BAWA Resolution No. 2020-15 RESOLUTION NO. 2020-15
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE BAYTOWN
AREA WATER AUTHORITY AUTHORIZING CHANGE ORDER NO. 12
WITH PEPPER LAWSON WATERWORKS, LLC, FOR THE BAWA 6 MGD
SURFACE WATER TREATMENT PLANT PROJECT IN THE AMOUNT OF
THIRTY-FOUR THOUSAND FIFTY AND 84/100 DOLLARS ($34,050.84);
AND PROVIDING FOR THE EFFECTIVE DATE THEREOF.
BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE BAYTOWN AREA
WATER AUTHORITY:
Section l: That the Board of Directors of the Baytown Area Water Authority does
hereby authorize Change Order No. 12 with Pepper Lawson Waterworks, LLC, for the BAWA 6
MGD Surface Water Treatment Plant Project. A copy of said change order is attached hereto,
marked Exhibit "A" and made a part hereof for all intents and purposes.
Section 2: That the Board of Directors of the Baytown Area Water Authority hereby
authorizes the payment of an amount not to exceed THIRTY-FOUR THOUSAND FIFTY AND
84/100 DOLLARS ($34,050.84) to Pepper Lawson Waterworks, LLC, consistent with the
change order authorized in Section I.
Section 3: This resolution shall take effect immediately from and after its passage by
the Board of Directors of the Baytown Area Water Authority.
INTRODUCED, READ and PASSED by the affirmative vote of the Board of Directors
of the Baytown Area Water Authority this the 2151 day of October, 2020.
BRENDA BRAD1 EY SMITH, President
ATTE T:
N WA
yo -74-
LETICIA BRYSCH, Assistant Secretary T +—
=4 }— X�
� m
S �Y;
APPROVED AS TO FORM:
Kkff9
N h7fiORNER, General Counsel
RAKaren Anderson\RESOLUTIONSIBAWA\'-)020.10.211Resolution-Change Order No. 12 Pepper Lawson.doc
EXHIBIT "A"
BAYTOWN AREA WATER AUTHORITY
Change Order No. 12
6.0 MGD SURFACE WATER TREATMENT PLANT
BAYTOWN PO: 1806021
Date: 12-Oct-20
Brie escription of Changes:
CO 12.1 is for 2 knife gate valves installed in place of plug valves to avoid maintenance issues in the fututre.
CO 12.2 is for removing 2 Westfall Model 2800 Static Mixers and accessories and replacing with 1 Westfall 3050 static mixer and
accessories and modifying piping at the LLPS Metering Station.
CO 12.3 is for modification of an overhead door due to previous CMU column addition at the Operations Building.
Add or Delete Items:
Item Descrf lion Unit Quantity nit Price Toh
12.1 2 Knife Gate Valves Change(PCO r±20) 1 LS 21,072.43 $ 21,072.43
12.2 Static Mixer Replacement(PCO t26) 1 LS 6,503.78 $ 6,503.78
12.3 Overhead Door Modification(PCO#45) 1 LS 6,474.63 $ 6,474.63
Total $ 34,050.84
Contract Summary: Original Revised
1 Original Contract Price $52,186,000.00
2 Owner Contingency $0.00
Previous Change Orders
This Change Order
Remaining Contingency
3 Change Orders
Previous Change Orders $ (3,292,805-76)
This change order $ 34,050.84
4 Revised Contract Price $52,186,000.00 $48,927,250.08
Original Contract Duration 1095
Previous Extensions 0
This Change Order 0
Revised Duration-Calendar Days 1095
�. �1
/Ci /3 Zt) rjU'� `✓ ��-- 10/14/2020
Contractor: PLW Waterworks, LLC Date Director of Public Works�zingineering Date
GmtliTLopesPncetE,Executive Vice President
�o-r�-2ozo
Consultant: Jones I Carter,Inc. Date City Manager Date
waterworks
March 11,2019
Mr.Ajay Shakyaver
Assistant Director
Baytown Area Water Authority
The City of Baytown
2401 Market St.
Baytown,TX 77520
Re: CPR No. 20
BAWA 6 MGD Surface Water Treatment Plant
BA WA Job No. 1806021
Mr. Shakyaver,
The originally designed depth of the 12" plug valve at the backwash line connecting the backwash
EQ basin and the backwash pump station will cause maintenance issue in the future.Therefore,per the
Enigneer's recommendation and the attached RFP 002,PLW is proposing to replace the 12" plug valve
with the 12" knife gate valves which will be installed inside the backwash pump station as shown on
the revised Sheet 13-M-I. Total of two knife gate valves with stem guides and accessories will be
installed per the Drawing.
The knife gate valve change will result in a cost increase of $21,072.43
Please find the attached PLW cost summary and associated reference material for your review and
acceptance. Please be noted,should any additional costs be incurred as a result of this Work due to
clarifications,changes or unknown scope, PLW will seek reimbursement.Clarifications and exclusions
are listed on subcontractor's proposal.
If you have any questions or need additional information,please do not hesitate to call me
at 713-301-8637,or kdrown@plwus.com.
Regards,
PLW Waterworks
Xti
aty Drown
Project Manager
Page 1
Raytown Area Water Authority CPR No.: 20
RAWA 6 MGO Surface Water Treabross,Plant Data: 03/11/19
RAWA Jab N.1806021 PLW Job No.: P3T
Knife Gate Valve Change
Scone tripper
Furnish and Install(2)Knife Gate Valves and Accessories at the Backwash Pump Station and Rotative(I)Plug Valve per the Engineer's Recommendation and RFP 2
Nov-Taxed
Labor ISfalerial Subrontrart Tamed 8lia'" u
Item Unit TOW Unit Total Unit Total Unit Total
No. Desvi time Q1, Unit Cost Cost Coat Coal Cast Cost Cost Coss
1 PLWCoordination
Pmjcct Manx,. 2 FIRS S 9800 S 196.00
Project Engineer 4 HRS S 96.M S 30400
Project Supemmindent 4 23RS S ULDID S 484.00
2 Knife Gate Valve end Guide Stem
KGC Valve and Guide Stun Material(Dezurik) 2 EA S 5,403.41 S 10,80682
KGC Valve and Guide So.Installation Later
(1)Forcman 8 HRS S 46,50 S 332M
(2)Laborer 32 B I S S 28 40 S 908 80
(1)Opemtor-Lu11 8 HRS S 4400 S 35200
(1)L011 1 DYS S - 5 65000 S 65000
(1)30 Ton Cone 2 DYS S - S 1,150.00 S 2,30000
(1)Operate,-Crane 16 HRS $ 4 'w 5 10400
(1)Scissor Lill 2 DYS S - S 33250 S 665.W
(1)A,Finer 32 HRS S 3000 $ 950.00
Additional bolting hardware I LS S 50000 S 50000
Confined Spare Safety Equipment I IS $ - S 500M S 500.00
3 Delete 12"Plu,Valve per Plans
Delete 12"Plug Valve Mmedal Tuomrik) I EA S(2,0800) S (2,68800)
DAeo 12'Plug Valve Labor
(1)Forman 2 HRS $ 46,50. S (9300)
(2)Labored 8 HRS S 28.40 $ (22720)
(p Opeotm 4 HRS $ M,w $ (176007
(I)Imll 1 DYS 5 65000 S (65000)
Direct Cost Subtotal I,38460 8,61882 - 3,46500
Small Tools®508 18923 Na - Na Na
Equipment Darden aQ 50.M. Na Na Na 1(73250
Tax ra 0ON Na Na Na
Subtotal 3,97393 8,61882 - 5,19750
Overhred&pmfit rd I5.011. 59609 129282 77963
Suboal3 4,56990 9.911M - 5,937.13
Roods&Insurance 0 10Y. 133.10 29235 13931
Subtotal 4]0).00 I0.20S 99 6 I56.94
Total of columns 2107243
Oil,
(;road'l otal Cost 21,072.43
a
i
Paget
Order ## : 622504 Customer Acknowledgement (This is Not a Bill)
Date : 03-01-19 Order Date : 10.23-2018
Customer : 135556 Tax No Tax USA Sales order : 622504 Mork Order :472241
Customer P.O.: 2018CP3T-00021000 Rep Contact : Joey Justice
Carrier : Dezurik Choice Ship Point : Sartetl, MN
Project Name : BAWA - Surface WTP DEZURIK ONLY Page 10
DEZ CUST UNIT ACKNOWLEDGED l
ITEM ITEM ITEM REV PROJECT FF QUANTITY UNIT PRICE AMOUNT SHIP DATE
38 9690043 001 623949 112 1.00 ea 2,688.00 2,688.00 HFA
DeZURIK-PEF,12,F1,CI,NBR,CR,04C-S30SCC*GB-6A-N
TAG: SPECIAL TAG
41 9690206 13l 2.00 ea 4,248.20 8,496.40 01-23-2019
DeZURIK-KGC,I2,ES,F1,S1,SMP,S1-W*NN-N-SI,ENTS*EO5211
TAG: SPECIAL TAG
-EXTENDED NUT ON NON-RISING STEM, C/L OF VALVE TO TOP OF NUT = 306IN (25'-611)
Change Order Text Acknowledged Date Changed - Old Date -> - -
42 1278671 8 101 2.00 ea 1,155.21 2,310.42 02-08-2019
GUIDE STEM 1-1/4 5960 TRUM
TRUMBELL GUIDE - 367-5960
SHIP KITH ITEM 41
Change Order Text : Acknowledged Date Changed - Old Date -> - -
S
THIS ORDER ACKNOWLEDGEMENT INCLUDES THE TERMS AND CONDITIONS ON THE REVERSE SIDE HEREOF.
OJONESICARTER RFP NO.: 002
REQUEST FOR PROPOSAL(RFP)
1. PROJECT NAME: 6 MGD Surface Water Treatment Plant 2. 1&C PROJECT NO.: 09986-0001-00
3. CONTRACTOR: Pepper Lawson Waterworks 4. SUBMITTED TO: Dennis Wang
S. SUBJECT: Backwash Pump Station Knife Gate Valve 6. REFERENCE:Submittal No.26
7. REF.DWG.NO.: 13-M-1&13-M-2 8. REF.SPEC.NO.: 15101
9. DESCRIPTION OF WORK: (The Contractor is requested to furnish a price proposal for the below described work. Please complete,sign,date,and
return a proposal at your earliest convenience. Please attach a detailed cost breakdown to your proposal.
The Backwash Pump Station and corresponding isolation valve shall be constructed according to the attached reissued
construction drawing sheets 13-M-1 and 13-M-2.The 12"Knife Gate Valve shall be Dezurik Model KGC-ES or approved equal with
the following specifications:
- ANSI 150 flanged ends
- 304 stainless steel body and gate
- Standard braided packing to 500 degrees F
- Chloroprene seat to 180 degrees F
- 304 stainless steel extension including couplings,rod,bearing plate and supports.
Please provide credit information for the change from the eccentric plug valve, extension and valve box to the knife gate valve
and accessories per the attached drawings.
12. Requestor's Name&Signature: Larry Weppler Date: 8/6/2018
The Contractor acknowledges that this RFP Is to be used to request pricing Information only,and does NOT constitute a contract modification. The Contractor
I• Is NOT AUTHORIZED/DIRECTED to perform this work UNTIL/PRIOR TO written notification that a contract modification is approved.
I:wp\don\const\forros\di or rfp\dpforrr.dm
REV 9.+Iu00
Z.
iB ci
cE
#1 aAll, = d
LL
'Al
I I
I� $
F 'c. 41 I I
it
y, A L L 6 6 L
6 z � g 6 '
a
. Y
a
�33
d9
a �
a+
F
I b
Z O IE h 4
Q to F f eyj
a �i NCri
p
} i any • g 5 72 {
t �a�
mm 7 �4 a
� y11
11 r'
2 file $g
.z�. d
F
I{ s6a a say
a•
C rerCD
ilk
, " ED
SAJ
w � cutt!
waterworks
October 21,2019
Mr. Vinoth Manoharan
AECOM
5444 Westheimer Rd.#1400
Houston,TX 77056
Re: CPR No. 26 Rev 2
BAWA 6 MGD Surface Water Treatment Plant
BAWA Job No.
