Loading...
Ordinance No. 14,543ORDINANCE NO. 14,543 AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS, APPROVING CHANGE ORDER NO. 12 TO THE BAYTOWN AREA WATER AUTHORITY 6 MGD SURFACE WATER TREATMENT PLANT PROJECT BETWEEN THE BAYTOWN AREA WATER AUTHORITY AND PEPPER LAWSON WATERWORKS, LLC; AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. WHEREAS, the Baytown Area Water Authority's enabling legislation requires that the City Council approve certain agreements before Baytown Area Water Authority ("BAWA") enters into the same; and WHEREAS, on October 21, 2020, the Board of Directors of BAWA approved Change Order No. 12 to the Baytown Area Water Authority 6 MGD Surface Water Treatment Plant Project between the Baytown Area Water Authority and Pepper Lawson Waterworks, LLC; and WHEREAS, the City of Baytown desires to approve such change order; NOW THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS: Section 1: That the recitals set forth hereinabove are hereby found to be true and correct and are hereby adopted. Section 2: That the City Council of the City of Baytown, Texas, hereby approves Change Order No. 12 for the Baytown Area Water Authority 6 MGD Surface Water Treatment Plant Project between the Baytown Area Water Authority and Pepper Lawson Waterworks, LLC, which change order is attached hereto as Exhibit "A" and incorporated herein for all intents and purposes. Section 3: This ordinance shall take effect immediately from and after its passage by the City Council of the City of Baytown. INTRODUCED, READ and PASSED by the affinnative vote of the City Council of the City of Baytown this the 22°d day of October, 2020. B ANDON CAPETILLO, May APPROVED AS TO FORM: KAREN L. HORNER, City Attorney ^� RAKaren Homer\Documents Files -City Council'Ordinances\20201October22\ApprovingBAWAChangeOrderNol2.doc EXHIBIT "A" BAYTOWN AREA WATER AUTHORITY Change Order No. 12 6.0 MGD SURFACE WATER TREATMENT PLANT PO: 1806021 Date: 12-Oct-20 CO 12.1 is for 2 knife gate valves installed in place of plug valves to avoid maintenence issues in the fututre. CO 12.2 is for removing 2 Westfall Model 2800 Static Mixers and accessories and replacing with 1 Westfall 3050 static mixer and accessories and modifying piping at the LLPS Metering Station. CO 12.3 is for modification of an overhead door due to previous CMU column addition at the Operations Building. Add or Delete Items: Item Descri lion Unit QUantily Unit Price Total 12.1 2 Knife Gate Valves Change (PCO #20) 1 LS 21,072.43 $ 21,072.43 12.2 Static Mixer Replacement (PCO #26) 1 LS 6,503.78 $ 6,503.78 12.3 Overhead Door Modification (PCO #45) 1 LS 6,474.63 $ 6,474.63 $ - Total $ 34,050.84 1 Original Contract Price $52,186,000.00 2 Owner Contingency $0.00 Previous Change Orders This Change Order Remaining Contingency 3 Change Orders Previous Change Orders $ (3,292,800.76) This change order $ 34,050.84 4 lRevised Contract Price $52,186,000.00 $48,927,250.08 Original Contract Duration 1095 Previous Extensions 0 This Change Order 0 Revised Duration - Calendar Days 1095 10/14/2020 Contractor: PLW Waterworks, LLC Date Director of Public Works R: Engineering Date EmdtaT0pez-Pnceth Executive Vice President ellc,j f yi.-h = 70-13- 2020 Consultant: Jones I Carter, Inc. Date City Manager Date P1W waterworks March 11, 2019 Mr. Ajay Shakyaver Assistant Director Baytown Area Water Authority The City of Baytown 2401 Market St. Baytown, TX 77520 Re: CPR No. 20 BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. 1806021 Mr. Shakyaver, The originally designed depth of the 12" plug valve at the backwash line connecting the backwash EQ basin and the backwash pump station will cause maintenance issue in the future. Therefore, per the Enigneer's recommendation and the attached RFP 002, PLW is proposing to replace the 12" plug valve with the 12" knife gate valves which will be installed inside the backwash pump station as shown on the revised Sheet 13-M-1. Total of two knife gate valves with stem guides and accessories will be installed per the Drawing. The knife gate valve change will result in a cost increase of $21,072.43 Please find the attached PLW cost summary and associated reference material for your review and acceptance. Please be noted, should any additional costs be incurred as a result of this Work due to clarifications, changes or unknown scope, PLW will seek reimbursement. Clarifications and exclusions are listed on subcontractor's proposal. If you have any questions or need additional information, please do not hesitate to call me at 713-301-8637, or kdrown@plwus.com. Regards, PLW Waterworks 4a�Drrlow4n4g' Project Manager Page 1 Baytown Area Water Authority BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. ISW21 Knife Gate Valve Change CPR No.: 20 Date: 03/11/19 PLW Job No.: P3T Scope of Work Furnish and Install (2) Knife Gate Valves and Accessories at the Backwash Pump Station and Remove (1) Plug Valve per the Engmeces Recommendation and RFP 2 Non -Taxed Labor Material Subcontract Taxed Mat'6E ui Item Unit Total Unit Total Unit Total Unit Total No. Descri pop Orr Unit Cost Cost Cost Cost Cost Cost Cost Cost I PLW Coordination Project Manager 2 HRS S 9900 S 19600 Project Engineer 4 HRS $ 76 00 S 30400 Project Superintendent 4 HRS $ 121 00 S 49400 2 Knife Gate Valve and Guide Stem KGC Valve and Guide Stem Materiel (Dezurik) 2 EA S 5,403 41 $ 10,806 82 KOC Valve and Guide Stem Installation Labor (1)Foreman a HRS $ 46.50 S 37200 (2) Laborers 32 HRS S 2SL49 S 90990 (1)Opennor-Lull 8 HRS S 44,00 S 35200 (1) Lull 1 DYS S S 65000 S 65000 (1)30Ton Crane 2 DYS $ S 1,15000 S 2,30000 (1) Operator - Crane 16 HRS S 44,00' $ 70400 (1) Scissor Lift 2 DYS $ - S 33250 S 66500 (1) Pipe Fitter 32 HRS S 30•00 $ 96000 Additional bolting hardware i LS S 50000 S 50000 Confined Space Safety Equipment 1 LS S - S 50000 $ 500 w 3 Delete 12" Plug Valve per Plans Delete 12" Plug Valve Material (Dezurik) I EA $ (2,698 00) S (2,688 00 Delete 12" Plug Valve Labor (1)Foreman 2 HRS S 46.30 S (9300) (2) Laborers 8 HRS $ 28.40 S (227 20) (1)Operator 4 HRS $ 44.00 S (17600) (1) Lull 1 DYS 3 650 00 $ (650 00 Direct Cost Subtotal 3,78460 8,61892 - 3,46500 Small Tools @ 5.0% 18923 n/s n/a n/a Equipment Burden @ 50.0% n/a n/a n/a 1,73250 Tax d 0.00°. n/a n/a Na Subtotal 2 3,97383 8,61892 - 5,197 50 Overhead & Profit 4 13.0% 59607 1 292 82 77963 Subtotal 4,56990 9.91164 5.97713 Bonds & Insurance :� 3.0% 137 10 29735 17931 Su total 4 - 4,10700 10 708 99 6 156 44 oua 0: M I ca umns 2 1,0, 2 43 Other Grand lotaltost 21,072.43 Page 2 Order # : 622504 Customer Acknowledgement (This is Not a Hill) Date : 03-01-19 Order Date : 10-23-2018 Customer : 135556 Tax No Tax USA Sales Order : 622504 Work Order :472241 Customer P.O.: 2018CP3T-00021000 Rep Contact : Joey Justice Carrier DeZurik Choice Ship Point : Sartell, MN Project Name SAWA - Surface WTP DEZURIK ONLY Page 10 DEZ CUST UNIT ACKNOWLEDGED ITEM ITEM ITEM REV PROJECT FF QUANTITY UNIT PRICE AMOUNT SHIP DATE i 38 9690043 001 623949 112 1.00 ea 2.688.00 2,688.00 HFA DeZURIK-PEF,12,F1,CI,NBR,CR,CMC-S30SCC*GB-6A-M TAG: SPECIAL TAG 41 9690206 131 2.00 ea 4,248.20 DeZURIK-KGC,I2,ES,FI,SI,SMP,S1-M*MN-N-SI,ENTS*EO5211 TAG: SPECIAL TAG -EXTENDED NUT ON RON-RISING STEM, CA OF VALVE TO TOP OF NUT = 3061N (25'-6") Change Order Text - Acknowledged Date Changed - Old Date -> - - 42 1278671 B 101 2.00 as 1,155.21 GUIDE STEM 1-1/4 5960 TRUM TRUMBELL GUIDE - 367-5960 SHIP WITH ITEM 41 Change order Text : Acknowledged Date Changed - Old Date - - - 8,496.40 01-23-2019 2,310.42 02-08-2019 THIS ORDER ACKNOWLEDGEMENT INCLUDES THE TERMS AND CONDITIONS ON THE REVERSE SIDE HEREOF. JONESICARTER RFP NO.:002 REQUEST FOR PROPOSAL (RFP) 1. PROJECT NAME: 6 MGD Surface Water Treatment Plant 2. J&C PROJECT NO.: 09986-0001-00 3. CONTRACTOR: Pepper Lawson Waterworks 4. SUBMITTED TO: Dennis Wang S. SUBJECT: Backwash Pump Station Knife Gate Valve 6. REFERENCE: Submittal No. 26 7. REF. DWG. NO.: 13-M-1 & 13-M-2 B. REF. SPEC. NO.: 15101 9. DESCRIPTION OF WORK: (The Contractor is requested to furnish a price proposal for the below described work. Please complete, sign, date, and return a proposal at your earliest convenience. Please attach a detailed cost breakdown to your proposal. The Backwash Pump Station and corresponding isolation valve shall be constructed according to the attached reissued construction drawing sheets 13-M-1 and 13-M-2. The 12" Knife Gate Valve shall be Dezurik Model KGC-ES or approved equal with the following specifications: - ANSI 150 flanged ends - 304 stainless steel body and gate - Standard braided packing to 500 degrees F - Chloroprene seat to 180 degrees F - 304 stainless steel extension including couplings, rod, bearing plate and supports. Please provide credit information for the change from the eccentric plug valve, extension and valve box to the knife gate valve and accessories per the attached drawings. 11. Requestor's Name & Signature: Larry Weppler Date: 8/6/2018 The Contractor acknowledges that this RFP Is to be used to request pricing information only, and does NOT constitute a contract modification. The Contractor is NOT AUTHORIZED/DIRECTED to perform this work UNTIL/PRIOR TO written notification that a contract modification Is approved. I:wp\docs\const\forms\rfi or rfp\rfpform.doc REV 9 14 00 f 3 � c� f is I I a s _ t 7 'y gS �� If f �� all_ �.m` •• l M E`p IL a .o L 6 L L L L d� 1r ,� L � � k Ptw waterworks October 21, 2019 Mr. Vinoth Manoharan AECOM 5444 Westheimer Rd. #1400 Houston, TX 77056 Re: CPR No. 26 Rev 2 BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. Mr. Manoharan, PLW is submitting the attached PCO #026 in accordance to the RFP #007 dated on May 21st, 2019, and RFP #007 Rev 1 dated on June l7th, 2019, concerning the LLPS Metering Station Piping and Vertical Turbine Pump Modifications. PLW proposes to make the following changes on the above mentioned work per the Engineer's comments: 1. Remove two (2) Westfall Model 2800 Static Mixers and accessories per Original Sheet 0-M-4. 2. Add (1) Westfall Model 3050 Static Mixer and accessories per RFP #007. 3. Modify LLPS Metering Station Piping per RFP #007 Sheet 4-M-3. 4. Modify LLPS Vertical Turbine Pumps per RFP #007 Rev 1. The modifications on the LLPS Metering Station Piping and LLPS Vertical Turbine Pumps will result in a cost increase of $6,503.78. Please find the attached PLW cost summary and associated reference material for your review and acceptance. Please be noted, should any additional costs be incurred as a result of this Work due to clarifications, changes or unknown scope, PLW will seek reimbursement. If you have any questions or need additional information, please do not hesitate to call me at 713-301-8637, or kdrown@plwus.com. Regards, PLW Waterworks eaeWDrowgn— Project Manager Page 1 Baytown Area Water Authority BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. 