BAWA Resolution No. 2007-0009RESOLUTION NO. 2007-0009
•
•
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE BAYTOWN
AREA WATER AUTHORITY REJECTING THE BID RECEIVED ON MAY
22, 2007, FOR THE BAWA RAW WATERLINE PROJECT; ACCEPTING THE
BID OF ALVIN CONTRACTING FOR THE BAWA RAW WATERLINE
PROJECT SUBJECT TO THE APPROVAL OF THE CITY COUNCIL OF THE
CITY OF BAYTOWN, TEXAS, AND AUTHORIZING PAYMENT BY THE
BAYTOWN AREA WATER AUTHORITY IN THE AMOUNT OF SEVENTY-
SIX THOUSAND FOUR HUNDRED SIXTY AND NO/100 DOLLARS
($76,460.00); MAKING OTHER PROVISIONS RELATED THERETO; AND
PROVIDING FOR THE EFFECTIVE DATE THEREOF.
******************************************************************************
WHEREAS, the Board of Directors of the Baytown Area Water Authority advertised for
bids for the BAWA Raw Waterline Project to be received on May 22, 2007; and
WHEREAS, only one bid was received and such bid was higher than the BAWA's
engineer's cost estimate; and
WHEREAS, the Board of Directors of the Baytown Area Water Authority decided to
rebid the BAWA Raw Waterline Project to be received on June 28, 2007; and
WHEREAS, notice to bidders as to the time and place, when and where the contract
would be let was published in accordance with law; and
WHEREAS, all bids were opened and publicly read at the Baytown Area Water
Authority 's Fritz Lanham Water Treatment Facility at 2:00 p.m., on Thursday, June 28, 2007, as
per published notice to bidders; NOW THEREFORE
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE BAYTOWN AREA
WATER AUTHORITY:
Section 1: That the Board of Directors of the Baytown Area Water Authority hereby
rejects the bid received on May 22, 2007, for the BAWA Raw Waterline Project.
Section 2: That subject to the approval of the City Council of the City of City of
Baytown, Texas, the Board of Directors of the Baytown Area Water Authority hereby accepts
the bid of Alvin Contracting for the BAWA Raw Waterline Project for the sum of SEVENTY-
SIX THOUSAND FOUR HUNDRED SIXTY AND NO/100 DOLLARS ($76,460.00).
Section 3: That the Interim General Manager is hereby granted general authority to
approve any change order involving a decrease or an increase in costs of TWENTY-FIVE
THOUSAND AND NO/100 DOLLARS ($25,000.00) or less, provided that the original contract
price may not be increased by more than twenty-five percent (25%) or decreased by more than
twenty-five percent (25%) without the consent of the contractor to such decrease.
Section 3: This resolution shall take effect immediately from and after its passage by
the Board of Directors of the Baytown Area Water Authority.
i
INTRODUCED, READ and PASSED, by the affirmative vote of the Board of Directors
of the Baytown Area Water Authority this the 18th day of July, 2007.
LORRI C • OD , Assistant Secretary
APPROVED AS TO FORM:
ALACIO RAMIREZ, SR.,
eral Counsel
R:Ueanene\My Documents\BAWA\AwardBAWARawWaterlineProject.doc
,--fete*Ay„.
ROBERT L. GILLETTE, President
2