Mr. Manoharan,
PLW is submitting the attached PCO#026 in accordance to the RFP 4007 dated on May 21st,
2019, and RFP#007 Rev I dated on June 17th, 2019, concerning the LLPS Metering Station Piping
and Vertical Turbine Pump Modifications. PLW proposes to make the following changes on the above
mentioned work per the Engineer's comments:
1. Remove two (2) Westfall Model 2800 Static Mixers and accessories per Original Sheet 0-M-4.
2. Add(I) Westfall Model 3050 Static Mixer and accessories per RFP#007.
3. Modify LLPS Metering Station Piping per RFP#007 Sheet 4-M-3.
4. Modify LLPS Vertical Turbine Pumps per RFP#007 Rev 1.
The modifications on the LLPS Metering Station Piping and LLPS Vertical Turbine Pumps
will result in a cost increase of$6,503.78.
Please find the attached PLW cost summary and associated reference material for your review and
acceptance. Please be noted,should any additional costs be incurred as a result of this Work due to
clarifications, changes or unknown scope, PLW will seek reimbursement.
If you have any questions or need additional information, please do not hesitate to call me
at 713-301-8637, or kdrown@plwus.com.
Regards,
PLLWWW Waterworks
K' aty Drown—
Project Manager
Page 1
B,mxn Area Water AnlhOrily CPR No.: 26
BAWA 6 31GD Surface Water Treatment PLna Date: 10/21/19
BAWA Job No.1806021 PLW Job No.: P3T
LLPS Metering Station Static blixer and VTP Modifications
Saone of Wn.
Replace tno(2)%"stfall Model 2800 Static Misers udm One(1)WesBall Model 3050 Static Mixer,revise the LLPS Metering Station Piping,add one(1)sample lap at the Rapid Miser Basin influent
lam,-d modify the vertical turbine pumps and esparedd..j0ints at the LLPS per So RFP 9007
Noo-Taved
Lubnr Material Subcontract LI—I NIUPDEtm
Item Unit Total out, Toul Poir Tutul I'nh Total
No. Dearriuims Q11 Unit Cost Cost Cost Cart Cost Curl Ca.t Coss
I PLWSupsrsislan
LI Pmjas Manager D His S 98 D0 S -
1.2 Pmjues Englnecf It His S 74.110 S -
1.3 Pmjat S.,Rsmasndem 11 HR $ 12100 $ -
2 Wenlall Susie Miser Modificadom
2_I Delete Mudd 2800 Sulie Miaar 2 EA 5 (211,48000) 5 (4096000)
2.2 Delete Solution Tube Armanblier PVC 2 EA $ ISIDRO) S (Lb.0000)
23 Add Mount 3050 Su0e Mixer 1 EA 5 23.f.6300 S 23.663(11)
24 Add Solution Tube Around,Striate,Smal 1 EA S 2.2511011 5 2.250 RD
25 Add lojeaion Arescolies to Raw Water Line I LS S 93636 5 936.36
3 LLPS Menem,Smun.Piping Mudils.omm
3A LLPS hlnering Stalion Piping Fabrication and Ddlsss 1 LS S In,838 11 5 I0,838.30
32 LLPS Meaning Station RcvirN Piping Pmtmiivc Coaling 1 LS S6.200.110 5 62010110
3.3 LLPS Manrng Station Ddivemd Piping per Original Durgin Credit I LS $ (3892) 5 (38 92)
Jet LLPS Metering Smtinn Dal—red Piping Pumesuw Coming Rcnmral 1 LS 5 4.200 00 $ {20000
and Reapply Primer I LS
J Vertical Turbine Pump Modification
i.l Vertical Turbine Pump Modifications I LS S - S -
Ducat Con Subtotal - (4,9D926) 10,400al) -
Smdl Tools'a,50 - Ma - n/a Na
Equipment Burden a 5D.0r. Na nA W. -
Tas'n.8.25% n/a Wo
SubDnd2 - (49n926) 10,40000 -
Oeeebe'dk PmGI+/151E°. 173639 "Root
SublomlJ - 1564565) 11960.00 -
Bond,M h-a'uw b J 1". I6937 358.80
Sublmal4 15 a1502) 12319,80
Tout of all---as 6,50378
Omer
Grand Total Cost 6,503.78
Page 2
J ❑ N E S CARTER RFP NO.: 007
REQUEST FOR PROPOSAL (RFP)
1. PROJECT NAME: 6 MGD Surface Water Treatment Plant 2. AC PROJECT NO.: 09986-0001-00
3. CONTRACTOR: Pepper Lawson Waterworks 4. SUBMITTED TO: Dennis Wang.
S. SUBJECT: Westfall Static Mixer 6. REFERENCE:Submittal No.262
7. REF. DWG.NO.: 4-M-3&6-M-1 S. REF.SPEC.NO.: 11512&11021
9. DESCRIPTION OF WORK: (The Contractor is requested to furnish a price proposal for the below described work. Please complete,sign,date,and
return a proposal at your earliest convenience. Please attach a detailed cost breakdown to your proposal.
The Low Lift Pump Station flow metering station shall be constructed according to the attached reissued construction drawing
sheet 4-M-3.
— The 16"static mixer shall be the Westfall Static Mixer Model 3050 per the attached cut sheets.
— The piping and chemical layouts of the flow metering station shall be in accordance with the reissued construction
drawing.
Addition of a sample valve as shown on the reissued construction drawing sheet 6-M-1.
The Low Lift Pump Station Vertical Turbine Pumps shall be constructed with the following design changes:
— Design Flow(1't Design Point):2,387 gpm
— Total Head(1"Design Point):32.3 ft
— Design Flow(2nd Design Point) :2,213 gpm
— Total Head (2nd Design Point):35 ft
Please provide cost increase/decrease information for the changes to the Low Lift Pump Station flow metering station and Low
Lift Pump Station.
11. Requestor's Name&Signature: Larry Weppler Date: 5/21/19
The Contractor acknowledges that this RFP is to be used to request pricing information only,and does NOT constitute a contract modification. The Contractor
is NOT AUTHORIZED/DIRECTED to perform this work UNTIL/PRIORTO written notification that a contract modification is approved.
l:wp\flocs\wnst\forms\rfl or rfp\rfpform.doc
R V 9/14/00
>' T
J YS Ya.win
o•rc�:'sr-�RiR-o•o
NO1 O S ri MOl NO1 V S drill 1 II MOl
1 3 L313 ! 1 1 d ! V
2i31atlND181 3S
ONV NVId 8313VI MOl! �� 1 :-✓Y�✓Vvv-v v vv^ �w
NO11V1S dmnd 1lll MOl ��v ✓� �\-��; j��. .z_LNrld am co
lr arM vvirea�5 ran o � I I � !I %�J as-•�\ (ad < �z..E....v)G.xn.,,� /��- ,o Jdly�.x a::• t'AJr `• ....v.t I1 i/t J:o+J� I_`//` <
>11Q�Ml�t tl�1rM V3tlr W,()1>16
o.. .m.•.o.rar .e4, I �
p Yff'•'iwo�si. �I ` I J b 1
„
tx.-r6:::Gr•k WA—
0'I 1.tf...3ul I—tire,
IK IV f!
M31A NVId OAR MOl NOIlr15 drills 1!1 MO I
.Ky W-It0„fJ•wtIuM✓•J A9l•0>�•w••6tp•st./D•aI...,e�M..wJJ xfili ` ) !�t�.'l v �,-. ,�.+ tS y l - /-y _"c---V D�--�v—�---v'-'----- a.n1 uv VVVV v- .v.�-V.V. —
1 vu o
-a- ,
--'--.-.......... - -... ..........- )-- - __._ a Lre.w:_,! s: { Y � I ti(.i✓� ���J ,F _ � ,f' o
—_- :Ix wJ i).•Itw•QJ r.>.r/w-l. (i I, ( f' i� S i!I:J.I'�,' 'r��i .,J �J `J VV V `�„I b
G COI :Yi`O Qv� 0. t Y Y t
rvS••S..waw+f.o ..q.ai.•w.+5 !i ) �. l9 I �i /t J:0'.'1
IK«f.I.oOs^f•Yr.M...rp u:'uD.AJ :: ;-- -_--.--... 4 Ya..� �\�j
,tJ
..w,t•.••w:aa0o 9.n9-e>c•9WJ,9: I � ",yy-D �/� >r -r/.
^"v,rw„1 r/-s-a l.s!14+•g,..eaa.s.: D �`•._.`✓-^ :' s-', a7J.O.ccg ..%%
„E..I•ro w t<t ey aub i /9x-nJB-,/•><++4.w1Y.9. J �-.r^r�-^ `^�
.aq• • Oe•S tf•t.D ( •cGM.MD-9: D .Hc.
•s9 s.Of-.-I,K ae Er a Ow,�«G I o•0.gJ�!.9: f
S31ON w'0«S!C••f/4w«•r.•w>d 9i ^I^J1 9i
.C-.•.Y�G 71, P•D•wJ wrpy. uJ-9...>! J .. i !-.:: .f-9
f� J-S-J IK':Iq•K/..awnf 90 �:.- /„-'+�
53�'+JCS5JJ,iv G.tir 3-a?vn.
>
f I 1:
N I
N
------- -----------
A V
I . ss-
4- A 1
c—I "q 'S.»s.•C—A— I i C
IA I-
IFAS
TTT--
gill
I rA
r !!!mr
t
6 WGO su"ACE*All*
Ma
7
PULSED BED CLARIFIER
PLAN
—————11T-
JONESICAStTER
11
...r« ` PULSED CEO CLARIFIER PLAN VIEW
WESTFALL STATIC MIXER MODEL 3050
SCH40 CARBON STEEL CONSTRUCTION
�111
2 ROWS OF 4J CARBON STEEL MIXING TABS
13/4"316SS�NJECITON PORT WELDOLET
# RFSO CARBON STEEL FLANGE ENDS
INTERIOR COATED WITH 3M SKOTCHCOAT 134 COATING _
EXTERIOR COATED WITH RUSTOLEUM PRIMER
SHOWN WITH:
�1)STAINLESS CORP STOP WITH HASTELLOY SOLUTION TUBE
0
023.50 FLANGE 0
0 16.00 PIPE OD
O O O
O �15.25 PIPE ID
O O
0 o FLOW
O o .....> m v7!
o O
0 0
36.00 FLGxFLG LENGTH
CLIENT APPROVAL: WES TFAL L WESTFALL STATIC MIXER
APPpOVEO ar: Are MODEL W50-I N'
Pi91f NANf: 1111E WAENWMAXWW4R WI GT16iW6ENG1®�
NESiFALLA LWACI GCWPAW 109.POlA
MGP W305Q8 f•umAM* _ YEFY••�Vl vw'vpMA1X rnn
• o a • ' f I �
I
Model 3050 Series
Mixer
US PATENT PENDING
The Perfect Mixer for Pressure-Limited Operation
The Westfall 3050 Mixer consists of a pipe fitted with one, two or
three sets of strategically placed vanes, each occupying one diameter
of length. The vanes create vortices and multiple zones of turbulence
that intersect to produce optimal mixing when there is very low available
head. Its unique geometry makes the mixer resistant to fouling. In
addition, "Since the device was originally designed as a flow conditioner,
Four tapered and curved vanes it is also very effective at mitigating any swirling flow that is created
with precisely designed geometry turn flow inside out to mix fluids upstream, and creating a fully developed flow profile," according to
or gases, while generating two Kimbal Hall at Alden Research Laboratory.
to four times less headloss than
other mixers. L�
The k-value is 0.58 44 �tq. atpr y
and the CoV is.057 rdat,
Cross section of
Westlall 3050 Mixer
The addition of a second
row of vanes aligned with S�9�P Sf
the first row provides a'9P rL/j
additional mixing as the key'
vortices intersect and overlap La�oe
in a braiding effect. `'`�'�^;, �Sa
gib•
The k-value is 1.13 and �.
the Co V is.026.