1806021 LLPS Metering Station Static Mixer and VTP Modifications CPR No.: 26 Date: 10:21 19 PLW Job No.: P3T Scope of W ork Replace tuu (2) Westfall Model 2800 Static Mixers with One (I) Westfall Model 3050 Static Mixer. revise the LLPS Metering Station Piping add one (1) sample tap at the Rapid Mixer Basin influent line and modify the vertical turbine pumps and expaitstonjoints at the LLPS per the RFP 9007 Noa-Taxed Labor Material Subcontract Taxed Mat'VE ui Unit Total Unit Total Unit Total Unit Total Item No. Description Qtv Unit Cost Cost Cost Cost Cost Cost Cost Cost I PLW Superwision I I Project Manager 0 HR $ 9800 S 12 Project Engineer 0 HR S 7600 S 13 Project Superintendent 0 HR S 12100 S - 2 Westfall Static Mixer Modification 2 1 Delete Model 2800 Static Mixer 2 EA S (20,480 00) S (40.960 00) 22 Delete Solution Tube Assemblies PVC I EA $ (800 00) S (1 600 00) 23 Add Model 3050 Static Mixer 1 EA S 23,665 00 S 23 665 00 24 Add Solution Tube Aswmbh Stainless Steel 1 EA S 2 250 00 S 2 250 00 25 Add Injection Assemblies to Rau Water Line 1 LS $ 93636 S 93636 3 LLPS Metering Station Piping Modification 1 LLPS Metering Station Piping Fabrication and Dclnen I LS S 10,939 30 $ 10 839 30 3.2 LLPS Metering Station Reused Piping Pro(move Coating I LS $ 6.20000 S 6.20000 311 LLPS Metering Station Min'erod Piping per Original Dcsgm Credit I LS S (39 92) S (38 92) 3 4 LLPS Metering Station Dcln cmd Piping PmIccu%c Coating Remo%at I LS $ 4.20000 $ 4 200 00 and Re -apply Pruner I LS 4 Vertical Turbine Pump Modification 41 Vertical Turbine Pump Modifications 1 LS S - S - Direct Cost Subtotal - (4 909 26) 1 U 400 00 - Small Tools a' 5 0'. - n/a - n/a n Equipment Burden a 50 0'. n/a ate n/a T. a 8 25'. n/a n/a n/a Subtotal 2 - (4.90926) 10 400 00 - O%cnccad & Profit n 15 0'. 736 39 1 560 00 Subtotal 3 - (5 645 65) 11 960 00 - Bands & Insurance a 3 0'. 169 37 35880 Subtotal 4 (5 815 02) 12 318 80 Total of all columns 6.503 78 Other Grand Total Cost 6,503.78 JONES CARTER RFP NO.: 007 REQUEST FOR PROPOSAL (RFP) 1. PROJECT NAME: 6 MGD Surface Water Treatment Plant 2. J&C PROJECT NO.: 09986-0001-00 3. CONTRACTOR: Pepper Lawson Waterworks 4. SUBMITTED TO: Dennis Wang S. SUBJECT: Westfall Static Mixer 6. REFERENCE: Submittal No. 262 7. REF. DWG. NO.: 4-M-3 & 6-M-1 8. REF. SPEC. NO.: 11512 & 11021 9. DESCRIPTION OF WORK: (The Contractor is requested to furnish a price proposal for the below described work. Please complete, sign, date, and return a proposal at your earliest convenience. Please attach a detailed cost breakdown to your proposal. The Low Lift Pump Station flow metering station shall be constructed according to the attached reissued construction drawing sheet 4-M-3. — The 16" static mixer shall be the Westfall Static Mixer Model 3050 per the attached cut sheets. — The piping and chemical layouts of the flow metering station shall be in accordance with the reissued construction drawing. Addition of a sample valve as shown on the reissued construction drawing sheet 6-M-1. The Low Lift Pump Station Vertical Turbine Pumps shall be constructed with the following design changes: Design Flow (1st Design Point): 2,387 gpm — Total Head (11t Design Point): 32.3 ft — Design Flow (2nd Design Point) : 2,213 gpm — Total Head (2"d Design Point): 35 ft Please provide cost increase/decrease information for the changes to the Low Lift Pump Station flow metering station and Low Lift Pump Station. 11. Requestor's Name & Signature: Larry Weppler Date: 5/21/19 The Contractor acknowledges that this RFP is to be used to request pricing information only, and does NOT constitute a contract modification. The Contractor is NOT AUTHORIZED/DIRECTED to perform this work UNTIL/PRIOR TO written notification that a contract modification is approved. i:wP%docAconst\forms\rfi or rfP\rfpform.doc REV 9/14100 VAL W �O ACCaSORICS SCHi'ME NOTES. .77) r-9 . ........... ...... ..... A (DawLIFr PUMP Sjj�T_PtL METER PLAN VIEW ....... A SCM B—OM AKA WAIER AUTI tv I FTUrTH11 - T LOW L FT PUMP STATION IMETER FLOW PLAN AND [Mill. SECTION e).l .... CARTER LOW LIFT PUMP STATION W METER SECTION 4-M-3 W-0717 ON MEMO a I i 1111 - - ------------ rllll Intelft 11111ir PULSED BED CLARIFIER PLAN vl a I WESTFALL STATIC MIXER MODEL 3050 SCH40 CARBON STEEL CONSTRUCTION ((2)) ROWS OF ((4 CARBON STEEL MIXING TABS ( 13/4" 316SS 1 JECITON PORT WELDOLET l # RFSO CARBON STEEL FLANGE ENDS INTERIOR COATED WITH 3M SKOTCHCOAT 134 COATING EXTERIOR COATED WITH RUSTOLEUM PRIMER SHOWN WITH: (1) STAINLESS CORP STOP WITH HASTELLOY SOLUTION TUBE 023.50 FLAT 16.00 PIPE OD 015.25 PIPE ID FLOW -----> " CLIENT BPROVAL: DATE �/,/ESTFALL W�ALLSTATIC MIMODEL 3050 - IN' XER PRW NAME: TALE: DIMENMM ARE IN NCNES (UNLESS OiHSMSE NOTED( WESIFALLMANLIFAC1URNG C7lOWANY 10.2 M11 COMPANY. ;�W54.8 MGP ■o ■o 14 Model 3050 Series Mixer 0 US PATENT PENDING The Perfect Mixer for Pressure -Limited Operation Four tapered and curved vanes with precisely designed geometry turn flow inside out to mix fluids or gases, while generating two to four times less headloss than other mixers. The k-value is 0.58 �* and the CoV is .057 The addition of a second row of vanes aligned with the first row provides additional mixing as the vortices intersect and overlap in a braiding effect. The k-value is 1.13 and the CoV is .026. Three sets of vanes in alignment produce a k-value of 1.64 and a CoV of .014. The Westfall 3050 Mixer consists of a pipe fitted with one, two or three sets of strategically placed vanes, each occupying one diameter of length. The vanes create vortices and multiple zones of turbulence that intersect to produce optimal mixing when there is very low available head. Its unique geometry makes the mixer resistant to fouling. In addition, "Since the device was originally designed as a flow conditioner, it is also very effective at mitigating any swirling flow that is created upstream, and creating a fully developed flow profile," according to Kimbal Hall at Alden Research Laboratory. ° e MrkPr � ThrPO st 91. _ 7.61 Cross section of Westfall 3050 Mixer Westfall's Model 3050 Mixer series provides consistent mixing with very little headloss, ideal for situations with very low available head. 1 0.01 4 0 Westfall 3050 Staged Mixer CFD Results - Single -stage Mixer I .t Two -stage Mixer _ ..�. Three -stage Mixer- 1 i 3 4 S 6 7 8 9 :.p Distance Downstream of Mixer Inlet (L/D) Cross section of Westfall 3050 The CoV values for Model 3050 Low Headloss Static Mixer were determined for: • single -stage • two -stage • three -stage Alden Research Laboratory, Inc. APPLICATIONS performed numerical ♦ Municipal and simulations using the CFD software package FLUENT V6.3.26, Industrial Water Treatment a state-of-the-art, finite volume -based fluid flow simulation ♦ Potable Water package, to calculate the three-dimensional, incompressible, ♦ Waste Water turbulent flow through the pipe and around the mixer ♦ Chlorination/De-Chlorination The model geometry was developed using the commercially ♦ Chemical Blending available three-dimensional CAD and mesh generation software, ♦ Dissolving Gases GAMBIT V2.4.6 and the computational domain generated for ♦ Contact Chambers the model consisted of approximately 2 million hexahedral and ♦ Flocculant Blending tetrahedral cells. westfallmfg.com/alden ♦ Anaerobic Digestion --- — ♦ Dewatering ♦ pH Control ADVANTAGES ♦ Contacting - -- — ♦ Product Blending • Mixes well in situations with low head and is resistant to fouling • Creates minimal headloss — two to four times less than other mixers • Reduced laying length — just one diameter per stage • Can be fabricated from PVC, FRP, 316 Stainless Steel, with or without Teflon coating • Is available in pipe diameters from 112" to 120" • Low cost, easy installation • Long service life and low maintenance requirements Westfall Manufacturing Company 15 Broad Common Road • Bristol, RI 02809-2721 Voice: Toll Free: 888-928-3747 or 401-253-3799 Fax: 401-253-6530 • E-mail: info®westfallmfg.net www.westfallmfg.com Westfall Innovates —Others Imitate 10/2010 Baytown Area Water Authority 6 MGD Surface Water Treatment Plant SECTION 11021 VERTICAL TURBINE PUMPS PARTI-GENERAL 1.1 SCOPE RFP NO. 7 A. Contractor shall provide all labor, materials, and equipment as shown and specified to furnish and install all vertical turbine pumps, complete and operable. B. Equipment shall include electric motor, pump column, shaft, base, impellers, bowls, bearing, suction inlet bell, sole plate, and all appurtenances. 1.2 RELATED SECTIONS A. Related sections include but are not necessarily limited to: 1. Division 0 — Bidding Requirements, Contract Forms, and Conditions of Contract 2. Division 1— General Requirements 3. Division 3 - Concrete 4. Division 9 — Coatings 5. Division 11- Equipment 6. Division 15 - Mechanical 7. Division 16 — Electrical 1.3 REFERENCES A. Comply as a minimum with applicable provisions and recommendations of the following standards: 1. American National Standards Institute (ANSI) 2. American Society for Testing and Materials (ASTM) 3. Anti -Friction Bearing Manufacturers Association (AFBMA) 4. Hydraulic Institute 5. Institute of Electrical and Electronic Engineers (IEEE) 6. National Electric Code (NEC) 7. National Electrical Manufacturers Association (NEMA) 8. Steel Structures Painting Council (SSPC) 1.4 SUBMITTALS A. Provide submittal data, manuals and drawings as specified in Section 1340, Shop Drawings. B. Pump Data: 1. Certified pump curves shall identify cut-off point, rated point, and a minimum head at which the pump operates without vibration and cavitation. Curves shall be corrected for pump losses and shaft friction HP losses. Pump losses shall include column and discharge head losses. For pumps that are to be operated by variable speed units, provide a minimum of five curves with at least three different speeds between the maximum and minimum rpm of the pump. 2. Submit certified characteristic curves showing head -capacity relationship, brake horsepower, net positive suction head requirements, pump efficiency (ratio of water horsepower to brake horsepower), pump thrust, and pump speed. i. Curves shall be complete over the entire range of operation from shut-off to zero head conditions. 