing of drilled piers complete. D] UNIT PRICE NO. 4: Unit Price per linear foot for Straight Shaft piers Convert Pier P1: 24/72 to Straight Shaft 72" dia Add: $178.23/LF Convert Pier P2: 30/90 to Straight Shaft 90" dia Add: $264.15/LF Convert Pier P3: 18/48 to straight Shaft 48" dia Add: $81.92/1-F Description: Unit prices shall include all labor, materials, equipment, overhead and fee for drilling of straight shaft piers complete. E] UNIT PRICE NO. 5: N/A F] UNIT PRICE NO. 6: N/A G] UNIT PRICE NO. 7: Additional Concrete Placement: If additional concrete is required and approved by the Project Engineer, the following unit prices shall be used in adjusting the Contract Price. 1. Grade Beams, price per cu. yd. $356.62/CY 2. Slab on grade, price per cu. yd. $291.47/CY 3. Normal weight concrete slab over metal deck, price per cu. yd. $303.16/CY 4. Light weight concrete slab over metal deck, price per cu. yd. $228.17/CY H] UNIT PRICE NO. 8: Site Concrete Placement The price includes subgrade prep, reinforcing steel, concrete, and labor. 34 EXHIBIT 'H' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety— Phase 1 B —Vehicle Service Center UNIT PRICES 1. 8" concrete paving Add: $204.85/CY Deduct: $174.12/CY 2. 6" concrete paving Add: $219.00/CY Deduct: $186.15/CY 3. 4.5" concrete sidewalk Add: $404.50/CY Deduct: $343.82/CY 35 EXHIBIT `I' DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety-Phase 1 B-Vehicle Service Center COST SAVING ITEMS The following Cost Savings Items have been incorporated into the Guaranteed Maximum Price Proposal. This list is included for information purposes only. DESCRIPTION ACCEPTED 3 CONCRETE 1 Delete rolled or mountable curb at crushed granite trail as shown in detail 07/C-45. $ (24,273) 6711PPENINGS Section 08 36 00-Overhead Doors:Provide the following doors as outlined below:(refer to the attached drawing sheet(pdf). a)Type A Doors:3728,R-18.4,2"Electric Motor, 100,000 cycles(t2la,1:21 b,t22a,t22b,t23a, t23b,t24a,t24b,t5l a,t5l b,t52a,t52b,t53a,t53b,t54a,t54b) b]Type B Doors:3728,R-18.4,2",Manual Operation,25,000 cycles(t30,t34b,t35b,t39b) 1 c)Type C Doors:3718,R-16.2, 1 3/4",Manual Operation,25,000 cycles(1:61a,t6lb,t62a,t62b, $ (264,077) t63a,t63b,u01a,u01b,u02a,u02b,u03a,u03b,u04a,u04b,u05a,u05b,u06a,u06b,u07a, u09a,u09b,u10a,ul0b,v01a,v02,v03,v04,v05,v06a,x01a,x01b) d]Provide standard door finish in lieu of the optional finish Color Blast(as specified in Para 2.02.A.14.b.1).Standard Door Color Options:white,almond,desert tan,sandstone,bronze, chocolate,mocha brown,gray&charcoal 9; FINISHES (35,713) 1 Use Daltile(2"x 2")Reminiscent for Shower Floor Tile and Daltile(12"x 24")Reminiscent $ (35,713) (Shower Wall Tile)in lieu of Solid Surfacing Fabrications(Swanstone panels)as shown. 13 SPECIAL CONSTRUCT/O_N 1 Section 13 34 19-Pre-Engineered Metal Building Frame a Delete ceiling liner panel in Building U $ (9,972) b Delete ceiling liner panel in Building V $ (3,763) c Delete ceiling liner panel in Building X $ (3,552) 22 PLUMBING Use Vehicle Trench Drain(TD-1)as manufactured by EJ Co.(Model 6906M2 20"x 24"Trench 1 Grate,Heavy Duty;Model 6900Z2 Trench Rail)in lieu of as specified(Dura Trench Model $ (87,517) DTPF18-HDSS15ZSA 8'x 18") 2 WC-1:Use'Persuade Cury Comfort Height'(Model K-75790-96)as manufactured by Kohler in $ (3,100) lieu of as specified. 3 Use Pex for water line piping $ (10,600) 26 ELECTRICAL 1 Provide 750kW natural gas generator in lieu of 1000kW and 1200 Amp ATS in lieu of 1600 Amp. $ (105,732) 2 Delete UPS-1 (Note#8/E-303). $ (57,500) 36 EXHIBIT T DUROTECH BUILDERS OF INTEGRITY Baytown Public Safety-Phase 1 B-Vehicle Service Center COST SAVING ITEMS Section 08 36 00-Overhead Doors:Provide the following doors as manual chain hoist in lieu of motorized as specified: Building T:t6la,t6lb,t62a,t62b,t63a,t63b(6 Doors) 3 Building U:u01a,u01b,u02a,u02b,u03a,u03b, u04a,u04b,u05a,u05b,u06a,u06b,u07a, $ (17,660) u09a,u09b,ul0a,ul0b(All 17 doors) Building V:v01a,v02,v03,v04,v05,v06a(All 6 doors) Building X:x01a,x01b(All 2 doors) Delete conduit,back boxes,rough-ins and wiring for the doors listed above. Delete 1"conduit underground for Fire Alarm Cabling routed to Building U,V and X per Note 4 #1/E-010. $ (6,000) Delete any conduit,back-boxes and rough-ins inside the buildings(U,V and X)related to the Fire Alarms stem scope. 5 Use aluminum conductors in lieu of copper 1/0 and larger $ (119,000) 6 Reduce innerduct to(1)per conduit in lieu of(2) $ (13,500) 7 MC for device drops in lieu of conduit $ (1,000) 8 Use minimum 1/2"conduit in lieu of 3/4" $ (3,500) 28. ELECTRONICSAFETYAI'ND 5OWRITY F. (18,417) 1 Deduct for not providing spare parts(Section 28 10 00-Para 1.07.B.1;Section 28 20 00-Para $ (g 000) 1.05.B.1 2 Delete Fire Alarm System in Buildings U,V and X. $ (9,417) 32 EXTERIOR IMPROIIEENTS. _ (83,180) 1 Provide 8'H galvanized chain link fence with barbed wire in lieu of Precast Concrete Fence $ (93,939) Panels. 2 Add concrete sloped paving at detention pond $ 10,759 33 UTILITIES. _ (27,548) . 1 Reduce the length of concrete pilot channel $ (27,548) SUB TOTAL $ (895,604) Total-Cost Saving Items $ (895,604) 37