Three sets of vanes in s9a�rkel
S
alignment produce a k�a�
k-value of 1.64 and Fla `Pa -
a CoV of.014.
+ �A
xPo Westfall's Model 3050 Mixer series
provides consistent mixing with very
Th little headloss, ideal for situations with
�Sra very low available head.
9P
M�kP k
Lague`
7 64
Westfall 3050 Staged Mixer
CFD Results
tow --..
-<- Single-stage Mixer
Cross section of
Westfall 3050
y— Two-stage Mixer
w—Three-stage Mixer
3
a The CoV values for
Model 3050 Low Headloss
a Static Mixer were
01Q — determined for:
• single-stage
• two-stage
• three-stage
I
n t ] 3 C 6 6 7 a 9 in
Distanc<Dovmstmmol MMer Inlet(l/Di
APPLICATIONS
Alden Research Laboratory, Inc.performed numerical + Municipal and
simulations using the CFD software package FLUENT V6.3.26, Industrial Water Treatment
a state-of-the-art, finite volume-based fluid flow simulation + Potable Water
package, to calculate the three-dimensional, incompressible, + Waste Water
turbulent flow through the pipe and around the mixer. + Chlorination/De-Chlorination
The model geometry was developed using the commercially + Chemical Blending
available three-dimensional CAD and mesh generation software, + Dissolving Gases
GAMBIT V2.4.6 and the computational domain generated for + Contact Chambers
the model consisted of approximately 2 million hexahedral and + Flocculant Blending
tetrahedral cells. westfallmfg.com/alden + Anaerobic Digestion
♦ Dewatering
♦ pH Control
ADVANTAGES + Contacting
♦ Product Blending
• Mixes well in situations with low head and is resistant to fouling
• Creates minimal headloss—two to four times less than other mixers
• Reduced laying length—just one diameter per stage i
• Can be fabricated from PVC, FRP, 316 Stainless Steel,
with or without Teflon coating Westfall Manufacturing Company
• Is available in pipe diameters from 112" to 120" 15 Broad Common Road • Bristol, RI 02809-2721
• Low cost, easy installation Voice: Toll Free: 888-928-3747 or 401-253-3799
Fax: 401-253-6530 • E-mail: info®westfallmfg.net
• Long service life and low maintenance requirements www.westfallmfg.com
Westfall Innovates — others Imitate
1012010
RFP NO. 7
Baytown Area Water Authority
6 MGD Surface Water Treatment Plant
SECTION 11021
VERTICAL TURBINE PUMPS
PARTI-GENERAL
1.1 SCOPE
A. Contractor shall provide all labor,materials,and equipment as shown and specified to furnish and install all vertical
turbine pumps,complete and operable.
B. Equipment shall include electric motor, pump column,shaft, base, impellers, bowls, bearing,suction inlet bell,sole
plate,and all appurtenances.
1.2 RELATED SECTIONS
A. Related sections include but are not necessarily limited to:
1. Division 0—Bidding Requirements,Contract Forms,and Conditions of Contract
2. Division 1—General Requirements
3. Division 3-Concrete
4. Division 9—Coatings
5. Division 11-Equipment
6. Division 15-Mechanical
7. Division 16—Electrical
1.3 REFERENCES
A. Comply as a minimum with applicable provisions and recommendations of the following standards:
1. American National Standards Institute(ANSI)
2. American Society for Testing and Materials(ASTM)
3. Anti-Friction Bearing Manufacturers Association(AFBMA)
4. Hydraulic Institute
5. Institute of Electrical and Electronic Engineers(IEEE)
6. National Electric Code(NEC)
7. National Electrical Manufacturers Association(NEMA)
8. Steel Structures Painting Council(SSPC)
1.4 SUBMITTALS
A. Provide submittal data,manuals and drawings as specified in Section 1340,Shop Drawings.
B. Pump Data:
1. Certified pump curves shall identify cut-off point, rated point, and a minimum head at which the pump
operates without vibration and cavitation.Curves shall be corrected for pump losses and shaft friction HP
losses. Pump losses shall include column and discharge head losses. For pumps that are to be operated by
variable speed units, provide a minimum of five curves with at least three different speeds between the
maximum and minimum rpm of the pump.
2. Submit certified characteristic curves showing head-capacity relationship, brake horsepower, net positive
suction head requirements, pump efficiency (ratio of water horsepower to brake horsepower), pump
thrust,and pump speed.
i. Curves shall be complete over the entire range of operation from shut-off to zero head conditions.
09986-0001-00 11021-1 CONFORMED SET
Rev. Per Add.No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
3. Submit manufacturer's L-10 bearing life calculations for radial and thrust bearings at pressure heads and
flow rates shown.
4. Submit manufacturer's specifications, engineering data, pump weight,dimensions, coating requirements,
size,parts list,and illustrations.
5. Minimum submergence required over suction bell,critical distances from structural floor and walls.
6. Impeller Diameter
7. Diameter of pump can(if applicable).
8. Maximum downward thrust and upthrust in pounds exerted by pump.
9. Schematic diagrams illustrating utility requirements such as air,water,drainage,etc.for each component.
10. Detailed mechanical and electrical plans and elevation drawings showing the equipment dimensions,size,
and location of connections and weights of associated equipment including single largest component.
11. Power and control wiring diagrams,including all sensory and control devices,terminals,and numbers;such
as RTD connection diagrams, anti-condensation heater connection diagrams, and vibration sensor
connection diagrams.
12. Alarm and shutdown level trip points for specified motor enclosure, winding and bearing resistive
temperature detectors(RTD's),and vibration monitors.
13. A schedule for all shop testing and delivery of equipment to the job site.
14. Factory finish and system.
15. Test reports.
C. Manufacturer's Certifications
1. Submit manufacturer's certification that Contract Documents have been examined by the manufacturer for
proposed electrical, mechanical,and structural systems affecting performance of the pumping equipment.
2. Submit manufacturer's certification that the maximum power requirement, if used, shall not exceed the
motor rating under operating conditions on the pump characteristic curve.
3. Submit seal manufacturer's certification that the seal is designed for service and application specified and
is installed and aligned properly.
4. Submit Manufacturer's statement indication that the required lateral and torsional critical speed analyses
have been performed and that the specified critical frequency limitations will be met.
5. Submit manufacturer's statement indicating that the design of the pumping units avoids the natural
frequencies of the existing Pump Station's structure.
6. Pump manufacturer is responsible for certifying that the variable speed drive unit is compatible with the
pump and motor allowing full compliance with the job conditions and performance requirements specified
herein.
D. Motor Data
1. Horsepower
2. Electrical characteristics
3. Bearing life ratings
4. Insulation ratings
5. Weight
6. Thrust Bearing
7. Other data to provide a complete description
E. Instruction Books
1. Service and maintenance manual
2. Service parts list
3. Outline drawing
09986-0001-00 11021—2 CONFORMED SET
Rev. Per Add.No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
1.5 QUALITY ASSURANCE
A. Use new materials of high grade,and with properties best suited to the work required.
B. Pumping units and motors shall be the product of manufactures with at least ten(10)years of successful experience
in the design, manufacturing and application of pumping units of the type, size and performance capabilities as
specified.The pump manufacturer shall have at least three similar size pumps of the model,type,and size of pump
in service and operational for at least five(5)years. Manufacturers shall provide a list of references for the same.
C. All components of the pump shall be supplied, assembled, and warranted by one of the approved pump
manufacturers. Pump components shall not be acquired from separate entities and assembled as a final product by
a manufacturer's representative.
D. Factory Tests:
1. Provide certificates of the non-witness factory test of the entire pump assembly, with driver fully
assembled, to demonstrate compliance with the specifications and to verify guaranteed performance of
the pump.The factory test shall include the actual flow,total dynamic head,pump horse power,and pump
efficiency for all the duty points listed. Test pump and recirculate water for at least one hour under
simulated service conditions. The Contractor shall submit the factory test certification to the Engineer
before the pumps are shipped and delivered.Give pump bowls an operational test at the factory to check
for excessive vibration and for leaks in all piping and seals.Test pump and recirculate water for at least one
(1)hour under simulated service conditions.
2. Provide certified factory test reports to the Engineer for review and approval prior to pump delivery.
3. The motors installed shall be tested by the motor manufacturer and a full written report provided to the
engineer. The testing shall be performed in accordance with IEEE 112 method B at 60 Hz.The test shall
include percent slip,no load current,full load current,locked rotor current,locked rotor torque,efficiency,
and power factor at the frequencies listed above,megger,winding resistance and higher potential.
4. The manufacturer shall perform both lateral and torsional critical speed analyses on the assembled
pumping units to identify and ensure that:
a. The first lateral critical speed shall be at least 25 percent above the specified pump speed.
b. No torsional natural frequencies occur within a range extending from 25 percent below to 25
percent above the specified pump speed.
C. Any blade excited resonant frequency shall be no closer than plus or minus 25 percent of the
natural frequency of any part of the installed assembled pumping unit.
d. On VFD applications, both Goodman &Gerber fatigue analyses will be performed on the shaft to
verify shaft fatigue strength is acceptable.
E. Delivery,Storage,and Handling:
1. Store equipment off the ground in enclosed shelter. Store and maintain equipment in accordance with
manufacturer's direction.
2. Deliver materials to the site to ensure uninterrupted progress of the Work.
3. Deliver anchor bolts and anchorage devices which are to be embedded in cast-in-place concrete in ample
time to prevent delay of Work.
4. All boxes, crates, and packages shall be inspected by the contractor upon delivery to the site. Contractor
shall notify Engineer of any loss or damage to equipment or components.Replace losses and repair damage
to new conditions,in accordance with manufacturer's instructions.
09986-0001-00 11021—3 CONFORMED SET
Rev. Per Add. No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
F. In-Place Test:
1. Perform a complete pump test including static and pumping levels, flow rates, motor amperage, and all
other information normally checked on a maintenance-type pump test. Include flows and meter readings
at three different points on the curve, and repeated for a total of 3 different operating speeds for VFD
applications.
1.6 OPERATIONS AND MAINTENANCE DATA
A. The manuals shall be prepared specifically for this installation and shall include all required cut sheets, drawings,
equipment lists, descriptions, etc. In addition to the requirements of Section 1340, the manuals shall include the
following at a minimum:
1. Complete column assembly,pumping equipment,discharge head,oiler,parts list,test reports,maintenance
data and schedules,spare parts information,and cross-referenced to exploded view of assembly drawings.
2. Dimensional drawings for all provided components with their respective weights.
1.7 WARRANTY
A. Warranty:
1. For a period of 12 months from final acceptance,the manufacturer shall warrant that the equipment shall
be free of defects in material and workmanship under normal use and service,and when properly installed.
The manufacturer shall repair or replace such equipment or any part thereof furnished by the manufacturer
and found defective after inspection by the manufacturer.
B. Performance Guarantee:
1. In consideration that the award of this equipment is based on performance representations as shown on
the plans,the manufacturer/Supplier shall guarantee the performance of each pumping unit to perform as
represented.
2. Represented performance will be verified via factory and field testing as defined herein.
3. Pumping units failing to perform as guaranteed during factory testing will be subject to performance
penalties as defined in paragraph C below.
4. Pumping units failing to meet minimum specified performance during factory testing will be rejected
outright by the Owner.The manufacturer shall be responsible for any liquidated damages resulting from
any delay associated with failure to meet minimum specified performance during factory testing. The
manufacturer liquidated damage liability is limited to 10%of the unit price on the applicable Bid item value.
5. The guaranteed performance of each specified pumping unit shall be stated by the Manufacturer.
C. Performance Penalty:
1. If the owner chooses to accept a unit that does not meet the minimum pump efficiency, a penalty of
$10,000 per 1% per unit will applied. The penalty will be used to offset the additional cost of electricity
incurred by the Owner over the operational life of the pumping units.