09986-0001-00 11021-1 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 Baytown Area Water Authority 6 MGD Surface Water Treatment Plant RFP NO. 7 VERTICAL TURBINE PUMPS 3. Submit manufacturer's L-10 bearing life calculations for radial and thrust bearings at pressure heads and flow rates shown. 4. Submit manufacturer's specifications, engineering data, pump weight, dimensions, coating requirements, size, parts list, and illustrations. 5. Minimum submergence required over suction bell, critical distances from structural floor and walls. 6. Impeller Diameter 7. Diameter of pump can (if applicable). 8. Maximum downward thrust and upthrust in pounds exerted by pump. 9. Schematic diagrams illustrating utility requirements such as air, water, drainage, etc. for each component. 10. Detailed mechanical and electrical plans and elevation drawings showing the equipment dimensions, size, and location of connections and weights of associated equipment including single largest component. 11. Power and control wiring diagrams, including all sensory and control devices, terminals, and numbers; such as RTD connection diagrams, anti -condensation heater connection diagrams, and vibration sensor connection diagrams. 12. Alarm and shutdown level trip points for specified motor enclosure, winding and bearing resistive temperature detectors (RTD's), and vibration monitors. 13. A schedule for all shop testing and delivery of equipment to the job site. 14. Factory finish and system. 15. Test reports. C. Manufacturer's Certifications 1. Submit manufacturer's certification that Contract Documents have been examined by the manufacturer for proposed electrical, mechanical, and structural systems affecting performance of the pumping equipment. 2. Submit manufacturer's certification that the maximum power requirement, if used, shall not exceed the motor rating under operating conditions on the pump characteristic curve. 3. Submit seal manufacturer's certification that the seal is designed for service and application specified and is installed and aligned properly. 4. Submit Manufacturer's statement indication that the required lateral and torsional critical speed analyses have been performed and that the specified critical frequency limitations will be met. 5. Submit manufacturer's statement indicating that the design of the pumping units avoids the natural frequencies of the existing Pump Station's structure. 6. Pump manufacturer is responsible for certifying that the variable speed drive unit is compatible with the pump and motor allowing full compliance with the job conditions and performance requirements specified herein. D. Motor Data 1. Horsepower 2. Electrical characteristics 3. Bearing life ratings 4. Insulation ratings 5. Weight 6. Thrust Bearing 7. Other data to provide a complete description E. Instruction Books 1. Service and maintenance manual 2. Service parts list 3. Outline drawing 09986-0001-00 11021— 2 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 RFP NO. 7 Baytown Area Water Authority VERTICAL TURBINE PUMPS 6 MGD Surface Water Treatment Plant 1.5 QUALITY ASSURANCE A. Use new materials of high grade, and with properties best suited to the work required. B. Pumping units and motors shall be the product of manufactures with at least ten (10) years of successful experience in the design, manufacturing and application of pumping units of the type, size and performance capabilities as specified. The pump manufacturer shall have at least three similar size pumps of the model, type, and size of pump in service and operational for at least five (5) years. Manufacturers shall provide a list of references for the same. C. All components of the pump shall be supplied, assembled, and warranted by one of the approved pump manufacturers. Pump components shall not be acquired from separate entities and assembled as a final product by a manufacturer's representative. D. Factory Tests: 1. Provide certificates of the non -witness factory test of the entire pump assembly, with driver fully assembled, to demonstrate compliance with the specifications and to verify guaranteed performance of the pump. The factory test shall include the actual flow, total dynamic head, pump horse power, and pump efficiency for all the duty points listed. Test pump and recirculate water for at least one hour under simulated service conditions. The Contractor shall submit the factory test certification to the Engineer before the pumps are shipped and delivered. Give pump bowls an operational test at the factory to check for excessive vibration and for leaks in all piping and seals. Test pump and recirculate water for at least one (1) hour under simulated service conditions. 2. Provide certified factory test reports to the Engineer for review and approval prior to pump delivery. 3. The motors installed shall be tested by the motor manufacturer and a full written report provided to the engineer. The testing shall be performed in accordance with IEEE 112 method B at 60 Hz. The test shall include percent slip, no load current, full load current, locked rotor current, locked rotor torque, efficiency, and power factor at the frequencies listed above, megger, winding resistance and higher potential. 4. The manufacturer shall perform both lateral and torsional critical speed analyses on the assembled pumping units to identify and ensure that: a. The first lateral critical speed shall be at least 25 percent above the specified pump speed. b. No torsional natural frequencies occur within a range extending from 25 percent below to 25 percent above the specified pump speed. C. Any blade excited resonant frequency shall be no closer than plus or minus 25 percent of the natural frequency of any part of the installed assembled pumping unit. d. On VFD applications, both Goodman & Gerber fatigue analyses will be performed on the shaft to verify shaft fatigue strength is acceptable. E. Delivery, Storage, and Handling: 1. Store equipment off the ground in enclosed shelter. Store and maintain equipment in accordance with manufacturer's direction. 2. Deliver materials to the site to ensure uninterrupted progress of the Work. 3. Deliver anchor bolts and anchorage devices which are to be embedded in cast -in -place concrete in ample time to prevent delay of Work. 4. All boxes, crates, and packages shall be inspected by the contractor upon delivery to the site. Contractor shall notify Engineer of any loss or damage to equipment or components. Replace losses and repair damage to new conditions, in accordance with manufacturer's instructions. 09986-0001-00 11021— 3 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 Baytown Area Water Authority 6 MGD Surface Water Treatment Plant In -Place Test: RFP NO. 7 VERTICAL TURBINE PUMPS 1. Perform a complete pump test including static and pumping levels, flow rates, motor amperage, and all other information normally checked on a maintenance -type pump test. Include flows and meter readings at three different points on the curve, and repeated for a total of 3 different operating speeds for VFD applications. 1.6 OPERATIONS AND MAINTENANCE DATA A. The manuals shall be prepared specifically for this installation and shall include all required cut sheets, drawings, equipment lists, descriptions, etc. In addition to the requirements of Section 1340, the manuals shall include the following at a minimum: 1. Complete column assembly, pumping equipment, discharge head, oiler, parts list, test reports, maintenance data and schedules, spare parts information, and cross-referenced to exploded view of assembly drawings. 2. Dimensional drawings for all provided components with their respective weights. 1.7 WARRANTY A. Warranty: 1. For a period of 12 months from final acceptance, the manufacturer shall warrant that the equipment shall be free of defects in material and workmanship under normal use and service, and when properly installed. The manufacturer shall repair or replace such equipment or any part thereof furnished by the manufacturer and found defective after inspection by the manufacturer. Performance Guarantee: 1. In consideration that the award of this equipment is based on performance representations as shown on the plans, the manufacturer/Supplier shall guarantee the performance of each pumping unit to perform as represented. 2. Represented performance will be verified via factory and field testing as defined herein. 3. Pumping units failing to perform as guaranteed during factory testing will be subject to performance penalties as defined in paragraph C below. 4. Pumping units failing to meet minimum specified performance during factory testing will be rejected outright by the Owner. The manufacturer shall be responsible for any liquidated damages resulting from any delay associated with failure to meet minimum specified performance during factory testing. The manufacturer liquidated damage liability is limited to 10% of the unit price on the applicable Bid item value. 5. The guaranteed performance of each specified pumping unit shall be stated by the Manufacturer. C. Performance Penalty: 1. If the owner chooses to accept a unit that does not meet the minimum pump efficiency, a penalty of $10,000 per 1% per unit will applied. The penalty will be used to offset the additional cost of electricity incurred by the Owner over the operational life of the pumping units. 2. The calculated performance penalty (if applicable) will be deducted from the manufacturer's subsequent progress payment request or requests (as appropriate). 09986-0001-00 11021— 4 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 Baytown Area Water Authority 6 MGD Surface Water Treatment Plant PART 11-PRODUCTS 2.1 GENERAL RFP NO. 7 VERTICAL TURBINE PUMPS A. Description: 1. Provide new vertical, multistage turbine pump complete with electric motor and all other appurtenances for a complete operating pumping system. Select pump and motor combination on overall efficiency. Pump shall conform to ANSI B58. 