BAWA Resolution No. 2009-06 RESOLUTION NO.2009-06
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE BAYTOWN AREA
WATER AUTHORITY ACCEPTING THE BAWA 30-INCH WATER
TRANSMISSION LINE PROJECT:AUTHORIZING FINAL PAYMENT IN THE
AMOUNT OF SIX I IUNDRED NINETY-EIGHT THOUSAND SIX HUNDRED
EIGHTY-ONE AND 35/100 DOLLARS($698,681.35)TO REYTEC
CONSTRUCTION RESOURCES.INC..SUBJECT TO CERTAIN STIPULATED
TERMS AND CONDITIONS:AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
WHEREAS.all of the said improvements,as provided in the plans and specifications
heretofore prepared by BAWA's engineer have been performed and completed in full accordance
with all of the terms and conditions of the contract for construction of the BAWA 30-inch Water
Transmission Line Project:and
WHEREAS,the BAWA's engineer in the manner provided by the terms of the said contract
and the plans and specifications thereof.has approved and accepted the BAWA 30-inch Water
Transmission Line Project,has heretofore issued his Certificate of Final Acceptance,has certified
same to the Board of Directors of the Baytown Area Water Authority,and has recommended that it
accept and receive said work and improvements as constructed and completed by Contractor:and
WHEREAS,BAWA has withheld the sum of FOUR HUNDRED SEVENTY-THREE
THOUSAND SIX HUNDRED EIGI ITY-ONE AND 35/100 DOLLARS($473,681.35)in retainage;
and
WHEREAS.there is a dispute regarding the design of the project.appropriate liquidated
damages and work performed by Reytec Construction Resources,Inc.:and
WHEREAS.mindful of the cost and expense associated with litigation,Reytec Construction
Resources.Inc.,has agreed to compromise,settle,and waive certain claims without admitting or
conceding any matter:NOW THEREFORE
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE BAYTOWN AREA
WATER AUTHORITY:
Section 1:That the Board of Directors of the Baytown Area Water Authority hereby
accepts and approves the above-described work and improvements,and finds and determines that all
of said improvements have been completed as provided in the plans and specifications thereof.and
in full accordance with all of the terms and provisions of the aforesaid contract.
Section 2:That the Certificate of Final Acceptance heretofore issued by BAWA's
engineer and certified to the Board of Directors is hereby accepted and received.
Section 3:That subject to a release and settlement agreement containing terms and
conditions acceptable to BAWA's General Manager and General Counsel,payment to Reytec
Construction Resources,Inc.,in the amount of SIX HUNDRED NINETY-EIGHT THOUSAND
SIX HUNDRED EIGHTY-ONE AND 35/100 DOLLARS($698,681.35)is hereby authorized.
Section 4:This resolution shall take effect immediately Gom and after its passage by the
Board of Directors of the Baytown Area Water Authority.
INTRODUCED.READ and PASSED,by the affirmative vote of the Board of Directors of
the Baytown Area Water Authority this the 15`h day of July.2009.
1Q R.SAND OP,President
A"1"l'IST:
y
LETICIA G,.'A.h Vern Assistant Secretary
APPROVED AS TO FORM:
ACIO RAMIREZ.SR..G al Counsel
R:\KarenTiles\BAWA\Resolution\2009\FinalPayBAWA3OInchTransmissionLineProjectSettlement.doc
2