2. The calculated performance penalty(if applicable)will be deducted from the manufacturer's subsequent
progress payment request or requests(as appropriate).
09986-0001-00 11021—4 CONFORMED SET
Rev. Per Add.No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
PART II-PRODUCTS
2.1 GENERAL
A. Description:
1. Provide new vertical, multistage turbine pump complete with electric motor and all other appurtenances
for a complete operating pumping system.Select pump and motor combination on overall efficiency.Pump
shall conform to ANSI B58. 1-1961 "American Standard for Vertical Turbine Pumps" and the Hydraulic
Institute Standards for Centrifugal Pumps.
B. The pump shall have a Capacity vs. Head curve with an increasingly rising slope steeper or equal to the slope of the
line between the two(2)duty points.
C. Select equipment which is designed and built for continuous service at all points on pump curve, without
overheating,without cavitation,and without excessive vibration or strain.The pump shall have a continuously rising
head-capacity,characteristic curve.
D. Pumps shall meet the following design conditions:
Design Conditions LLP-P-100,200,300 TPS-P-100,200,300 HSP-P-100,200,300
Use/Location Raw Water/Low Lift Transfer Pump High Service Pump
Pump Station Station Station
Number of Pumps Required (Phase 1) 3 3 3
Variable or Constant Speed Variable Variable Variable
Design Flow(15t Design Point) (gpm) 292- 2,387 2,083 2,083
Total Head(1"Design Point)(ft.) 36- 32.3 57 175
Minimum Bowl Efficiency(1"Design 75 73 80
Point)
Design Flow(2nd Design Paint)(gpm) +6092,213 1,775 2,350
Total Head(2nd Design Point)(ft.) 36- 35 68 150
Minimum Bowl Efficiency(2n1 Design 70 70 76
Point)
NPSHa(ft) 38 41.85 40.85
Motor Size(hp) 30 50 150
Max.Operating Speed (rpm) 1,770 1,800 1,800
Lubrication Oil/Grease Product Product
Shaft Type Enclosed Open I Open
E. Performance Requirements:
1. Each pumping unit shall be capable of pumping the flow and head as shown.
2. Each pumping unit shall operate from runout to shutoff head condition without exceeding the motor
horsepower.
3. Each pumping unit shall operate smoothly without abnormal noise, vibration, or excessive heat over the
defined range of operating conditions.
4. Each pumping unit shall operate smoothly over its entire range as defined by the Hydraulic Institute's
Allowable Operating Range.Vibration shall not exceed the limits set by the current edition of the Hydraulic
Institute Standards within the pump's Preferred Operating Range or within the pump's Allowable Operating
Range.This vibration limit applies to both the top of the pump and the top of the motor.
5. Each pumping unit shall be designed and fabricated so as to limit operating sound pressure levels to 85 dBA
in any direction at a distance of 3-foot from the equipment over the defined flow range.
09986-0001-00 11021—5 CONFORMED SET
Rev. Per Add. No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
6. Each pumping unit shall be designed and fabricated so as to limit heat generation and gain to that specified
herein over the defined operating flow range.
2.2 ACCEPTABLE MANUFACTURERS
A. Provide vertical line shaft pumps of one of the following:
1. Pentair Fairbanks
2. Ruhrpumpen
3. Flowserve
4. Goulds
5. Sulzer
6. Patterson
B. Provide motors as specified in Section 16013.
2.3 PUMP BOWL ASSEMBLY
A. Provide pump bowls fabricated of fine grained,high tensile strength iron,ASTM A 48,Class 30 or better,with smooth
surfaces devoid of blow holes and other irregularities. Use clean,sound casting without defect.Do not plug,weld or
otherwise repair defects.
1. Furnish bowls able to withstand a hydrostatic pressure twice the pressure at rated capacity or 1Y times
shutoff head,whichever is greater.
2. Equip bowls with replaceable stainless steel wear rings on the suction side of enclosed impellers.
3. Pump bowls shall have electrostatically bonded,fused epoxy coating on the inside only.
B. Install impellers of the enclosed type.
1. Use zinc-free bronze or stainless steel impellers, balanced hydraulically and dynamically.
2. Equip impellers with stainless steel collets.
3. Do not coat impellers with porcelain,enamel,or any other material.
4. Securely fasten the impellers on the shaft by a split-tapered lock bushing.
C. Employ a zinc free bronze suction case bearing, packed with insoluble grease, and protected against entry of sand
or other abrasives.
D. Provide zinc free bronze bowl bearings,water or oil lubricated,securely fastened to the bowl.See Section 2.1.1)for
lubrication requirement for different applications.
E. Provide sufficient lateral in the pump bowls to allow operation at shutoff head and at run-out.
F. Pumps,as an assembled unit,shall be compliant to NSF/ANSI Standard 61 and Annex G and meet the requirements
of the US Safe Drinking Water Act of 2014.
2.4 COLUMN
A. Pump columns shall be ANSI threaded and coupled ASTM A53 or ASTM A120 steel of flanged and bolted construction
in lengths not exceeding 5 foot and a minimum wall thickness of 0.375-inches. Columns shall be interchangeable
with identical flanged ends that are parallel faced and machined accurately with a register fit to insure proper
alignment.All flanged hardware shall be Type 316 stainless steel with anti-seize compound. Provide two lifting lugs
and support brackets on all column sections and bowl assemblies. Pump discharge head shall be fabricated
identically to columns. Pump discharge shall be as shown on the Drawings with a minimum 3-piece fabricated
discharge elbow with 150 lb ANSI flanged ends. Pump columns shall be designed to hang down into the pump well
with no lateral braces. Pump column sections shall be marked to indicate their installation sequence.
09986-0001-00 11021—6 CONFORMED SET
Rev. Per Add. No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
2.5 SHAFT
A. Provide pump shafts which are machined,precision ground and polished.Select shafts of ample size to operate the
pump without distortion or vibration.Ample size is larger than determined by Section A4.3.3,of the latest revision
of AWWA E-101. Provide bearing support for shaft above and below each impeller. Line shaft shall be furnished in
interchangeable sections not over S feet in length and shall be coupled with high grade, machined steel couplings.
Shafting shall be straight to within 0.003 inches TIR at any point along the length of the shaft.Any shaft not meeting
this requirement shall be replaced. Repairing or straightening will not be allowed.The pump line shaft and motor
shaft shall each be of solid shaft construction. Shafts shall have butting faces, machined square to the axis of the
shaft to insure accurate alignment. Couplings shall be designed with a safety factor of 1.5 times the shaft design
strength and shall be of the split ring key type to prevent uncoupling in the event of backspin. Motor to pump
couplings shall be rigid 3-piece and shall be adjustable for use in impeller lift adjustments.Shafts shall be marked to
indicate the installation sequence.
2.6 SHAFT ENCLOSING TUBE
A. Shaft enclosing tube shall consist of interchangeable sections not over 5-feet in length of Schedule 80 ASTM A53
Grade B steel pipe to receive bronze couplings which will act as line shaft bearings.The bearings shall be made of
ASTM B584 C903 and shall have a spiral groove in the inside surface to promote the downward movement of
lubricant in the tubing.Tubing shall be sized to fit inside the column pipe and house the shaft.
2.7 CENTRALIZERS
A. Provide rubber centralizing spiders in the column pipe to hold the shaft on enclosing tube in the center of the
column. Install one spider per join of column.
2.8 LIFTING,ALIGNMENT,AND ACCESS
A. Provide two(2)lifting lugs with support brackets capable of supporting the weight of the entire pump and motor.
B. Provide the motor support pedestal with an accurate,machine-registered fit for alignment of the driver.
C. Provide suitable openings for each access to the mechanical seal.
2.9 MECHANICAL SEAL
A. Provide a balanced single cartridge mechanical seal with a vent and flush port on gland, floating seal rings and a
static O-ring.The adjusting studs and nuts shall be stainless steel for the mechanical seal housing.The materials shall
be 316 stainless steel for all metal components,graphite-loaded sintered silicon carbide for the rotating seal ring,
sintered silicon carbide for the stationary seal ring,hastellow C-276 for the spring,and Viton or Fluoroelastomer for
the 0-ring. Provide%-inch(%")diameter galvanized pipe from pump head to a point along the ground to carry any
water that leaks past the mechanical seal to the ground away from the pumps.
2.10 DISCHARGE HEAD
A. Provide a fabricated steel discharge head with separate base plate and ANSI Class 125 flanged outlet above ground.
The fabricated head shall be supplied with four-equally spaced 2-inch schedule 80 pipes connecting the top motor
mounting plate to the bottom head plate on all VFD driven pumps. Discharge heads shall be designed and provided
by pump manufacturer.
09986-0001-00 11021—7 CONFORMED SET
Rev. Per Add. No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MG Surface Water Treatment Plant
B. Discharge head shall be designed to carry the maximum down-thrust which the electric motor can handle.
C. Sole Plate:
1. Provide a sole plate large enough to span the opening in the support structure. Attach the plate to the
suction barrel.
2. The sole plate must be suitable for mounting the discharge head.
3. The pump manufacturer must furnish all the hardware for securing the head to the sole plate. Foundation
bolts will be supplied by the Contractor.
D. Lubricator and Immersion Heater:
1. Three(3)gallon nominal capacity welded steel reservoir with integral mounting foot.
2. Hinged waterproof cover that opens past 90 degrees and has a hasp for a padlock.
3. Oiled interior,epoxy primed exterior.
4. Fluid level indicator and fluid level sensor.
5. 150W maximum, 120 volt, 60Hz immersion heater in a moisture resistant enclosure with thermostat,
adjustable 30 to 110 degrees F.
6. Solenoid valve with bypass, 120V,60Hz molded coil—NEMA 4 enclosure for outdoor use.
7. Toggle valve for flow control of oil to bearing,outlet%-inch copper tubing.
8. Oiler shall be full at time of start up.
2.11 SUCTION BARREL(PUMP CANS)
A. Prefabricated steel pipe suction barrels shall be provided as shown on the plan sheets. Suction barrels with
anticipated flows in excess of 3,000 gpm shall have internal straightening vanes and an inlet pipe splitter plate, as
required by HI latest standards.Suction barrels wall thickness and top flange thickness are shown below.All suction
barrels shall have the top flange shipped loose,with jack bolts to assist in leveling,for field leveling&welding.Each
top flange shall have a drilled and tapped bolt pattern that is equal to a standard 150#flange. These holes shall
straddle centerline of the can inlet.The top surface shall have a minimum surface finish of 125 RMS and include an
0-ring groove with O-ring for sealing purposes.A gasket will not be acceptable.The barrel inlet shall be as shown on
the plan sheets and shall be flanged with an AWWA C207-94 Class D steel flange.A vertical splitter plate shall be
provided in the inlet pipe the entire length of the inlet.The bolting to attach the discharge head to the suction barrel
will be 18-8 SST&furnished by the barrel manufacturer.The barrel length shall be as shown on the plan sheet and
shall have a bottom cap plate in equal thickness to the top flange.Four(4)evenly spaced,3"x 3"x 3/8"angles,with
a 1" holes in each, shall be welded to the outside diameter on the barrel to assist the installing Contractor in
mounting and aligning the suction barrel.The barrel shall be fitted with two(2)W couplings to serve as a vent for
the barrel. All suction barrels shall be equipped with internal straightening vanes and anti-vortex cross in the can
bottom.
B. The suction barrel shall be blasted and coated as described in the Specification 09920.The coating must meet the
requirements of NSF 61 for potable water applications.
C. The top flange of suction barrels and soleplates shall be leveled to within.002 of an inch per foot of diameter of the
flange.