1-1961 "American Standard for Vertical Turbine Pumps" and the Hydraulic Institute Standards for Centrifugal Pumps. B. The pump shall have a Capacity vs. Head curve with an increasingly rising slope steeper or equal to the slope of the line between the two (2) duty points. C. Select equipment which is designed and built for continuous service at all points on pump curve, without overheating, without cavitation, and without excessive vibration or strain. The pump shall have a continuously rising head -capacity, characteristic curve. D. Pumps shall meet the following design conditions: Design Conditions LLP-P-100, 200, 300 TPS-P-100, 200, 300 HSP-P-100, 200, 300 Use/Location Raw Water/Low Lift Pump Station Transfer Pump Station High Service Pump Station Number of Pumps Required (Phase 1) 3 3 3 Variable or Constant Speed Variable Variable Variable Design Flow (1st Design Point) (gpm) iM 2 , 367 2,083 2,083 Total Head (11t Design Point) (ft.) -246- 32.3 57 175 Minimum Bowl Efficiency (111 Design Point) 75 73 80 Design Flow (2"d Design Point) (gpm)6A@ 2 , 213 1,775 2,350 Total Head (2"d Design Point) (ft.) 36- 35 68 150 Minimum Bowl Efficiency (2"d Design Point) 70 70 76 NPSHa (ft) 38 41.85 40.85 Motor Size (hp) 30 50 150 Max. Operating Speed (rpm) 1,770 1,800 1,800 Lubrication Oil/Grease Product Product Shaft Type Enclosed Open Open Performance Requirements: 1. Each pumping unit shall be capable of pumping the flow and head as shown. 2. Each pumping unit shall operate from runout to shutoff head condition without exceeding the motor horsepower. 3. Each pumping unit shall operate smoothly without abnormal noise, vibration, or excessive heat over the defined range of operating conditions. 4. Each pumping unit shall operate smoothly over its entire range as defined by the Hydraulic Institute's Allowable Operating Range. Vibration shall not exceed the limits set by the current edition of the Hydraulic Institute Standards within the pump's Preferred Operating Range or within the pump's Allowable Operating Range. This vibration limit applies to both the top of the pump and the top of the motor. 5. Each pumping unit shall be designed and fabricated so as to limit operating sound pressure levels to 85 dBA in any direction at a distance of 3-foot from the equipment over the defined flow range. 09986-0001-00 11021— 5 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 RFP NO. 7 Baytown Area Water Authority VERTICAL TURBINE PUMPS 6 MGD Surface Water Treatment Plant 6. Each pumping unit shall be designed and fabricated so as to limit heat generation and gain to that specified herein over the defined operating flow range. 2.2 ACCEPTABLE MANUFACTURERS A. Provide vertical line shaft pumps of one of the following: 1. Pentair Fairbanks 2. Ruhrpumpen 3. Flowserve 4. Goulds 5. Sulzer 6. Patterson B. Provide motors as specified in Section 16013. 2.3 PUMP BOWL ASSEMBLY A. Provide pump bowls fabricated of fine grained, high tensile strength iron, ASTM A 48, Class 30 or better, with smooth surfaces devoid of blow holes and other irregularities. Use clean, sound casting without defect. Do not plug, weld or otherwise repair defects. 1. Furnish bowls able to withstand a hydrostatic pressure twice the pressure at rated capacity or 1Y2 times shutoff head, whichever is greater. 2. Equip bowls with replaceable stainless steel wear rings on the suction side of enclosed impellers. 3. Pump bowls shall have electrostatically bonded, fused epoxy coating on the inside only. B. Install impellers of the enclosed type. 1. Use zinc -free bronze or stainless steel impellers, balanced hydraulically and dynamically. 2. Equip impellers with stainless steel collets. 3. Do not coat impellers with porcelain, enamel, or any other material. 4. Securely fasten the impellers on the shaft by a split -tapered lock bushing. C. Employ a zinc free bronze suction case bearing, packed with insoluble grease, and protected against entry of sand or other abrasives. D. Provide zinc free bronze bowl bearings, water or oil lubricated, securely fastened to the bowl. See Section 2.1.1) for lubrication requirement for different applications. E. Provide sufficient lateral in the pump bowls to allow operation at shutoff head and at run -out. F. Pumps, as an assembled unit, shall be compliant to NSF/ANSI Standard 61 and Annex G and meet the requirements of the US Safe Drinking Water Act of 2014. 2.4 COLUMN A. Pump columns shall be ANSI threaded and coupled ASTM A53 or ASTM A120 steel of flanged and bolted construction in lengths not exceeding 5 foot and a minimum wall thickness of 0.375-inches. Columns shall be interchangeable with identical flanged ends that are parallel faced and machined accurately with a register fit to insure proper alignment. All flanged hardware shall be Type 316 stainless steel with anti -seize compound. Provide two lifting lugs and support brackets on all column sections and bowl assemblies. Pump discharge head shall be fabricated identically to columns. Pump discharge shall be as shown on the Drawings with a minimum 3-piece fabricated discharge elbow with 150 lb ANSI flanged ends. Pump columns shall be designed to hang down into the pump well with no lateral braces. Pump column sections shall be marked to indicate their installation sequence. 09986-0001-00 11021— 6 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 Baytown Area Water Authority 6 MGD Surface Water Treatment Plant 2.5 SHAFT RFP NO. 7 VERTICAL TURBINE PUMPS A. Provide pump shafts which are machined, precision ground and polished. Select shafts of ample size to operate the pump without distortion or vibration. Ample size is larger than determined by Section A4.3.3, of the latest revision of AWWA E-101. Provide bearing support for shaft above and below each impeller. Line shaft shall be furnished in interchangeable sections not over 5 feet in length and shall be coupled with high grade, machined steel couplings. Shafting shall be straight to within 0.003 inches TIR at any point along the length of the shaft. Any shaft not meeting this requirement shall be replaced. Repairing or straightening will not be allowed. The pump line shaft and motor shaft shall each be of solid shaft construction. Shafts shall have butting faces, machined square to the axis of the shaft to insure accurate alignment. Couplings shall be designed with a safety factor of 1.5 times the shaft design strength and shall be of the split ring key type to prevent uncoupling in the event of backspin. Motor to pump couplings shall be rigid 3-piece and shall be adjustable for use in impeller lift adjustments. Shafts shall be marked to indicate the installation sequence. 2.6 SHAFT ENCLOSING TUBE A. Shaft enclosing tube shall consist of interchangeable sections not over 5-feet in length of Schedule 80 ASTM A53 Grade B steel pipe to receive bronze couplings which will act as line shaft bearings. The bearings shall be made of ASTM B584 C903 and shall have a spiral groove in the inside surface to promote the downward movement of lubricant in the tubing. Tubing shall be sized to fit inside the column pipe and house the shaft. 2.7 CENTRALIZERS A. Provide rubber centralizing spiders in the column pipe to hold the shaft on enclosing tube in the center of the column. Install one spider per join of column. 2.8 LIFTING, ALIGNMENT, AND ACCESS A. Provide two (2) lifting lugs with support brackets capable of supporting the weight of the entire pump and motor. B. Provide the motor support pedestal with an accurate, machine -registered fit for alignment of the driver. C. Provide suitable openings for each access to the mechanical seal. 2.9 MECHANICAL SEAL A. Provide a balanced single cartridge mechanical seal with a vent and flush port on gland, floating seal rings and a static O-ring. The adjusting studs and nuts shall be stainless steel for the mechanical seal housing. The materials shall be 316 stainless steel for all metal components, graphite -loaded sintered silicon carbide for the rotating seal ring, sintered silicon carbide for the stationary seal ring, hastellow C-276 for the spring, and Viton or Fluoroelastomer for the C-ring. Provide %-inch (W) diameter galvanized pipe from pump head to a point along the ground to carry any water that leaks past the mechanical seal to the ground away from the pumps. 2.10 DISCHARGE HEAD A. Provide a fabricated steel discharge head with separate base plate and ANSI Class 125 flanged outlet above ground. The fabricated head shall be supplied with four -equally spaced 2-inch schedule 80 pipes connecting the top motor mounting plate to the bottom head plate on all VFD driven pumps. Discharge heads shall be designed and provided by pump manufacturer. 09986-0001-00 11021— 7 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 RFP NO. 7 Baytown Area Water Authority VERTICAL TURBINE PUMPS 6 MGD Surface Water Treatment Plant B. Discharge head shall be designed to carry the maximum down -thrust which the electric motor can handle. C. Sole Plate: 1. Provide a sole plate large enough to span the opening in the support structure. Attach the plate to the suction barrel. 2. The sole plate must be suitable for mounting the discharge head. 3. The pump manufacturer must furnish all the hardware for securing the head to the sole plate. Foundation bolts will be supplied by the Contractor. Lubricator and Immersion Heater: 1. Three (3) gallon nominal capacity welded steel reservoir with integral mounting foot. 2. Hinged waterproof cover that opens past 90 degrees and has a hasp for a padlock. 3. Oiled interior, epoxy primed exterior. 4. Fluid level indicator and fluid level sensor. 5. 150W maximum, 120 volt, 60Hz immersion heater in a moisture resistant enclosure with thermostat, adjustable 30 to 110 degrees F. 6. Solenoid valve with bypass, 120V, 60Hz molded coil — NEMA 4 enclosure for outdoor use. 7. Toggle valve for flow control of oil to bearing, outlet %-inch copper tubing. 