Suction Barrel Outside Diameter* Top Flange Thickness* Barrel Wall Thickness*
16"—24" 1-1/2" 0.375"
30" 1-3/4" 0.375"
36" 2-3/8" 0.375"
42"—60" 2-1/2" 0.375"
*Minimum Values
09986-0001-00 11021—8 CONFORMED SET
Rev. Per Add.No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
2.12 ELECTRIC MOTOR FOR PUMPS
A. Refer to Section 16013 ELECTRIC MOTORS under Division 16,Electrical for motor information.
2.13 NAMEPLATES
A. Provide each pump and motor with a standard nameplate securely affixed in a conspicuous place showing serial
number and name of the manufacturer.
1. Pump Nameplate. Each pump nameplate will show capacity in gallons per minute at rated speed in
revolutions per minute and head in feet.
2. Motor Nameplate.See Electric Motor section in Division 16.
3. Number the pumps with six-inch (6") or larger stencils using black alkyd paint. Pump numbers are to
correspond to wiring in motor control center.
2.14 VORTEX SUPPRESSOR/BASKET STRAINER
A. Raw water pumps shall have a vortex suppressor/basket strainer installed on the pump's suction. The vortex
suppressor/basket strainer shall be constructed to meet the following requirements:
1. Performance requirements:
a. Approach velocity:3.0 feet per second,maximum,at design flow
b. Net open area:65 percent
2. Design requirements:
a. Configuration: Basket-type with solid bottom plate and internal straightening vanes.
b. Screen:0.120 inch woven wire cloth on 5/8"centers
C. Materials:Wire cloth to be 316 stainless steel material.All other materials to be 304 stainless steel
with a minimum thickness of 3/16".
d. Mounting: Bolted to the pump suction bell using 5/16"minimum diameter 18-8 SST bolts. "Clips"
are not acceptable
PART III-EXECUTION
3.1 INSTALLATION
A. Install all equipment and connecting piping in accordance with manufacturer's instructions.Prior to testing and start-
up,inspect to verify the system is complete.
B. No form of energy shall be turned on to any part of the system prior to approval of factory authorized service
representative.
C. Allow concrete floor and curb at pump openings to cure at least seven days prior to installing the sole plates and at
least 14 days before installing the pumps.Pumps shall not be operated until concrete has cured 28 days.
3.2 FIELD QUALITY CONTROL
A. Furnish the services of a qualified representative of the Pump Manufacturer to inspect the completed installation,
make any necessary adjustments,participate in the startup of the equipment, participate in the field testing of the
equipment and place the equipment in trouble-free operation.
09986-0001-00 11021—9 CONFORMED SET
Rev. Per Add. No.6 09/12/2017
RFP NO. 7
Baytown Area Water Authority VERTICAL TURBINE PUMPS
6 MGD Surface Water Treatment Plant
B. All piping connections to the pump shall be done without bending and/or twisting the piping to mate with the pump
flange connections.
C. A certificate for the Pump Manufacturer shall be submitted stating that the installation of the equipment is
satisfactory,that the equipment is ready for operation and that the Owner's operating personnel have been suitably
instructed in the operation,lubrication and care of each unit.
D. After pumps have been completely installed and working under the direction of the manufacturer, conduct field
tests necessary to demonstrate that pump operation conforms to these Specifications. Supply water, labor,
equipment are incidentals required to complete field tests.
E. If the pump performance does not comply with Specifications, take corrective measures or remove and replace
pumps with pumps which satisfy the conditions specified.
3.3 START-UP AND ACCEPTANCE
A. Start-Up:
1. Final Completion will not occur until after the start-up activities have been performed and accepted by the
Engineer.Start-up activities include the following:
a. Receipt and acceptance by the Owner of draft Operation and Maintenance manuals,including the
wiring and ladder diagrams.
b. Installation inspection by representatives of the Owner and pump manufacturer followed by any
corrective measures required by the Design Builder.
C. Satisfactory operation of pumps for 7 consecutive days under the Owner's control.If malfunctions
or other operational problems halt the 7-day test period,the Design Builder shall make appropriate
corrections and restart the 7-day test period.
d. Provide the services of a factory-trained technician for a period of 4 hours at the pump station to
train the Owner's operating and maintenance personnel.Training session shall be scheduled and
coordinated by the Design Builder.
B. Acceptance:
1. After the start-up operation has been successfully completed, the final Operation and Maintenance
manuals have been received, reviewed, and accepted, and the Engineer has issued Final Completion, the
pumps will be accepted by the Owner. Include ladder logic diagrams and wiring and termination diagrams
for both power and instrumentation systems.
END OF SECTION
09986-0001-00 11021-10 CONFORMED SET
Rev. Per Add.No.6 09/12/2017
�GOULDS Performance Curve
lrgnw nctwfxry°r
a xylem brand
Product Name: VIT-Shod Set Lineshaft Turbine Pumps
Product Id: GWT VIT Quote Number BAWA-Low Lift
9.88 in
40
r 55 66
72 78
40 8 80 81
m
80
78
A 40 65 72
_ 72 78
20
78
55
72
55
0 400 800 1200 1600 2000 2400 2800 3200
C 20
S
N
a
Z O 400 $Do 1200 1600 2000 2400 2800 3200
1-0
L
p 0 400 800 1200 1600 2000 2400 2800 3200
0- US gpm
Curve&hydraulic data presented is nominal performance based on ANSIIHI 14.6 acceptance grade 2B.Design values are guaranteed
within the following tolerances:Flow±8%,Head±5%,and optionally either Power+8%or Efficiency-5%at manufacturer's discretion.
Series GWT_VIT Max Power on Design Curve 24.70 Hp
Size 14FHC Max Power on Max Imp Trim 24.70 Hp
Additional Size - Guaranteed Max Power on Design Curve 26.68 Hp
Speed 1.180 RPM Guaranteed Max Power on Max Imp Trim 26.68 Hp
Number of Stages 1 Flow at BEP 2,236 USgpm
Frequency 60 Hz Head at BEP 35.4 R
Impeller Trim 9.88 in NPSH Required 11.9 It
Additional Impeller - Specified NPSH Avail. 33.17 ft
Impeller Maximum Trim 9.88 in Specified NPSH Avail.Margin 1.1
Specified Flow 2.292 USgpm Min Flow 559 USgpm
Specified Head 34 It Flow on Max Imp Trim @ Max Power 2,236 USgpm
Flow at Design 2,292 USgpm Shut-Off Head 54.3 ft
Head at Design 34 ft Shut-Off Disc Pressure 23.5 psi
Run-Out Flow null USgpm Fluid Type Water ,
Run-Out Head null If Water Temperature 68°F
Efficiency at Design 75.00% Allowable Sphere Size 1.75 in
Guaranteed Efficiency at Design 75.00% Exact Bowl Diameter 14 in
Best Efficiency 81 % Curve Id E6414FAPCO
Driver Size 30 Hp Thrust K Factor 17 lb/ft
Power at Design 24.60 Hp Add Thrust K Factor -
Guaranleed Power 26.57 Hp Max Lateral 1 in
Flow on Design Trim @ Max Power 2,236 USgpm Total Flow Derate Factor 1
Acceptance Grade 2B Total Head Derate Factor 1
Service Factor No Total Efficiency Derate Factor 1
6/19/2019 FW:P3T-BAWA LLPS vertical turbine pump change-Wang,Qiang
FW- P3T-BAWA LLPS vertical turbine pump change
Larry Weppler <LWeppler@jonescarter.com>
Mon 6/17/2019 10:18 AM
To Wang,Qiang <gwang@plwus.com>;
ct:Drown, Katy <kdrown@plwus.com>; Ibana,Antonio <aibarra@plwus.c0m>;
(h 1 attachments (357 KB)
BAWA 14FHC 1-Stage.pdf;
CAUTION: External email. Do not click links or open attachments unless you recognize the sender and know the content is safe.
Dennis—Use this new pump curve for RFP No. 007. Replace the old on with this one.
Larry
Larry A. Weppler, P.E.
Corporate Construction Management Services
lweppLer@.jonescarter.com
JONES i CARTER
6330 West Loop South, Suite 150
-- --
Telephone 713.777.5337 Ext. 2511
Cell 713.819.2220
Smart Engineering. Smart SolutionS.r"'
www.jonescarter.com
From:Trevor Otter
Sent: Monday,June 17, 2019 10:15 AM
To: Larry Weppler
Cc:Vinoth.Manoharan@aecom.com; Bethany Miller;Stephanie Kaspar
Subject: FW: P3T-BAWA LLPS vertical turbine pump change
Larry,
Please see AECOM's approval of the modified pump selection for the LLPS as attached.This curve supersedes both the duty
conditions and capacities listed in RFP 007.
Thank you,
Trevor Otter, P.E. (Texas No.132077)
Project Engineer
Lotter@.jonescarter.com
https://outlook.off ce365.com/owa/?Iteml D=AAMkADc3ZGZiNjcOLTgxZ WQtNG UOZC04M 2VILW E4NDIhO W U5Y WJhYgBGAAAAAAD Da KIOTQQ mRgn... 1/2
6/19/2019 FW:P3T-8AWA LLPS vertical turbine pump change-Wang,Qiang
JONES ( CARTER
-t Loop South, Suite 150
Direct 713.353.7299
Cell 281.460.2052
From: Manoharan,Vinoth fmailto:Vinoth.Manoharan@aecom.comj
Sent: Monday,June 17, 2019 10:03 AM
To:Trevor Otter<TOtter@jonescarter.com>;Zheng,Xuan<xuan.zheng,@aecom.com>
Cc: Bethany Miller<BMiller@jonescartercom>
Subject: RE: P3T-BAWA LLPS vertical turbine pump change
Trevor,
Based on the curve provided,the trimmed impeller would give a flow of about 6.73 MGD (4,675 gpm) at high wet well
elevation and about 6.32 MGD(4,325 gpm) at low wet well elevation. We approve the trimmed impeller forthe LLPS pumps.
Thanks,
Vinoth
From: Trevor Otter [mailto:TOtter@jonescarter.coml
Sent: Thursday, June 13, 2019 3:48 PM
To: Manoharan, Vinoth; Zheng, Xuan
Cc: Bethany Miller
Subject: FW: P3T-BAWA LLPS vertical turbine pump change
Vinoth,
Per our discussion, please see the trimmed impeller from Weisinger/Xylem attached. Once you sign off,we will instruct PLW
to use the attached pump for the LLPS pumps.
Please review this as soon as possible
Thank you,
Trevor Otter, P.E. (Texas No.132O77)
Project Engineer
totter@jonescarter.com
JONES I CARTER
63',fl \Al'^ t I r,nn i 150
Direct 713.353.7299
Cell 281.460.2052
This e-mail and any attachments are intended only for the named recipient(s)and may contain information that is legally privileged,confidential,or exempt from
disclosure under applicable law.If you have received this message in error,or are not the named recipient(s),you may not retain copy or use this e-mail or any
attachment for any purpose or disclose all or any part of the contents to any other person.Any such dissemination,distribution or copying of this e-mail or its
attachments is strictly prohibited.Please immediately notify the sender and permanently delete this e-mail and any attachment from your computer and/or electronic
devices.Any personal views or opinions expressed by the writer may not necessarily reflect the views or opinions of Jones&Carter,Inc.