8. Oiler shall be full at time of start up. 2.11 SUCTION BARREL (PUMP CANS) A. Prefabricated steel pipe suction barrels shall be provided as shown on the plan sheets. Suction barrels with anticipated flows in excess of 3,000 gpm shall have internal straightening vanes and an inlet pipe splitter plate, as required by HI latest standards. Suction barrels wall thickness and top flange thickness are shown below. All suction barrels shall have the top flange shipped loose, with jack bolts to assist in leveling, for field leveling & welding. Each top flange shall have a drilled and tapped bolt pattern that is equal to a standard 150# flange. These holes shall straddle centerline of the can inlet. The top surface shall have a minimum surface finish of 125 RMS and include an 0-ring groove with 0-ring for sealing purposes. A gasket will not be acceptable. The barrel inlet shall be as shown on the plan sheets and shall be flanged with an AWWA C207-94 Class D steel flange. A vertical splitter plate shall be provided in the inlet pipe the entire length of the inlet. The bolting to attach the discharge head to the suction barrel will be 18-8 SST & furnished by the barrel manufacturer. The barrel length shall be as shown on the plan sheet and shall have a bottom cap plate in equal thickness to the top flange. Four (4) evenly spaced, 3" x 3" x 3/8" angles, with a 1" holes in each, shall be welded to the outside diameter on the barrel to assist the installing Contractor in mounting and aligning the suction barrel. The barrel shall be fitted with two (2) %" couplings to serve as a vent for the barrel. All suction barrels shall be equipped with internal straightening vanes and anti -vortex cross in the can bottom. B. The suction barrel shall be blasted and coated as described in the Specification 09920. The coating must meet the requirements of NSF 61 for potable water applications. C. The top flange of suction barrels and soleplates shall be leveled to within .002 of an inch per foot of diameter of the flange. Suction Barrel Outside Diameter* Top Flange Thickness* Barrel Wall Thickness* 16" — 24" 1-1/2" 0.375" 30" 1-3/4" 0.375' 36" 2-3/8" 0.375" 42" — 60" 2-1/2" 0.375" *Minimum Values 09986-0001-00 11021— 8 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 Baytown Area Water Authority 6 MGD Surface Water Treatment Plant RFP NO. 7 VERTICAL TURBINE PUMPS 2.12 ELECTRIC MOTOR FOR PUMPS A. Refer to Section 16013 ELECTRIC MOTORS under Division 16, Electrical for motor information. 2.13 NAMEPLATES A. Provide each pump and motor with a standard nameplate securely affixed in a conspicuous place showing serial number and name of the manufacturer. 1. Pump Nameplate. Each pump nameplate will show capacity in gallons per minute at rated speed in revolutions per minute and head in feet. 2. Motor Nameplate. See Electric Motor section in Division 16. 3. Number the pumps with six-inch (6") or larger stencils using black alkyd paint. Pump numbers are to correspond to wiring in motor control center. 2.14 VORTEX SUPPRESSOR/BASKET STRAINER A. Raw water pumps shall have a vortex suppressor/basket strainer installed on the pump's suction. The vortex suppressor/basket strainer shall be constructed to meet the following requirements: 1. Performance requirements: a. Approach velocity: 3.0 feet per second, maximum, at design flow b. Net open area: 65 percent 2. Design requirements: a. Configuration: Basket -type with solid bottom plate and internal straightening vanes. b. Screen: 0.120 inch woven wire cloth on 5/8" centers C. Materials: Wire cloth to be 316 stainless steel material. All other materials to be 304 stainless steel with a minimum thickness of 3/16". d. Mounting: Bolted to the pump suction bell using 5/16" minimum diameter 18-8 SST bolts. "Clips" are not acceptable PART III - EXECUTION 3.1 INSTALLATION A. Install all equipment and connecting piping in accordance with manufacturer's instructions. Prior to testing and start- up, inspect to verify the system is complete. B. No form of energy shall be turned on to any part of the system prior to approval of factory authorized service representative. C. Allow concrete floor and curb at pump openings to cure at least seven days prior to installing the sole plates and at least 14 days before installing the pumps. Pumps shall not be operated until concrete has cured 28 days. 3.2 FIELD QUALITY CONTROL A. Furnish the services of a qualified representative of the Pump Manufacturer to inspect the completed installation, make any necessary adjustments, participate in the startup of the equipment, participate in the field testing of the equipment and place the equipment in trouble -free operation. 09986-0001-00 11021-9 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 Baytown Area Water Authority 6 MG Surface Water Treatment Plant RFP NO. 7 VERTICALTURBINE PUMPS B. All piping connections to the pump shall be done without bending and/or twisting the piping to mate with the pump flange connections. C. A certificate for the Pump Manufacturer shall be submitted stating that the installation of the equipment is satisfactory, that the equipment is ready for operation and that the Owner's operating personnel have been suitably instructed in the operation, lubrication and care of each unit. D. After pumps have been completely installed and working under the direction of the manufacturer, conduct field tests necessary to demonstrate that pump operation conforms to these Specifications. Supply water, labor, equipment are incidentals required to complete field tests. E. If the pump performance does not comply with Specifications, take corrective measures or remove and replace pumps with pumps which satisfy the conditions specified. 3.3 START-UP AND ACCEPTANCE A. Start -Up: 1. Final Completion will not occur until after the start-up activities have been performed and accepted by the Engineer. Start-up activities include the following: a. Receipt and acceptance by the Owner of draft Operation and Maintenance manuals, including the wiring and ladder diagrams. b. Installation inspection by representatives of the Owner and pump manufacturer followed by any corrective measures required by the Design Builder. C. Satisfactory operation of pumps for 7 consecutive days under the Owner's control. If malfunctions or other operational problems halt the 7-day test period, the Design Builder shall make appropriate corrections and restart the 7-day test period. d. Provide the services of a factory -trained technician for a period of 4 hours at the pump station to train the Owner's operating and maintenance personnel. Training session shall be scheduled and coordinated by the Design Builder. B. Acceptance: 1. After the start-up operation has been successfully completed, the final Operation and Maintenance manuals have been received, reviewed, and accepted, and the Engineer has issued Final Completion, the pumps will be accepted by the Owner. Include ladder logic diagrams and wiring and termination diagrams for both power and instrumentation systems. END OF SECTION 09986-0001-00 11021-10 CONFORMED SET Rev. Per Add. No. 6 09/12/2017 AaULos a xViem band Product Name: VIT - Short Set Lineshaft Turbine Pumps Product Id: GWT VIT 40 t Performance Curve Quote Number BAWA- Low Lift 4f:,.: dM 1200 16W 2000 2400 two 320, 2400 2800 3200 0 . j + 400 800 1200 1600 2000 2400 2800 3200 a US 9pm Curve & hydraulic data presented is nominal performance based on ANSI/HI 14.6 acceptance grade 2B. Design values are guaranteed within the following tolerances: Flow t 8%, Head t 5%, and optionally either Power + 8% or Efficiency - 5% at manufacturer's discretion. Series GWT_VIT Max Power on Design Curve 24.70 Hp Size 14FHC Max Power on Max Imp Trim 24.70 Hp Additional Sire - Guaranteed Max Power on Design Curve 26.68 Hp Speed 1,180 RPM Guaranteed Max Power on Max Imp Trim 26.68 Hp Number of Stages 1 Flow at BEP 2,236 USgpm Frequency 60 Hz Head at BEP 35.4 ft Impeller Trim 9 88 in NPSH Required 11.9 ft Additional Impeller - Specified NPSH Avail. 33.17 ft Impeller Maximum Trim 9.88 in Specified NPSH Avail. Margin 1.1 Specified Flow 2,292 USgpm Min Flow 559 USgpm Specified Head 34 ft Flow on Max Imp Trim @ Max Power 2,236 USgpm Flow at Design 2,292 USgpm Shut -Off Head 54.3 ft Head at Design 34 ft Shut -Off Disc Pressure 23.5 psi Run -Out Flow null USgpm Fluid Type Water Run -Out Head null ft Water Temperature 68 °F Efficiency at Design 75.00 % Allowable Sphere Size 1.75 in Guaranteed Efficiency at Design 75.00 % Exact Bowl Diameter 14 in Best Efficiency 81 % Curve Id E6414FAPCO Driver Size 30 Hp Thrust K Factor 17 lb/ft Power at Design 24.60 Hp Add Thrust K Factor - Guaranteed Power 26.57 Hp Max Lateral 1 in Flow on Design Trim @ Max Power 2,236 USgpm Total Flow Derate Factor 1 Acceptance Grade 2B Total Head Derate Factor 1 Service Factor No Total Efficiency Derate Factor 1 6/19/2019 FW: P3T BAWA LLPS vertical turbine pump change - Wang, Qiang FW: P3T-BAWA LLPS vertical turbine pump change Larry Weppler < LWeppler@jonescarter.com > Mon 6/17/2019 10:18 AM To:Wang, Qiang <gwang@plwus.com>; cc:Drown, Katy <kdrown@plwus.com>; Ibarra, Antonio <aibarra@plwus.com>; 6 1 attachments (357 KB) BAWA 14FHC 1-Stage.pdf; CAUTION: External email. Do not click links or open attachments unless you recognize the sender and know the content is safe. Dennis — Use this new pump curve for RFP No. 007. Replace the old on with this one. Larry Larry A. Weppler, P.E. Corporate Construction Management Services Iweppler@jonescarter.com JONES I CARTER 6330 West Loop South, Suite 150 B( e, Texas 77401 Telephone 713.777.5337 Ext. 2511 Cell 713.819.2220 Smart Engineering. Smart Solutions.TM www.jonescarter.com From: Trevor Otter Sent: Monday, June 17, 2019 10:15 AM To: Larry Weppler Cc: Vinoth.Manoharan@aecom.com; Bethany Miller; Stephanie Kaspar Subject: FW: P3T-BAWA LLPS vertical turbine pump change Larry, Please see AECOM's approval of the modified pump selection for the LLPS as attached. This curve supersedes both the duty conditions and capacities listed in RFP 007. Thank you, Trevor Otter, P.E. (Texas No.132077) Project Engineer totter@jonescarter.com https://outlook.office365.com/owa/?ltemlD=AAMkADc3ZGZiNjcOLTgxZWOtNGUOZC04M2VILWE4NDIhOWU5YWJhYgBGAAAAAADDaKioTQQmRgn... 1 /2 6/19/2019 FW: P3T-BAWA LLPS vertical turbine pump change - Wang, Qiang JONES I CARTER 6330 West Loop South, Suite 150 ---------------------------------------- Bellaire, Texas 77401 ------------------------- Direct 713.353.7299 Cell 281.460.2052 From: Manoharan, Vinoth(mailto:Vinoth.Manoharan@aecom.com) Sent: Monday, June 17, 2019 10:03 AM To: Trevor Otter <TOtter@jonescartercom>; Zheng, Xuan <xuan.zheng@aecom.com> Cc: Bethany Miller <BMiller@jonescarter.com> Subject: RE: P3T-BAWA LLPS vertical turbine pump change Trevor, Based on the curve provided, the trimmed impeller would give a flow of about 6.73 MGD (4,675 gpm) at high wet well elevation and about 6.32 MGD (4,325 gpm) at low wet well elevation. We approve the trimmed impeller for the LLPS pumps. Thanks, Vinoth From: Trevor Otter [mailto:TOtter@jonescarter.comj Sent: Thursday, June 13, 2019 3:48 PM To: Manoharan, Vinoth; Zheng, Xuan Cc: Bethany Miller Subject: FW: P3T-BAWA LLPS vertical turbine pump change Vinoth, Per our discussion, please see the trimmed impeller from Weisinger/Xylem attached. Once you sign off, we will instruct PLW to use the attached pump for the LLPS pumps. Please review this as soon as possible Thank you, Trevor Otter, P.E. (Texas No.132077) Project Engineer totter@jonescartercom JONES I CARTER 6330 West Loop South, Suite 150 ---------------------------------------- Bellaire, Texas 77401 ------------------------- Direct 713.353.7299 Cell 281.460.2052 This e-mail and any attachments are intended only for the named recipient(s) and may contain information that is legally privileged. confidential, or exempt from disclosure under applicable law. If you have received this message in error, or are not the named recipient(s), you may not retain copy or use this e-mail or any attachment for any purpose or disclose all or any part of the contents to any other person. Any such dissemination, distribution or copying of this e-mail or its attachments is strictly prohibited Please immediately notify the sender and permanently delete this e-mail and any attachment from your computer and/or electronic devices. Any personal views or opinions expressed by the writer may not necessarily reflect the views or opinions of Jones & Carter, Inc. https://outlook. office365.com/owa/?Item I D=AAMkADc3ZGZi NjcOLTgxZWQtNGUOZC04M2VILWE4N DIhOWU5YWJ hYg BGAAAAAADDaKioTQQmRq n... 2/2 GOULDS a xylem brand PERFORMANCE ON DESIGN CURVE AT 1180 RPM SUBMITTAL Quote ID: 9001-190612-075:0:1 QTY: 1 VIT-BAT 14FHC, 1 Stage Shut Off Design [2] Run Out [5] Flow (USGPM) 0.0 2292.0 0.0 1 Best Efficiency 79.00 % at 2198.0 USgpm TDH-Bowl (ft) 51.4 31.8 0.0 Design Flow % BEP 104.28 % TDH-Disch Flange (ft) 50.5 30.9 0.0 Pump Efficiency 76.24 % Bowl Efficiency (%) - 78.60 - Overall Efficiency 0.00 % Guaranteed Bowl Efficiency (%) - 76.24 - INOL Power 23.4 Hp at 2233.0 USgpm Power (Hp) - 23.3 - IGuaranteed NOL Power 24.3 Hp at 2233.0 USgpm Guaranteed Power (Hp) - 24.2 - IMax Power (NOL) at Max Trim 24.8 Hp at 2236.0 USgpm NPSHr (ft) - 11.9 - IGuaranteed Max Power (NOL) 25.8 Hp at 2236.0 USgpm at Max Trim NPSH Margin (ft) - 20.1 - !Specified NPSH Ratio 1.1 Hydraulic Thrust(lb) 873.8 540.6 0.0 ;Thrust Load Power Loss 0.05390 Hp Thrust (lb) 998.4 639.9 0.0 jTotal Flow Derate Factor 1.00 Pressure -Bowl (psi) 22.3 13.8 0.0 'Total Head Derate Factor 1.00 Pressure-Disch Flange (psi) 21.9 13.4 0.0 ITotal Efficiency Derate Factor 1.00 Min Submergence (Inch) - 44.95 - !Actual Submergence 0.00 in Friction Loss (ft) - 0.89 0.00 JShaft Friction Power Loss 0.00 Hp Lineshaft Elongation (Inch) -0.00133 -0.00082 Min Flow (MCSF) 550.0 USgpm Column Elongation (Inch) 0.00000 0.00000 !kWh per 1000 gal 0.00000 Lateral (Inch) 0.12867 0.12918 Elmpeller Running Clearance 0.13 in [11 at 1st impeller eye [21 rated values (3] from bottom of pump [4] from bowl to disch flange [5] based on user entered TDH OPERATING CONDITIONS Pi I nn CHARACTIPIPICTICS Specified Flow 2292.00 USgpm' Fluid '- Water Specified TDH 31.50 ft Fluid Temperature 68.0 °F Rated Speed 1180 RPM Specific Gravity 1.0000 Atmospheric Pressure 14.70 psi Viscosity 1.0017 cP NPSHa at 1st Impeller 32.0 It Vapor Pressure 0.3393 psi NPSHa at Grade 33.9 ft _ Density 62 Ibs/ft' MATERIALS & DIMENSIONS Bowl Da' Bowl Data Bowl Material =_ Cast Iron with Glass Enamel Max Impeller Trim 9.88 in Bowl Material Derate Factor 1.00 Thrust K-Factor 17.0 Lb/Ft Impeller Material Bronze Bowl Pressure Limit 340 psi Impeller Matl Derate Factor 1.00 Available Lateral 1.00 in Bowl Shaft Material 416SS Bowl Assembly Length (BL) 34.76 in Impeller Attachment Taper Lock Disch Bowl Length OLS (01) 6.63 in Taper Lock Material Carbon Steel Disch Bowl Length ELS (1-2) 13.50 in Discharge Bowl Material Cast Iron Bowl Shaft Diameter 2 3/16" [55.6 mm] Suction Type Bell Impeller Balance Manufacturer's Standard Suction Material Cast Iron Impeller Design Enclosed Bowl Bolting Material Carbon Steel Bowl Wear Ring Not Included Sand Collar 304SS Impeller Wear Ring Not Included Pipe Plug Iron Suction Pipe Diameter No Suction Pipe Suction Bearing Bronze Bowl Diameter (D) 14.00 in Discharge Bowl Bearing Bronze Bowl Length (1-3) 13.63 in Intermediate Bowl Bearing Bronze Bowl Flange Diameter (A) 7.13 in Strainer Type Not Included Bowl Flange Thickness (E) 14.50 in Tube Adapter Bearing Not Included Floor Clearance (X) 8.75 in Material Min Column Diameter 10 in impeller Trim _ _ _9.69 in _ _ . __.. Max Column Diameter 12 in DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED Certified By Project Tag PO Number Serial Number ��ouL a xylem brand Max Bowl Shaft Diameter 2.19 in Bowl Shaft Length 40.25 in Bowl Shaft Power Limit 590.08 Hp Bowl Specials SUBMITTAL Quote ID: 9001-190612-075:0:1 QTY: 1 VIT-BAT 14FHC, 1 Stage Motor Data Motor Data Driver Type Vertical Hollow Shaft Motor Motor Provided By Customer Motor Manufacturer Motor Mounted By Customer Motor Speed 1180 RPM HP Rating 25 Hp Phase / Frequency Speed [Poles] 1200 rpm [6 pole] BD 10.0 in Enclosure Mfg Catalog Number Motor Frame Motor Part Number Inverter Duty Driver Size Criteria Max power on design curve Steady Bushing (NOL) Motor Coupling Allow Service Factor No Insulation Class Service Factor Motor Specials Coating Data Bowl OD Goulds Water Technology Standard Blue Enamel Column ID Not Included Column OD Goulds Water Technology Standard Blue Enamel Column Bearing Retainer Not Included Can ID Not Included Testing Data Miscellaneous Specials Coating Data_ _ Can OD Not Included Head ID Not Included Goulds Water Technology Head OD Standard Blue Enamel Enclosing Tube OD Not Included Steel Sub Base Not Included _. _Weight Data _Weight Data Total Bowl Weight 49.3. Ibs Total Weight 493 Ibs Unit Bowl Weight 493 Ibs Total Rotating Weight 58 Ibs INFO, WARNING & ERROR MESSAGES Our offer does not include specific review and incorporation of any Statutory or Regulatory Requirements and the offer is limited to the requirements of the design specifications. Should any Statutory or Regulatory requirements need to be reviewed and incorporated then the Customer is responsible to identify those and provide copies for review and revision of our offer. Our quotation is offered in accordance with our comments and exceptions identified in our proposal and governed by our standard terms and conditions of sale — Xylem Americas attached hereafter. For units requiring performance test, all performance tests will be conducted per ANSI/HI 14.6 standards unless otherwise noted in the selection software submittal documents. Test results meeting with grade 2B tolerances for pumps with a rated shaft power of 134HP or less and grade 1 B for greater than 134HP will be considered passing. Customer is responsible for verifying that the recommendations made and the materials selected are satisfactory for the Customer's intended environment and Customer's use of the selected pump. Customer is responsible for determining the suitability of Xylem recommendations for DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED all operating conditions within Customer's and/or End User's Certified By control. Xylem disclaims all warranties, express or implied warranties, including, but not limited to, warranties of Project Tag PO Number Serial Number ■GOULDS ■ %KTOT5CWWCL yr a xylem brand "L" - UNS-LH 'M- TPI ENSIONS COL [Column Diameter] MIN SUB [Minimum Submergence] BL [Bowl Assembly Length] L [Shaft Turndown Size] M [Shaft Thread Pitch] SU [Shaft Stickup] Certified By Project Tag PO Number OUTLINE DRAWING Quote ID: 9001-190612-075:0:1 QTY: 1 VIT-BAT 14FHC, 1 Stage PUMP DATA 10.00 in Column Diameter 10" [254mm] 44.95 in Lineshaft Diameter 1 in [25.4 mm] Specified Flow 2292.00 USgpm 34.76 in Specified TDH 31.50 ft Motor Manufacturer "1w 1.00 in 12.00 in Driver Type Vertical Hollow Shaft Motor 8.00 in Motor Speed 1180 RPM Phase / Frequency Total Bowl Weight 493 Ibs Unit Bowl Weight 493 Ibs Total Weight 493 Ibs Total Rotating Weight 58 Ibs NOTES 1 Total Pump Length t 1.0 inch. 2 Tolerance on all dimensions is .12 or t .12 inch per 5 ft, whichever is greater. 3 All dimensions shown are in inches unless otherwise specified. 4 Drawing not to scale. 5 %_" NPT — Gauge Conn (plugged) 6 Driver may be rotated at 901 intervals about vertical centerline for details refer to driver dimension drawing. 7 Refer to product IOM for impeller setting requirements. 8 This assembly has been designed so that its natural frequency responses avoid the specific operating speeds by an adequate safety margin. The design has assumed the foundation to be rigid. UNLESS CERTIFIED ULLDS� SGOTWOMOX a xylem brand CROSS SECTION DRAWING Quote ID:9001-190612-075:0:1 QTY:1 VIT-BAT 14FHC, 1 Stage _�-660 66d� r 661 BILL OF MATERIALS ITEM PART NAME CODE ` MATERIAL ASTM# 677 Bowl Assembly 7601 670 660 Shaft - Bowl 2227 SST 416 A582 S41600 673 661 Discharge Bowl 1003 Cast Iron C130 A48 CLASS 30B 672 -- 664 Bearing - Discharge Bowl 1618 Bronze Bismuth B584 Modified 692--- 688 668 Bearing Tube Adapt N/A Not Included N/A 690 — 670 Bowl - Intermediate 6911 Cast Iron C130 Enamel A48 672 Bearing - Intermediate Bowl 1618 Bronze Bismuth B584 Modified 7 W 673 Impeller 1398 Silicon Bronze C87610 B584 677 Taper Lock -Impeller 2242 Carbon Steel 1018 A108 680 Wear Ring -Bowl N/A Not Included N/A 681 Wear Ring - Impeller NA Not Included NA 688 Suction 1003 Cast Iron C130 A48 CLASS 30B 690 Bearing - Suction 1109 Bronze C90300 "G" Mod B584 692 Sandcollar 1205 SST 304 A744M 747 Pipe Plug 1046 Malleable Iron A197 760 Capscrew-Hex 2298 Steel Bolting Gr 8 J429 DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED Certified By Project Tag PO Number Serial Number PERFORMANCE CURVE �GO Quote ID: 9001-190612-075:0:1 QTY: 1 Man LDULDS� VIT-BAT 14FHC, 1 Stage a xylem brand 9. 8 in --- -- - - 50 38 63 - - J 1 40 j'�� 715 78 !-- 78 a 30 70 = 38 53 64 70. 