https://oullook.office365.com/owa/?I leml D=AAMkADc3ZGZiNjcOLTgxZ W QtN G UOZC04M2 V I LW E4N DIhO W U5Y WJ hYgBGAAAAAADDa KioTQQmRgn... 2/2
SUBMITTAL
8GGOOUnaDS� Quote ID:9001-190612-075:0:1 CITY: 1
VIT-BAT 14FHC, 1 Stage
a xylem brand
PERFORMANCE ON DESIGN CURVE AT 1180 RPM
Shut Off Design[21 Run Out I51 I
Flow(USGPM) 0.0 2292.0 0.0 IBest Efficiency 79.00%at 2198.0 USgpm
TDH-Bowl(it) 51.4 31.8 0.0 Design Flow%BEP 104.28%
TDH-Disch Flange(ft) 50.5 30.9 0.0 Pump Efficiency 76.24%
Bowl Efficiency(%) - 78.60 - Overall Efficiency 0,00%
Guaranteed Bowl Efficiency(%) - 76.24 - NOL Power 23.4 Hp at 2233.0 USgpm
Power(Hp) - 23.3 - Guaranteed NOL Power 24.3 Hp at 2233.0 USgpm
Guaranteed Power(Hp) - 24.2 - Max Power(NOL)at Max Trim 24.8 Hp at 2236.0 USgpm
NPSHr(ft)I i I - 11.9 - Guaranteed Max Power(NOL) 25.8 Hp at 2236.0 USgpm
at Max Trim
NPSH Margin(ft)[11 - 20.1 - Specified NPSH Ratio 1.1
Hydraulic Thrust(lb) 873.8 540.6 0.0 Thrust Load Power Loss 0.05390 Hp
Thrust(lb) 998.4 639.9 0.0 Total Flow Derate Factor 1.00
Pressure-Bowl(psi) 22.3 13.8 0.0 Total Head Derate Factor 1.00
Pressure-Disch Flange(psi) 21.9 13.4 0.0 Total Efficiency Derate Factor 1.00
Min Submergence(Inch)t31 - 44.95 - Actual Submergence 0.00 in
Friction Loss(ft) a'; - 0.89 0.00 Shaft Friction Power Loss 0.00 Hp
Lineshaft Elongation(Inch) -0.00133 -0.00082 - Min Flow(MCSF) 550.0 USgpm
Column Elongation(Inch) 0.00000 0.00000 - kWhr 1000 gat 0.00000
Lateral(Inch) 0.12867 0.12918 - Immpeller Running Clearance_ 0.13 in pe
(1)at 1st impeller eye [21 rated values [31 from bottom of pump [4]from bowl to disch flange [5]based on user entered TDH
OPERATING CONDITIONS FLUID CHARACTERISTICS
Specified Flow 2292.00 USgpm Fluid Water
Specified TDH 31,50 ft Fluid Temperature 68.0°F
Rated Speed 1180 RPM Specific Gravity 1.0000
Atmospheric Pressure 14.70 psi Viscosity 1.0017 cP
NPSHa at 1st Impeller 32.0 it Vapor Pressure 0.3393 psi
NPSHa at Grade 33.9 ft Density 62 Ibs/W
MATERIALS & DIMENSIONS
Bowl Data Bowl Data
Bow[Material Cast Iron with Glass Enamel Max Impeller Trim 9.88 in
Bowl Material Derate Factor 1.00 Thrust K-Factor 17.0 Lb/Ft
Impeller Material Bronze Bow[Pressure Limit 340 psi
Impeller Mail Derate Factor 1.00 Available Lateral 1.00 in
Bowl Shaft Material 416SS Bow[Assembly Length(BL) 34.76 in
Impeller Attachment Taper Lock Disch Bowl Length OLS(01) 6.63 in
Taper Lock Material Carbon Steel Disch Bow[Length ELS(1-2) 13.50 in
Discharge Bowl Material Cast Iron Bowl Shaft Diameter 2 3/16"[55.6 mm]
Suction Type Bell Impeller Balance Manufacturer's Standard
Suction Material Cast Iron Impeller Design Enclosed
Bowl Bolting Material Carbon Steel Bowl Wear Ring Not Included
Sand Collar 304SS Impeller Wear Ring Not Included
Pipe Plug Iron Suction Pipe Diameter No Suction Pipe
Suction Bearing Bronze Bow[Diameter(D) 14.00 in
Discharge Bowl Bearing Bronze Bowl Length(1-3) 13.63 in
Intermediate Bowl Bearing Bronze Bowl Flange Diameter(A) 7.13 in
Strainer Type Not Included Bowl Flange Thickness(E) 14.50 in
Tube Adapter Bearing Not Included Floor Clearance(X) 8.75 in
Material Min Column Diameter 10 in
Impeller Trim 9.69 in Max Column Diameter 12 in
DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED
Certified By
Project
Tag
PO Number
Serial Number
SUBMITTAL
�GOULDS Quote ID:9001-190612-075:0:1 QTY: 1
. noonreo.
VIT-BAT 14FHC, 1 Stage
a xylem brand
Bowl Data
Max Bowl Shaft Diameter 2.19 in
Bowl Shaft Length 40.25in
Bowl Shaft Power Limit 590.08 Hp__
Bowl Specials
Motor Data Motor Data
Driver Type Vertical Hollow Shaft Motor Motor Provided By Customer
Motor Manufacturer Motor Mounted By Customer
Motor Speed 1180 RPM HP Rating 25 Hp
Phase I Frequency Speed[Poles] 1200 rpm[6 pole]
Enclosure BD 10.0 in
Mfg Catalog Number
Motor Frame
Motor Part Number
Inverter Duty Max power on design curve
Steady Bushing Driver Size Criteria (NOL)
Motor Coupling Allow Service Factor __ No
Insulation Class
Service Factor
Motor Specials
Coating Data Coating Data
Bowl OD Goulds Water Technology Can OD Not Included
Standard Blue Enamel Head ID Not Included
Column ID Not Included Head OD Goulds Water Technology
Column OD Goulds Water Technology Standard Blue Enamel
Standard Blue Enamel Enclosing Tube OD Not Included
Column Bearing Retainer Not Included Steel Sub Base Not Included
Can ID Not Included
Testing Data
Miscellaneous Specials
Weight Data Weight Data
Total Bowl Weight 493 lbs Total Weight 49311is
Unit Bowl Weight 493 lbs Total Rotating Weight 581bs
INFO,WARNING&ERROR MESSAGES
Our offer does not include specific review and incorporation of any Statutory or Regulatory Requirements and the offer is limited to the requirements of the
design specifications.Should any Statutory or Regulatory requirements need to be reviewed and incorporated then the Customer is responsible to identify those
and provide copies for review and revision of our offer.
Our quotation is offered in accordance with our comments and exceptions identified in our proposal and governed by our standard terms and conditions of sale—
Xylem Americas attached hereafter.
For units requiring performance test,all performance tests will be conducted per ANSI/HI 14.6 standards unless otherwise noted in the selection software
submittal documents.Test results meeting with grade 213 tolerances for pumps with a rated shaft power of 134HP or less and grade 1 B for greater than 134HP will
be considered passing.
Customer is responsible for verifying that the recommendations made and the materials selected are satisfactory for the Customer's intended environment and
Customer's use of the selected pump.Customer is responsible
for determining the suitability of Xylem recommendations for DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED
all operating conditions within Customer's and/or End User's Certified By
control.Xylem disclaims all warranties,express or implied
warranties,including,but not limited to,warranties of Project
Tag
PO Number
Serial Number
OUTLINE DRAWING
�GOUL,. r Quote ID:9001-190612-075:0:1 CITY: 1
VIT-BAT 14FHC,1 Stage
a rylem brand
'L"-P DIMENSIONS PUMP DATA
1? UI
COl
a COL[Column Diameter] 10.00 in Column Diameter 10"[254mm]
s
-- u MIN SUB[Minimum Lineshak Diameter 1 in[25.4 mm]
Submergence] 44.95 in
Specified Flow 2292.00 USgpm
BL[Bowl Assembly 34.76 in Specified TDH 31.50 If
Length]
Motor Manufacturer
BL L[Shaft Turndown Size] 1.00 in
qnx sue M Shaft Thread Pitch 12.00 in Driver Type Vertical Hollow
( ] Shaft Motor
SU[Shaft Stickup] 8.00 in Motor Speed 1180 RPM
Phase/Frequency
WEIGHTS
Total Bowl Weight 493 Ibs
Unit Bowl Weight 493 lbs
Total Weight 493 lbs
Total Rotating Weight 58 lbs
NOTES
1 I Total Pump Length t 1.0 inch.
2 Tolerance on all dimensions is.12 or t.12
inch per 5 it,whichever is greater.
3 All dimensions shown are in inches unless
otherwise specified.
4 Drawing not to scale.
5 Y;NPT—Gauge Conn(plugged)
6 Driver may be rotated at 90°intervals about
vertical centerline for details refer to driver
dimension drawing,
7 Refer to product IOM for impeller setting
requirements.
8 This assembly has been designed so that
its natural frequency responses avoid the
specific operating speeds by an adequate
safety margin. The design has assumed
the foundation to be rigid.
DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED
Certified By
Project
Tag
PO Number
Serial Number
�GOULDS CROSS SECTION DRAWING
�1v 1wma�oov
a zytem brand Quote ID:
4FHC,9 Stage75:0:1 QTY: i
VIT-BAT 14FHC, 1 Stage
__�660
664� - 661 _ BILL OF MATERIALS
ITEM PART NAME CODE MATERIAL ASTM#
677 Bowl Assembly
J �670 660 Shaft-Bowl 2227 SST416 A582 S41600
760 —673 661 Discharge Bowl 1003 Cast Iron CI30 A48 CLASS 30B
672 664 Bearing-Discharge Bowl 1618 Bronze Bismuth B584 Modified
692 --698 668 Bearing Tube Adapt N/A Not Included N/A
690 670 Bowl-Intermediate 6911 Cast Iron C130 Enamel A48
672 Bearing-Intermediate Bowl 1618 Bronze Bismuth B584 Modified
—747 673 Impeller 1398 Silicon Bronze C87610 B594
677 Taper Lock-Impeller 2242 Carbon Steel 1018 A108
680 Wear Ring-Bowl N/A Not Included N/A
681 Wear Ring-Impeller NA Not Included NA
688 Suction 1003 Cast Iron CI30 A48 CLASS 30B
690 Bearing-Suction 1109 Bronze C90300"G'Mod B584
692 Sandcollar 1205 SST 304 A744M
747 Pipe Plug 1046 Malleable Iron A197
760 Capscrew-Hex 2298 Steel Bolling Gr 8 J429
DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED
Certified By
Project
Tag
PO Number
Serial Number
PERFORMANCE CURVE
�GOUL Quote ID:9001-190612-075.0:1 QTY. 1
VIT-BAT I4FHC, 1 Stage
a xylem brand
9.88in !
in
50 38
53
fi4 70
40 76 78
8 in 79
78
ifi
v 30 38
y 53 64 70
= 70
20 76
76 53
70
10
53
0
20
u)
V1
a
z
0
Cl.
z 20 --
a
0 400 800 1200 1600 2000 2400 2800 S 9Pm
Curve&hydraulic data presented is nominal performance based on ANSI/HI 14.6 acceptance grade 18.
Design values are guaranteed within the following tolerances: Flow t 5%,Head t 3%,and optionally either Power+4%or Efficiency-3%at
manufacturer's discretion.
CURVE DATA
Specified Flow 2292.00 USgpm Shut Off TDH(Disch Flange) 50.5 it Trim
Specified TDH 31.50 it Shut Off Pressure(Bowl) 22.3 psi Recommended Power 25.00 Hp
Rated Speed 1180 RPM Shut Off Pressure(Disch Flange) 21.9 psi Allow Service Factor No
Atmospheric Pressure 14.70 psi Bowl Efficiency at Design 78.60% kWh per 1000 gal 0.00000
NPSHa at Grade 33.9 it Guaranteed Bowl Efficiency 76.24% NPSHr at Design 11.9 it
NPSHa at 1st Impeller 32.0 it Best Efficiency 79.00% NPSH Margin at Design 20.1 it
Fluid Water BEP Flow 2198.0 USgpm Min Submergence at Design 44.95 in
Fluid Temperature 68.0°F Design Flow%BEP 104.28% Thrust at Design 639.9lb
Specific Gravity 1.0000 Pump Efficiency 76.24% Thrust at Shut Off 998.4db
Viscosity 1.0017 cP Friction Loss at Design 0.89 it Bowl Material Cast Iron with Glass
Vapor Pressure 0.3393 psi Power at Design 23.3 Hp Enamel
Density 62 lbs/W Guaranteed Power 24.2 Hp Bowl Material Berets,Factor 1.00
Design Flow 2292.0 USgpm NOL Power 23.4 Hp Impeller Material Bronze
Min Flow(MCSF) 550.0 USgpm Guaranteed NOL Power 24.3 Hp Impeller Mail Berate Factor 1.00
Design TDH(Bowl) 31.8 it Max Power(NOL)Flow 2233.0 USgpm Total Flow Berate Factor 1.00
Design TDH(Disch Flange) 30.9 it Max Power(NOL)at Max Trim 24.8 Hp Total Head Berate Factor 1.00
Design Pressure(Bowl) 13.8 psi Guaranteed Max Power(NOL)at 258 H Total Efficiency Berate Factor 1.00
Design Pressure(Disch Flange) 13.4 psi Max Trim . p Curve ID E6414FAPCO
Shut Off TDH(Bowl) 51.4 it Max Power(NOL)Flow at Max 2236.0 USgpm
DO NOT USE FOR CONSTRUCTION UNLESS CERTIFIED
Certified By
Project
Tag
PO Number
Serial Number
6/20/2019 FW:Follow-up Response from Xylem FW:Submittals:#283.0:Sub...-Wang,Qiang
FW: Follow-up Response from Xylem FW.- Submittals: #283.0: Submittal
283 LLPS Vertical Turbine Pumps
Larry Weppler <LWeppler@jonescarter.com>
Thu 6/20/2019 11.54 AM
Il,:Wang, Qiang <gwang@plwus.com>;
CAUTION: External email. Do not click links or open attachments unless you recognize the sender and know the content is safe.