20 76 53 ��._.76 - - 70 10 o------ 20+1 - -t 1 ' s _ Z 0 i t 20 -- a 400 800 1200 1600 2000 2400 2800 US gpm Curve & hydraulic data presented is nominal performance based on ANSI/HI 14.6 acceptance grade 16. Design values are guaranteed within the following tolerances: Flow ± 5%, Head ± 3%, and optionally either Power + 4% or Efficiency - 3% at manufacturer's discretion. CURVE DATA Specified Flow 2292.00 USgpm Shut Off TDH (Disch Flange) 50.5 ft Trim - Specified TDH 31.50 it Shut Off Pressure (Bowl) 22.3 psi Recommended Power 25.00 Hp Rated Speed 1180 RPM Shut Off Pressure (Disch Flange) 21.9 psi Allow Service Factor No Atmospheric Pressure 14.70 psi Bowl Efficiency at Design 78.60 % kWh per 1000 gal 0.00000 NPSHa at Grade 33.9 ft Guaranteed Bowl Efficiency 76.24 % NPSHr at Design 11.9 It NPSHa at 1st Impeller 32.0 ft Best Efficiency 79.00 % NPSH Margin at Design 20.1 ft Fluid Water BEP Flow 2198.0 USgpm Min Submergence at Design 44.95 in Fluid Temperature 68.0 F Design Flow % BEP 104,28 % Thrust at Design 639.9 !b Specific Gravity 1.0000 Pump Efficiency 76.24 % Thrust at Shut Off 998.4 lb Viscosity 1.0017 cP Friction Loss at Design 0.89 it Bowl Material Cast Iron with Glass Vapor Pressure 0.3393 psi Power at Design 23.3 Hp Enamel Density 62 Ibsift' Guaranteed Power 24.2 Hp Bowl Material Derate Factor 1.00 Design Flow 2292.0 USgpm NOL Power 23.4 Hp Impeller Material Bronze Min Flow (MCSF) 550.0 USgpm Guaranteed NOL Power 24.3 Hp Impeller Mat! Derate Factor 1.00 Design TDH (Bowl) 31.8 ft Max Power (NOL) Flow 2233.0 USgpm Total Flow Derate Factor 1.00 Design TDH (Disch Flange) 30.9 It Max Power (NOL) at Max Trim 24.8 Hp Total Head Derate Factor 1.00 Design Pressure (Bowl) 13.8 psi Guaranteed Max Power (NOL) at 258 H .p Total Efficiency Derate Factor 1.00 Design Pressure (Disch Flange) 13.4 psi Max Trim f Curve ID E6414FAPCO Shut Off TDHShut Off TDH (Bowl) it -Max Power (NOL) Flow at Max 2236.0 USgpm DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED Certified By Project Tag PO Number Serial Number 6/20/2019 FW: Follow-up Response from Xylem FW: Submittals: #283.0: Sub... - Wang, Qiang FW: Follow-up Response from Xylem FW: Submittals: #283.0: Submittal 283 LLPS Vertical Turbine Pumps Larry Weppler < LWeppler@jonescarter.com > Thu 6/20/2019 11:54 AM To Wang, Qiang <gwang@plwus.com>; CAUTION: External email. Do not click links or open attachments unless you recognize the sender and know the content is safe. From: Larry Weppler Sent: Thursday, June 20, 2019 11:48 AM To: Katy Drown (kdrown@plwus.com); Dennis Fikes (dennisf@emetalsinc.com); Ibarra, Antonio Subject: FW: Follow-up Response from Xylem FW: Submittals: #283.0: Submittal 283 LLPS Vertical Turbine Pumps SAVE! FYI From: Trevor Otter Sent: Thursday, June 20, 2019 10:56 AM To: Larry Weppler Cc: Bethany Miller; Stephanie Kaspar Subject: RE: Follow-up Response from Xylem FW: Submittals: #283.0: Submittal 283 LLPS Vertical Turbine Pumps Larry, The 1U tolerance submittal curve provided for the LLPS is acceptable, please inform Dennis. Thank you, Trevor Otter, P.E. (Texas No.132077) Project Engineer totter@jonescarter.com JONES I CARTER 6330 West Loop South, Suite 150 Bellaire, Texas 77401 Direct 713.353.7299 Cell 281.460.2052 From: Stephanie Kaspar Sent: Thursday, June 20, 2019 7:56 AM To: Trevor Otter <TOtter@jonescarter.com> Cc: Bethany Miller <BMiller@jonescarter.com> Subject: FW: Follow-up Response from Xylem FW: Submittals: #283.0: Submittal 283 LLPS Vertical Turbine Pumps https://outlook. office365.com/owa/?Iteml D=AAM kADc3ZGZi NjcOLTgxZWQtNG UOZC04M2VILWE4N DIhOWU 5YWJ hYg BGAAAAAADDaKioTQQmRgn... 114 6/20/2019 FW: Follow-up Response from Xylem FW: Submittals: #283.0: Sub... - Wang, Qiang See below. From: Qiang (Dennis) Wang (Pepper Lawson Waterworks) (mailto:jones&carter notifications@procoretech.coml Sent: Thursday, June 20, 2019 7:55 AM To: Stephanie Kaspar <SKaspar@jonescarter.com> Subject: Follow-up Response from Xylem FW: Submittals: #283.0: Submittal 283 LLPS Vertical Turbine Pumps BAWA 6 MGD Surface Water Treatment Plant Project More details View online I iew PDF From: Qiang (Dennis) Wang (Pepper Lawson Waterworks) Date: Thursday, June 20, 2019 at 07:55 am CDT Sent To: Stephanie S. Kaspar, P.E. (JonesCarter, Houston) CC: Katy Drown (Pepper Lawson Waterworks) Bethany Miller (JonesCarter, Houston) Qiang (Dennis) Wang (Pepper Lawson Waterworks) Larry Weppler (JonesCarter, Houston) Attachments: None Hi Stephanie, Please see the response from Xylem concerning the new curve: "Your curve has a 1 B tolerance. My submittal curve has a 1 U tolerance per the specification requirements. " Please advise if it is acceptable. Thanks, Dennis Sent from Procore https://outlook. office365. com/owa/?ItemID=AAMkADc3ZGZi NjcO LTgxZWQtNGU OZC04M2VILWE4NDIhOWU5YWJ hYg BGAAAAAADDaKioTQQmRgn... 2/4 6/20/2019 FW: Follow-up Response from Xylem FW: Submittals: #283.0: Sub... - Wang, Qiang Submittal Item Details Project: BAWA 6 MGD Surface Water Treatment Plant Project Spec Section: 11021 -Vertical Turbine Pumps Submittal #: 283.0 Title: Submittal 283 LLPS Vertical Turbine Pumps Type: Product Information Responsible Contractor: Pepper Lawson Waterworks Received From: Antonio Ibarra Ball In Court: Stephanie S. Kaspar, P.E. Approvers: Kaspar, P.E., Stephanie S. (JonesCarter, Houston) Weppler, Larry (JonesCarter, Houston) Confirmed Delivery Date: 05/02/19 Final Due Date: 05/10119 Description: Attachments Approver: Date: Response: Attachments. - Comments: Item: Vertical Turbine Pumps - Low Lift Pump Station Submittal 283 LLPS Vertical Turbine Pumps .pdf Kaspar, P.E., Stephanie S. (JonesCarter, Houston) Sent: 05/03/19 Returned: Pending None None Approver: Weppler, Larry (JonesCarter, Houston) Date: Sent: Returned: Response: Pending hftps://outlook. office365.com/owa/?lteml D=AAM kADc3ZGZi NjcOLTgxZWQtNGU OZC04M2VI LWE4N DIhOWU5YWJhYg BGAAAAAADDaKioTQQmRgn... 314 6/20/2019 FW: Follow-up Response from Xylem FW. Submittals: #283.0: Sub... - Wang, Qiang Attachments: None Comments: None More details: View online iew PDF Powered By Procore I support@procore.com I https Usupport.procore.com This e-mail and any attachments are intended only for the named recipient(s) and may contain information that is legally privileged, confidential, or exempt from disclosure under applicable law. If you have received this message in error, or are not the named recipient(s), you may not retain copy or use this e-mail or any attachment for any purpose or disclose all or any part of the contents to any other person. Any such dissemination, distribution or copying of this e-mail or its attachments is strictly prohibited. Please immediately notify the sender and permanently delete this e-mail and any attachment from your computer and/or electronic devices. Any personal views or opinions expressed by the writer may not necessarily reflect the views or opinions of Jones & Carter, Inc. https://outlook.office365.com/owa/?Iteml D=AAMkADc3ZGZiNjcOLTgxZWQtNGUOZC04M2VILWE4NDIhOWUSYWJhYgBGAAAAAADDaKioTQQmRgn... 414 WESTFALL MANUFACTURING CO. 15 Broad Common Road Bristol, RI 02809 info(@westfallmfg.net www.westfallmfg.com QUOTATION 021219-162800-02 February 12, 2019 TO: PLW Waterworks FROM: Newman Regency Group (281) 980-7448 Jeff Rebenschied, P.E. ATTN: Dennis Wang, Ph.D., P.E. EMAIL: ieff ,newmanregency.com FAX/EMAIL: gwangnu,plwus.com REF: Westfall Static Mixer WE ARE PLEASED TO OFFER OUR QUOTATION FOR THE FOLLOWING ITEM QTY DESCRIPTION UNIT PRICE EXTENDED A 2 16" WESTFALL STATIC MIXER MODEL 2800 PVC MOUNTING RING (1) .8 BETA PVC MIXING PLATE (3)'/a" INJECTION PORTS (2 PLUGGED WITH PVC PLUGS) (2) 1/8" NSF-61 EPDM GASKETS MIXER IS MADE WITH NSF-61 CERTIFIED MATERIALS $ 20,480.00 $ 40,960.00 B 2 'Id' CPVC CORP STOPS WITH PVC SOLUTION TUBES $ 800.00 $ 1,600.00 NOTES: 1) MIXER IS DESIGNED TO BE INSTALLED BETWEEN 150# FLANGES WESTFALL MANUFACTURING CO. TERMS: NET 30 DAYS BY: SHIPMENT: 2-5 WEEKS ARO Please sign and return original copy. FREIGHT PREPAID AND ADD Retain duplicate copy for your records. FOB: BRISTOL, RI ACCEPTED BY: TITLE: DATE: O&M MANUALS: FIRST TWO: NO CHARGE ADDITIONAL O&M MANUALS: $20 EACH ***QUOTE IS VALID FOR 30 DAYS. ORDERS PLACED AFTER THIS TIME WILL BE PRICED TO REFLECT CURRENT MATERIAL COST** HEADLOSS CHART pipe ID 15.25 inches Pipe area 1.2684 ft2 MODEL 2800 MODEL 2800 MODEL 2800 MODEL 3060 MODEL 3060 MODEL 3050 0.7 BETA 0.8 BETA 0.9 BETA SINGLE DOUBLE TRIPLE GPM CFS fUs psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss 569 1.268 1.00 0.22 0.09 0.05 0.004 0.008 0.011 1139 2.537 2.00 0.88 0.37 0.18 0.015 0.030 0.044 1708 3.805 3.00 1.97 0.82 0.41 0.034 0.068 0.099 2277 5.074 4.00 3.51 1.47 0.73 0.060 0.122 0.176 2847 6.342 5.00 5.48 2.29 1.14 0.094 0.190 0.276 3416 7.611 6.00 7.89 3.30 1.64 0.135 0.274 0.397 3985 8.879 7.00 10.74 4.49 2.24 0.184 0.372 0.540 4555 10.147 8.00 14.03 5.87 2.92 0.240 0.486 0.706 5124 11.416 9.00 17.75 7.42 3.69 0.303 0.616 0.893 5693 12.684 10.00 21.92 9.17 4.56 0.375 0.760 1.103 6262 13.953 11.00 26.52 11.09 5.52 0.453 0.920 1.335 6832 15.221 12.00 31.56 13.20 6.57 0.539 1.094 1.588 j 4 16" WESTFALL STATIC MIXER MODEL 2800 PVC MOUNTING RING (1) .8 BETA PVC MIXING PLATE (3) 3/4" NPT PORTS WITH PVC HOUSING (2) 1 /8" NSF-61 EPDM GASKETS SHOWN WITH: (3) 3/4" CPVC CORP STOPS WITH PVC SOLUTION TUBES Q 20.250 MIXER OD D i-015.250 MIXER ID CLIENT APPROVAL: APPROVED BY. DATE: a 1 a 4 I 10141ka" 2.750 MOUNTING RING THICKNESS FLOW ------> F I I 2.000 LAYING LENGTH�� WITH GASKETS WESTFALL MIXER WESTFALL 2800 16" MODEL 2800 - 16" DIMENSIONS ARE IN INCHES (UNLESS OTHERWISE NOTED) " rNo. WESTFALL MANUFACTURING COMPANY r15BROAD CO—Ots ROAD. BRWOl RID°.SA D1-]53M f:4D1-ne.w w109w EI �"� DM 10.14.2014 C DRA-81 MGP " " PROv Br s . a' a I NEWMAN REGENCY GROUP �►����� WATER/WASTEWATER EQUIPMENT HOUSTON • AUSTIN • DALLAS/FT. WORTH • OKLAHOMA WESTFALL MANUFACTURING CO. 15 Broad Common Road Bristol, RI 02809 infona,westfallmfg.net www.westfalimfg.com (REVISED) QUOTATION 021219-162800-05-NRG May 6, 2019 TO: PLW Waterworks ATTN: Dennis Wang, Ph.D., P.E. EMAIL: gwang a,plwus.com FROM: Newman Regency Group (281) 980-7448 Jeff Rebencshied, P.E. (713) 582-7448 EMAIL: jeff(a�newmanreEency.com REF: Westfall Static Mixer WE ARE PLEASED TO OFFER OUR QUOTATION FOR THE FOLLOWING ITEM QTY DESCRIPTION UNIT PRICE EXTENDED A 1 16" STATIC MIXER MODEL 3050 $ 23,665.00 $ 23,665.00 SCH40 CARBON STEEL CONSTRUCTION (2) ROWS OF (4) CARBON STEEL MIXING ELEMENTS (1) -/<" PORT WITH 316SS HOUSING (2) CARBON STEEL RFSO 150# FLANGED ENDS INTERIOR COATED WITH 3M SKOTCHCOAT 134 COATING EXTERIOR COATED WITH RUSTOLEUM PRIMER B 1 3/4" STAINLESS CORP STOP WITH HASTELLOY SOLUTION TUBE $ 2,250.00 $ 2,250.00 NOTES: 1) MIXERS ARE DESIGNED TO BE INSTALLED BETWEEN 150# FLANGES TOTAL: $ 25,915.00 WESTFALL MANUFACTURING CO. TERMS: NET 30 DAYS BY: SHIPMENT: 4-5 WEEKS ARO Please sign and return original copy. FREIGHT PREPAID AND ADD Retain duplicate copy for your records FOB: BRISTOL, RI ACCEPTED BY: TITLE: DATE: O&M MANUALS: FIRST TWO: NO CHARGE ADDITIONAL O&M MANUALS: $20 EACH ***QUOTE IS VALID FOR 30 DAYS. ORDERS PLACED AFTER THIS TIME WILL BE PRICED TO REFLECT CURRENT MATERIAL COST** Newman Regency Group - 12705 S. Kirkwood - Ste. 140 - Stafford, TX 77477 HEADLOSS CHART pipe ID 15.25 inches MODEL 2800 MODEL 2800 MODEL 2800 MODEL 3060 MODEL 3050 MODEL 3050 MODEL 6000 0.7 BETA 0.8 BETA 0.9 BETA SINGLE DOUBLE TRIPLE GPM fus psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss 562.5 0.99 0.21 0.09 0.04 0.004 0.007 0.011 0.008 1125.0 1.98 0.86 0.36 0.18 0.015 0.030 0.043 0.033 1687.5 2.96 1.93 0.81 0.40 0.033 0.067 0.097 0.074 2250.0 3.95 3.42 1.43 0.71 0.059 0.119 0.172 0.132 2812.5 4.94 5.35 2.24 1.11 0.091 0.185 0.269 0.207 3375.0 5.93 7.70 3.22 1.60 0.132 0.267 0.388 0.298 3937.5 1 6.92 10.48 4.38 2.18 0.179 0.364 0.528 0.405 4500.0 7.90 13.69 5.73 2.85 0.234 0.475 0.689 0.529 5062.5 8.89 17.33 7.25 3.61 0.296 0.601 0.872 0.670 5625.0 9.88 21.40 8.95 4.45 0.366 0.742 1.077 0.827 6187.5 10.87 25.89 10.83 5.39 0.442 0.898 1.303 1.001 6750.0 11.86 30.81 12.89 6.41 0.527 1.068 1.550 1.191 WESTFALL STATIC MIXER MODEL 3050 SCH40 CARBON STEEL CONSTRUCTION 2 ROWS OF (4) CARBON STEEL MIXING TABS P 1 3/4" 316SS INJECITON PORT WELDOLET 150# RFSO CARBON STEEL FLANGE ENDS INTERIOR COATED WITH 3M SKOTCHCOAT 134 COATING EXTERIOR COATED WITH RUSTOLEUM PRIMER SHOWN WITH: (1) STAINLESS CORP STOP WITH HASTELLOY SOLUTION TUBE E D 023.50 FLAP Ic A CLIENT APPROVAL: APPROVED BY: DATE' PRINT NAME: TITLE: COMPANY: E 16.00 PIPE OD 0 15.25 PIPE ID FLOW -----> IXER WESTFALL WE ESTFALL STATICMODEL 050—M6" DIMENSIONS ARE IN INCHES (UNLESS OTHERWISE NOTED) WESTFALL MANUFACTURING COMPANY SCALE DALE 10.27.2014 15 BROAD COAWION ROAD, ERWOL RIDC USA P:�01-151119RF. a01-Z5365.N1 www.weiXdml9-comDRAWNSY MGP C 9Y APPRO 6Y 5 3 E R environmental E1 2 improvements Inc. 1183 Brittmoore RD 100 Houston, TX 77043 ph 713 461 1111 Customer: PLW Waterworks Attn: Dennis Wang Phone: 346-413-0503 Quotation DATE: DELIVERY: TERMS: FOB: We are pleased to have the opportunity to offer you the following quotation. Please sign and fax back along with your purchase order or alternate method of payment. By signing below you authorize Environmental Improvements, Inc. to provide the above mentioned items. Thank you, Signature 5/9/19 3-4 weeks Net 30 Factory unit Extended $775.44 $160.92 $ 775.44 $ 160.92 Total $936.36 Austin Dallas Houston Tulsa COHEN INDUSTRIAL SUPPLY COMPANY 1922 KNOLL STREET HOUSTON, TEXAS 77280 (713)467-3300 DATE: 6/11/19 ADD: T0,TAjL:$ 12,367.40 DELETE: TOTAL.(' S50.72) TOTAL:$ PROJECT: P3T -BAWA STATIC MIXER CHANGE CONTRACTOR: PEPPER LAWSON LOCATION: LLPS /_111931 TAG QTy. DESCRIPTION COST TOTAL 981.1 1 16 X 2'8-3/4" FLG X FLG $2,034.00 $2,034.00 W/ 1" HOLE :1 -$t,529.10 960.1 1 24 X 10'8-1/8" FLG X FLG $5,605.20 $5,602.20 W/ 1" HOLE 1055.1 2 24 X 2 SERVICE SADDLE $ 350.00 $ 700.00 1055.2 2 2 X 3/4 BRONZE BUSHING $ 21.70 $ 43.40 1055.3 1 2 X 1 BRONZE BUSHING $ 21.70 $ 21.70 1055.4 1 %" SCH80 45 BEND $ 2.50 $ 2.50 1055.5 10 316SS UNISTRUT $ 12.95 $ 129.50 1055.6 2 %" 316SS US CLAMP $ 2.50 $ 5.00 1055.7 2 316SS US BASE $ 150.00 $ 300.00 1055.8 1 FREIGHT $ 2,000.00 $ 2,000.00 DELETE: TAG QTy. DESCRIPTION COST TOTAL 981 1 16 X 3' FLG X FLG DI PIPE CL ($651.32) ($651.32) 960 1 24 X 12' FLG X FLG ($2,287.60) ($2,287.60) 1055 1 FREIGHT —RETURN $ 2,000.00 $ 2,000.00 1056 1 RESTOCKING $ 900.00 $ 900.00 Authorization Signature: painling PIVIC-ok-nal'. Inf June 19, 2019 Attention: Brian Buttry Brian Buttry I Superintendent T. 281-907-8600 1 C. 205-704-0903 bbuttry@plwUS.com I p1wUS.com Reference: Low lift Station Revised Piping and Mixer Attention: Brian, QUOTE# 19-075 Painting Professionals, Inc is pleased to submit our Lump Sum proposal for the above referenced project. Our pricing includes supervision, labor, equipment, miscellaneous materials and all tools necessary to complete the scope of work as outlined herein. Our proposal, associated pricing and clarifications are based on information received from job walk, scope and Email. Should you have any questions or require any additional information, please do not hesitate to call. Best Regards, Edward Ware Painting Professionals Office: 713-461-0004 Cell: 307-431-0087 E-Mail: edApaintingprofessionals.com wincing pfoksmonA4. line We are pleased to submit our scope for the following project. If at any time during the duration of the project, an unplanned scope of work is incurred or plant outage causing a delay, a change order will be submitted. Scope of Work: ■ Sandblast SSPC SP-10 ■ Apply 2 coats of Carbogaurd 60 and one coat carbothane 134 HG to customer spec. ■ Color —TBD per pipe spec ■ Hold for inspection and document on daily QC reports. Items included in pricing: 1. All labor. 2. All equipment needed for preparation & application. Items to be supplied by customer: Crew Size: 3 2 applicators 1 supervisor/NACE inspector Painting Professionals, Inc agrees to perform above work in a timely manner for a total price of Low lift Station Revised Piping & Mixer: $ 6,200.00 1. TUms of Payment: Terms of payment are that payment is due net thirty (30) days after submittal of invoice. 2. Proposal Term: This proposal is valid for 90 Days. P.11king A rvlv-s Onatt, Inc =MOD We are pleased to submit our scope for the following project. If at any time during the duration of the project, an unplanned scope of work is incurred or plant outage causing a delay, a change order will be submitted. Scope of Work: ■ Sandblast SSPC SP-10 ■ Apply 1 coats of Carbogaurd 60 to customer spec. ■ Color — TBD ■ Hold for inspection and document on daily QC reports. Items included in pricing: 1. All labor. 2. All equipment needed for preparation & application. Items to be supplied by customer: Crew Size: 3 2 applicators 1 supervisodNACE inspector Painting Professionals, Inc agrees to perform above work in a timely manner for a total price of Low lift Station Protective Coating Removal and Re -apply Primer: $ 4,200.00 PRICING CLARIFICATIONS 1. Terms of Pam Terms of payment are that payment is due net thirty (30) days after submittal of invoice. 2. ProRosal Term: This proposal is valid for 90 Days. z. Painting j • wresslonals. !r MMMG Acceptance of Proposal The undersigned on behalf of the owner or his agent accepts the terms and conditions above and agrees to the above prices and terms as quoted plus any agreed to and authorized additional work. Should a Purchase Order be issued in lieu of a signature, this document will be recognized as an addendum to the Purchase Order. Date: Signature: Painting Professionals,Inc agrees to perform the work in a timely manner for a total price (plus applicable sales tax) with payment due 30 days from completion of work. This proposal may be withdrawn in 90 days if not accepted. Ptw waterworks April 20, 2020 Mr. Andrea Brinkley Assistant Director Baytown Area Water Authority The City of Baytown 2401 Market St. Baytown, TX 77520 Re: CPR No. 45 BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. 1806021 Mrs. Brinkley, The prefabricated metal building added steel column at gridline B.8 and 1 is causing clearance conflict with the overhead coiling door. There is an 8" clearance requirement needed for the Trolley Rail System that connects to the edge of the overhead door frame. The CMU column addition, the overhead door cannot be installed in that location. PLW is proposing to add CMU brick in order to gain the required clearance for the motor. This change will result in a increase in the amount of $6,474.63 Please feel free to contact me at (713) 301-8637 with any questions or concerns. Regards, P�LWW Waterworks 74 Katy Drown Project Manager Page 1 Baytown Area M ater Authority BAW A 6 MGD Surface Water Treatment Plant BAWA Job No. 1806021 CML' OH Change Scope of Work CMU OH Door Change CPR No.: 8045 Date: 04: 18.20 PLN Job No.: P3T Non -Tried Labor Material Subcontract Taxed Mat'I/Equip Item Unit Total Unit Total Unit Total Unit Total No. Description Qlv Unit Cost Cost Cost Cost Cost Cost Cost Cost I CMU OR Door Change 11 Masons) Modifications 1 LS $ - S - S - i - S 4,300.00 S 4 500 00 $ - S - 12 Behar 1 LS S 250.00 S S - S - S - S - S - S - 13 Scaffolding 1 LS S - S - S - S - $ - S - S 65000 S i•:i• Duca Cost Subtotal 250101 - 410000 65000 Small Tools a 5 0•. 1230 Na Na Equipment Burdcn Qt 5000. Na M., Na Na Ta\ a 8 25•. Na Na 5361 Subtotal 2 262 5i) - 4 500 00 70161 Orenccad & foil 77 15 0•. 3938 67500 10554 Subtotals 10188 - 517500 80917 Bonds & Insurance a 3 0•, 906 15525 2428 Subtotal 31091 3 33025 83344 Total of all columta 6 474 61 Othcr Grand Total Cost 6,474.63 P, y' - RFI #148 Jones & Carter, Inc. Project: 09986-0001-00 - BAWA 6 MGD Surface Water Treatment Plant 6330 West Loop S #150 Project Bellaire, Texas 77401 5359 E Grand Parkway S Phone: (713) 777-5337 Baytown, Texas 77520 Phone:2814228281 Overhead Door Column Location Conflict TO: Larry Weppler (JonesCarter, Houston) FROM: Antonio Ibarra (Pepper Lawson Waterworks) DATE INITIATED: 10/17/2019 3701 Kirby, Suite 1133 Houston, Texas 77098 LOCATION: STATUS: Closed PROJECT STAGE: DUE DATE: 10/20/2019 SUB JOB: COST CODE: COST IMPACT: Yes (Unknown) SCHEDULE IMPACT: DRAWING NUMBER: SPEC SECTION: LINKED DRAWINGS: REFERENCE: RECEIVED FROM: Antonio Ibarra (Pepper Lawson Waterworks) COPIES TO: Andrea Brinkley (City of Baytown), Brian Buttry (Pepper Lawson Waterworks), Cole Buttry (Pepper Lawson Waterworks), Dana Buttry (Pepper Lawson Waterworks), Katy Drown (Pepper Lawson Waterworks), James Harris (Aecom), Dale Hughes (City of Baytown), Antonio Ibarra (Pepper Lawson Waterworks), Jose Luis Lopez (Pepper Lawson Waterworks), Joseph (Joey) Tocci (Pepper Lawson Waterworks), Vikki Unsell (Pepper Lawson Waterworks), Qiang (Dennis) Wang (Pepper Lawson Waterworks) Question•m Antonio lbarra (Pepper. • 1 on • • Per the prefabricated metal building submittal 160 response, the added steel column at gridline B.8 and 1 is causing clearance conflict with the overhead coiling door. There is an 8" clearance requirement needed for the Trolley Rail System that connects to the edge of the overhead door frame. Due to the CMU column addition, the overhead door cannot be installed in that location. PLW is proposing two options. Please see the attachments to get more clarity on the proposed options. Please be advised, a change order will be forthcoming depending on the choice of option. Attachments: Submittal AQ6A - Overhead Cgiling_Doors..(2).pdf RFI 148.odf Official Response: (Katie) Xuan Zheng (Aecom) responded on Monday, November 4th, 2019 at 3:51PM CST Please find the attached for the response. Attachments: RFI #148 Overhead Door Column Location Conflict-Response.pdf Official Response: Ryan Stephan (Joiner Architects) responded on Monday, October 28th, 2019 at 8:42AM CDT Architect confirms option 1 is acceptable. Attachments: All Replies: Please find the attached for the response. I Attachments: )verhead_DoQr_Column_Location Conflict-Response.pdf Jones & Carter, Inc. Page 1 of 2 Printed On: 11/14/2019 09 :11 AM espy1,57E eg- a -O6iner Architects) at o8:42AM.O'n 10/28/2019 optionArchitect confirms ... BY DATE COPIES TO RFI #148 Jones & Carter, Inc. Page 2 of 2 Printed On: 11/14/2019 09:11 AM