From: Larry Weppler
Sent:Thursday,June 20, 2019 11:48 AM
To: Katy Drown (kdrown@plwus.com); Dennis Fikes (dennisf@emetalsinc.com); Ibarra,Antonio
Subject: FW: Follow-up Response from Xylem FW:Submittals:#283.0:Submittal 283 LLPS Vertical Turbine Pumps
SAVE!
FYI
From:Trevor Otter
Sent:Thursday,June 20, 2019 10:56 AM
To: Larry Weppler
Cc: Bethany Miller;Stephanie Kaspar
Subject: RE: Follow-up Response from Xylem FW:Submittals:#283.0:Submittal 283 LLPS Vertical Turbine Pumps
Larry,
The lU tolerance submittal curve provided for the LLPS is acceptable, please inform Dennis.
Thank you,
Trevor Otter, P.E. (Texas No.132077)
Project Engineer
Lotter@.jonescarter.com
JONES I CARTER
6330 West Loop South, Suite 150
Bellaire,Texas 77401
Direct 713.353.7299
Cell 281.460.2052
From: Stephanie Kaspar
Sent:Thursday,June 20, 2019 7:56 AM
To:Trevor Otter<TOtter@jonescartencom>
Cc: Bethany Miller<BMiller@jonescarter.com>
Subject: FW: Follow-up Response from Xylem FW: Submittals:#283.0: Submittal 283 LLPS Vertical Turbine Pumps
https://outlook.ofrice365.com/owa/?Iteml D=AAMkADc3ZGZ!NjcOLTgxZ WQtN G U OZC04M 2VILWE4N DIh 0 W U 5Y WJhYgBGAAAAAAD DaKioTQQmRgn... 114
6/20/2019 FW:Follow-up Response from Xylem FW:Submittals:#283.0:Sub...-Wang,Qiang
See below.
From: Qiang(Dennis) Wang (Pepper Lawson Waterworks) (mailto:jones&carter notifications@_procoretech.com]
Sent:Thursday,June 20, 2019 7:55 AM
To:Stephanie Kaspar<SKaspar@jonescarter.com>
Subject: Follow-up Response from Xylem FW:Submittals:#283.0:Submittal 283 LLPS Vertical Turbine Pumps
BAWA 6 MGD Surface Water Treatment Plant
Project
More details View online iew PDF
From: Qiang (Dennis) Wang (Pepper Lawson Waterworks)
Date Thursday, June 20, 2019 at 07:55 am CDT
Sent To Stephanie S. Kaspar, P.E. (JonesCarter, Houston)
cc Katy Drown (Pepper Lawson Waterworks)
Bethany Miller (JonesCarter, Houston)
Clang (Dennis)Wang (Pepper Lawson Waterworks)
Larry Weppler(JonesCarter, Houston)
Attachments. None
Hi Stephanie,
Please see the response from Xylem concerning the new curve:
"Your curve has a 1 B tolerance. My submittal curve has a 1 U tolerance per the specification
requirements. "
Please advise if it is acceptable. Thanks,
Dennis
Sent from Procore
https://outlook.off ce365.com/owa/?I to m I D=AAMkADc3ZGZi NIcOLTgxZWQtNGU OZC04M 2VI LW E4NDIhO W U 5Y WJ hYgBGAAAAAAE)DaKioTQ DmRgn... 2/4
6/20/2019 FW:Follow-up Response from Xylem FW:Submittals:#283.0:Sub...-Wang.Qiang
Submittal Item Details
Project: SAWA 6 MGD Surface Water Treatment Plant Project
Spec Section: 11021 -Vertical Turbine Pumps
Submittal #: 283.0
Title: Submittal 283 LLPS Vertical Turbine Pumps
Type: Product Information
Responsible Contractor: Pepper Lawson Waterworks
Received From: Antonio Ibarra
Ball In Court: Stephanie S. Kaspar, P.E.
Approvers: Kaspar, P.E., Stephanie S. (JonesCarter, Houston)
Weppler, Larry (JonesCarter, Houston)
Confirmed Delivery Date: 05/02/19
Final Due Date: 05/10/19
Description:
Item:
Vertical Turbine Pumps -Low Lift Pump Station
Attachments: Submittal 283 LLPS Vertical Turbine Pumps .pdf
Approver: Kaspar, P.E., Stephanie S. (JonesCarter, Houston)
Date Sent: 05/03/19
Returned:
Response: Pending
Attachments: None
Comments: None
Approver: Weppler, Larry (JonesCarter, Houston)
Date Sent:
Returned:
Response: Pending
https://outlook.ofrice365.com/owa/?I teml D=AAMkAOc3ZGZiNjcO LTgxZWQtNGUOZC04M 2VI LW E4N DIhO W U 5Y WJ hYgBGAAAAAADDa KioTQQ m Rq n... 3/4
6/20/2019 FW:Follow-up Response from Xylem FW:Submittals:#283.0:Sub...-Wang.Qiang
Attachments: None
Comments: None
More details View online iew PDF
Powered By Prorore supig2d@procore.com hops!/sugpon procore.com
This e-mail and any attachments are intended only for the named recipient(s)and may contain information that is legally privileged,confidential,or exempt from
disclosure under applicable law.If you have received this message in error,or are not the named recipient(s),you may not retain copy or use this e-mail or any
attachment for any purpose or disclose all or any part of the contents to any other person.Any such dissemination,distribution or copying of this e-mail or its
attachments is strictly prohibited.Please immediately notify the sender and permanently delete this e-mail and any attachment from your computer and/or electronic
devices.Any personal views or opinions expressed by the writer may not necessarily reflect the views or opinions of Jones 8 Carter,Inc.
https://pu0ook.office365.com/owa/?I teml D=AAM kADc3ZGZi NicOLTgxZ WQING U OZC04M 2VI LW E4N DIhO W U 5Y WJhYg BGAAAAAADDaKioTQQmRgn... 414
WESTFALL MANUFACTURING CO.
15 Broad Common Road
Bristol,RI 02809
DrAswalm info(i4westfallmfa.net wwNN.westfallmf8.com
QUOTATION 021219-162800-02
February 12,2019
TO: PLW Waterworks FROM: Newman Regency Group (281) 980-7448
Jeff Rebenschied, P.E.
ATTN: Dennis Wang, Ph.D., P.E. EMAIL: ieffcr,newmanregency.com
FAX/EMAIL: gwang(d,)plwus.com REF: Westfall Static Mixer
WE ARE PLEASED TO OFFER OUR QUOTATION FOR THE FOLLOWING
ITEM QTY DESCRIPTION UNIT PRICE EXTENDED
A 2 16" WESTFALL STATIC MIXER MODEL 2800 PVC MOUNTING
RING
(1) .8 BETA PVC MIXING PLATE
(3)sW' INJECTION PORTS (2 PLUGGED WITH PVC PLUGS)
(2) 1/8"NSF-61 EPDM GASKETS
MIXER IS MADE WITH NSF-61 CERTIFIED MATERIALS $20,480.00 $40,960.00
B 2 '/,"CPVC CORP STOPS WITH PVC SOLUTION TUBES $ 800.00 $ 1,600.00
NOTES:
1) MIXER IS DESIGNED TO BE INSTALLED BETWEEN
150#FLANGES
WESTFALL MANUFACTURING CO.
TERMS:NET 30 DAYS
BY:
SHIPMENT: 2-5 WEEKS ARO Please sign and return original copy.
FREIGHT PREPAID AND ADD Retain duplicate copy for your records.
FOB:BRISTOL,RI ACCEPTED BY:
TITLE: DATE:
O&M MANUALS: FIRST TWO:NO CHARGE
ADDITIONAL O&M MANUALS: $20 EACH ***QUOTE IS VALID FOR 30 DAYS. ORDERS PLACED
AFTER THIS TIME WILL BE PRICED TO REFLECT CURRENT
MATERIAL COST**
WESTFALL MANUFACTURING CO.
HEADLOSS CHART
pipe ID 15.25 inches
Pipe area 1.2684 fl2 MODEL 2800 MODEL 2800 MODEL 2800 MODEL 3050 MODEL 3050 MODEL 3050
0.7 BETA 0.8 BETA 0.9 BETA SINGLE DOUBLE TRIPLE
GPM CFS ft/s psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss
569 1.268 1.00 0.22 0.09 0.05 0.004 0.008 0.011
1139 2.537 2.00 0.88 0.37 0.18 0.015 0.030 0.044
1708 3.805 3.00 1.97 0.82 0.41 0.034 0.068 0.099
2277 5.074 4.00 3.51 1.47 0.73 0.060 0.122 0.176
2847 6.342 5.00 5.48 2.29 1.14 0.094 0.190 0.276
3416 7.611 6.00 7.89 3.30 1.64 0.135 0.274 0.397
3985 8.879 7.00 10.74 4.49 2.24 0.184 0.372 0.540
4555 10.147 8.00 14.03 5.87 2.92 0.240 0.486 0.706
5124 11.416 9.00 17.75 7.42 3.69 0.303 0.616 0.893
5693 12.684 10.00 21.92 9.17 4.56 0.375 0.760 1.103
6262 13.953 11.00 26.52 11.09 5.52 0.453 0.920 1.335
6832 15.221 1 1200. 31.56 1 13.20 1 6.67 1 0.539 1.094 1.588
16"W ESTFALL STATIC MIXER MODEL 2800
PVC MOUNTING RING
(1) .8 BETA PVC MIXING PLATE
(3) 3/4"NPT PORTS WITH PVC HOUSING 9'
(2) 1/8"NSF-61 EPDM GASKETS
SHOWN WITH:
(3) 3/4"CPVC CORP STOPS WITH PVC SOLUTION TUBES
r
020.250 MIXER OD
2.750 MOUNTING�I
RING THICKNESS
0 15.250 MIXER ID
--------------
1
= FLOW
----->
2.000 LAYING LENGTH
WITH GASKETS
CLIENT APPROVAL:APPROVED BY: DATE VIAV,j=J` -T�� WE STATICMIXER
MODEL
2800-
'
PRWT NAME: MILE DIMENSIONS ARE IN MCHES(UNLESS OTHERWISE NOTED(
WESTFALL MANUFACTURING COMPANY 1A ° IO.Id.4016
COMPANY: o r ° eon _ a Uv 16-2800-C
MGP
,
NEWMAN REGENCY GROUP
�j•�•�WATER/WASTEWATER
EQUIPMENT WESTFALL MANUFACTURING CO.
HOUSTON•AUSTIN*DALLAS/Ft.WORTH•OKLAHOMA
15 Broad Common Road
Bristol,R102809
info(rbwestfallmf¢.net www.westfallmfe.com
(REVISED) QUOTATION 021219-162800-05-NRG
May 6,2019
TO: PLW Waterworks FROM: Newman Regency Group (281) 980-7448
ATTN: Dennis Wang, Ph.D., P.E. Jeff Rebencshied, P.E. (713) 582-7448
EMAIL: gwang(@plwus.com EMAIL: leffiRnewmanregency.com
REF: Westfall Static Mixer
WE ARE PLEASED TO OFFER OUR QUOTATION FOR THE FOLLOWING
ITEM QTY DESCRIPTION UNIT PRICE EXTENDED
A 1 16" STATIC MIXER MODEL 3050 $23,665.00 $23,665.00
SCH40 CARBON STEEL CONSTRUCTION
(2)ROWS OF(4)CARBON STEEL MIXING ELEMENTS
(1)%"PORT WITH 316SS HOUSING
(2)CARBON STEEL RFSO 150#FLANGED ENDS
INTERIOR COATED WITH 3M SKOTCHCOAT 134 COATING
EXTERIOR COATED WITH RUSTOLEUM PRIMER
B 1 '/a"STAINLESS CORP STOP WITH HASTELLOY SOLUTION TUBE $2,250.00 $2,250.00
NOTES:
1) MIXERS ARE DESIGNED TO BE INSTALLED BETWEEN
150#FLANGES
TOTAL: $25,915.00
WESTFALL MANUFACTURING CO.
TERMS:NET 30 DAYS
BY:
SHIPMENT:4-5 WEEKS ARO Please sign and return original copy.
FREIGHT PREPAID AND ADD Retain duplicate copy for your records.
FOB:BRISTOL,RI ACCEPTED BY:
TITLE: DATE:
O&M MANUALS:FIRST TWO:NO CHARGE
ADDITIONAL O&M MANUALS: $20 EACH ***QUOTE IS VALID FOR 30 DAYS. ORDERS PLACED
AFTER THIS TIME WILL BE PRICED TO REFLECT CURRENT
MATERIAL COST**
Newman Regency Group - 12705 S. Kirkwood - Ste. 140 - Stafford, TX 77477
-WESTFALL MANUFACTURING CO.
HEADLOSS CHART
pipe ID 15.25 inches
MODEL 2800 MODEL 2800 MODEL 2800 MODEL 3050 MODEL 3050 MODEL 3050 MODEL 6000
0.7 BETA 0.8 BETA 0.9 BETA SINGLE DOUBLE TRIPLE
GPM ftis psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss psi Head loss
562.5 0.99 0.21 0.09 0.04 0.004 0.007 0.011 0.008
1125.0 1.98 0.86 0.36 0.18 0.015 0.030 0.043 0.033
1687.5 2.96 1.93 0.81 0.40 0.033 0.067 0.097 0.074
2250.0 3.95 3.42 1.43 0.71 0.059 0.119 0.172 0.132
2812.5 4.94 5.35 2.24 1.11 0.091 0.185 0.269 0.207
3375.0 5.93 7.70 3.22 1.60 0.132 0.267 0.388 0.298
3937.5 6.92 10.48 4.38 2.18 0.179 0.364 0.528 0.405
4500.0 7.90 13.69 5.73 2.85 0.234 0.475 0.689 0.529
5062.5 8.89 17.33 7.25 3.61 0.296 0.601 0.872 0.670
5625.0 9.88 21.40 8.95 4.45 0.366 0.742 1.077 0.827
6187.5 10.87 25.89 10.83 5.39 0.442 0.898 1.303 1.001
6750.0 11.86 30.81 1 12.89 6.41 0.527 1.068 1 1.550 1.191
WESTFALL STATIC MIXER MODEL 3050
SCH40 CARBON STEEL CONSTRUCTION
2 ROWS OF (4) CARBON STEEL MIXING TABS
1 3/4"316SS I JECITON PORT WELDOLEf
150# RFSO CARBON STEEL FLANGE ENDS
INTERIOR COATED WITH 3M SKOTCHCOAT 134 COATING y
EXTERIOR COATED WITH RUSTOLEUM PRIMER y; c
SHOWN WITH: ✓ J
(1) STAINLESS CORP STOP WITH HASTELLOY SOLUTION TUBE
023.50 FLANGE OD
4L 16.00 PIPE OD
O o
0
O 015.25 PIPE ID F �,- ._._....._..........__..� . <
0 0
FLOW __:- :=,_:_:=:::,i.-------
0 0 - -
>
0 0
(�
--- ----- ...-.....-.:L.:.- -
O O - -
O 0
38.00 FLGxFLG LENGTH
CLIENTAPPROVAL APPROV : WESTFALL WESTFALL STATIC MIXER
APPRoveD er: DATE: MODEL 3050- 16'
PRIM NAME TITLE: DIMENSIONS ARE IN INCHES(UNLESS OTHERWISE NOTED)
WESTFALL MANUFACTURING COMPANY L t I027MI4
coMPANr. .,,�.,,.w .e. .... MGR .. 15-3050-B
environmental El 2
improvements Inc.
1183 Blitmoore RD 100 Quotation
Houston,Tx 77043
ph 713 451.1111
Customer: PLW Waterworks DATE: 5/9119
Attn: Dennis Wang DELIVERY: 3-4 weeks
Phone: 346-413-0503 TERMS: Net 30
Email: FOB: Factory
We are pleased to have the opportunity to offer you the following quotation.Please sign and fax back
along with your purchase order or alternate method of payment.
Item Oty Article Part Number Description unit Extended
1 1 B EB-146-B-S-6-0-E 1"MPT Brass CS x 1/2"316SS Solution Tube and $775.44 $ 775.44
Check Valve,EPDM
2 1 MISC FHA-CLR-050-P-E 3/4"Clear Flexible Hose Assembly,PVC,EPDM $160.92 $ 160.92
Total $936.36
By signing below you authorize Environmental Improvements,Inc.to provide the above mentioned
items.
Thank you,
signature
Dale
Pnnl
Austin Dallas Houston Tulsa
COHEN INDUSTRIAL SUPPLY COMPANY
1922 KNOLL STREET
HOUSTON, TEXAS 77280
(713)467-3300
DATE: 6/11/19 ADD: T L:$ 12,367.40
DELETE: TOTAL:( 0.72)
TOTAL:$ 11,71 .
PROJECT: P3T-BAWA STATIC MIXER CHANGE Total: $10,799.38
CONTRACTOR: PEPPER LAWSON
LOCATION: LLPS
ADD:
TAG QTy. DESCRIPTION COST TOTAL
981.1 1 16 X 2'8-3/4" FLG X FLG $2,034.00 $2,034.00
W/ 1" HOLE
960.1 1 24 X 10'8-1/8" FLG X FLG $5,605.20 $5,602.20
W/ 1" HOLE
1055.1 2 24 X 2 SERVICE SADDLE $ 350.00 $ 700.00
1055.2 2 2 X 3/4 BRONZE BUSHING $ 21.70 $ 43.40
1055.3 1 2 X 1 BRONZE BUSHING $ 21.70 $ 21.70
1055.4 1 %" SCH80 45 BEND $ 2.50 $ 2.50
1055.5 10 316SS UNISTRUT $ 12.95 $ 129.50
1055.6 2 Y2" 316SS US CLAMP $ 2.50 $ 5.00
1055.7 2 316SS US BASE $ 150.00 $ 300.00
1055.8 1 FREIGHT $ 2,000.00 $ 2,000.00
DELETE:
TAG CITY. DESCRIPTION COST TOTAL
981 1 16 X 3' FLG X FLG DI PIPE CL ($651.32) ($651.32)
960 1 24 X 12' FLG X FLG ($2,287.60) ($2,287.60)
1055 1 FREIGHT—RETURN $ 2,000.00 $ 2,000.00
1056 1 RESTOCKING $ 900.00 $ 900.00
Authorization Signature:
PAIMIng mmmo
June 19, 2019 QUOTE# 19-075
Attention: Brian Buttry
Brian Buttry I Superintendent
T. 281-907-8600 1 C. 205-704-0903
bbuttry@plwUS.com I plwUS.com
Reference: Low lift Station Revised Piping and Mixer
Attention: Brian,
Painting Professionals, Inc is pleased to submit our Lump Sum proposal for the above
referenced project. Our pricing includes supervision, labor, equipment, miscellaneous
materials and all tools necessary to complete the scope of work as outlined herein. Our
proposal, associated pricing and clarifications are based on information received from job
walk, scope and Email.
Should you have any questions or require any additional information, please do not
hesitate to call.
Best Regards,
Edward Ware
Painting Professionals
Office: 713-461-0004
Cell: 307-431-0087
E-Mail: edApaintingprofessionals.com
i
i,aan7anf -(
We are pleased to submit our scope for the following project. If at any time during the duration of the project, an
unplanned scope of work is incurred or plant outage causing a delay, a change order will be submitted.
Scope of Work:
• Sandblast SSPC SP-10
• Apply 2 coats of Carbogaurd 60 and one coat carbothane 134 HG to customer spec.
• Color—TBD per pipe spec
• Hold for inspection and document on daily QC reports.
Items included in pricing:
1. All labor.
2. All equipment needed for preparation&application.
Items to be supplied by customer:
Crew Size: 3
2 applicators
1 supervisor/NACE inspector
Painting Professionals,Inc agrees to perform above work in a timely manner for a total price of
Low lift Station Revised Piping & Mixer: $6,200.00
PRICING CLARIFICATIONS
1. Terms of Payment:
Terms of payment are that payment is due net thirty(30) days after submittal of invoice.
2. Proposal Term:
This proposal is valid for 90 Days.
z
We are pleased to submit our scope for the following project. If at any time during the duration of the project, an
unplanned scope of work is incurred or plant outage causing a delay, a change order will be submitted.
Scope of Work:
• Sandblast SSPC SP-10
• Apply 1 coats of Carbogaurd 60 to customer spec.
• Color—TBD
• Hold for inspection and document on daily QC reports.
Items included in pricing:
I. All labor.
2. All equipment needed for preparation&application.
Items to be supplied by customer:
Crew Size: 3
2 applicators
1 supervisor/NACE inspector
Painting Professionals,Inc agrees to perform above work in a timely manner for a total price of
Low lift Station Protective Coating Removal and Re-apply Primer: $4,200.00
PRICING CLARIFICATIONS
1. Terms of Payment:
Terms of payment are that payment is due net thirty(30) days after submittal of invoice.
2. Prollosal Term:
This proposal is valid for 90 Days.
2
Acceptance of Proposal
The undersigned on behalf of the owner or his agent accepts the terms and conditions above and agrees to the above
prices and terms as quoted plus any agreed to and authorized additional work.
Should a Purchase Order be issued in lieu of a signature, this document will be recognized as an addendum to the
Purchase Order.
Date: Signature:
Painting Professionals,Iuc agrees to perform the work in a timely manner for a total price(plus applicable
sales tax)with payment due 30 days from completion of work. This proposal may be withdrawn in 90 days if
not accepted.
3
pLw
waterworks
April 20, 2020
Mr. Andrea Brinkley
Assistant Director
Baytown Area Water Authority
The City of Baytown
2401 Market St.
Baytown, TX 77520
Re: CPR No. 45
BA WA 6 MGD Surface Water Treatment Plant
BAWA Job No. 1806021
Mrs. Brinkley.
The prefabricated metal building added steel column at gridline B.8 and 1 is causing clearance conflict
with the overhead coiling door. There is an 8" clearance requirement needed for the Trolley Rail
System that connects to the edge of the overhead door frame. The CMU column addition,the overhead
door cannot be installed in that location. PLW is proposing to add CMU brick in order to gain the
required clearance for the motor.
This change will result in a increase in the amount of$6,474.63
Please feel free to contact me at(713)301-8637 with any questions or concerns.
Regards,
P`LWW Waterworks
Air '�Q--
Katy Drown
Project Manager
Page 1
Rad'lotin Area Water AulhonlY CPRNo.: pus
R:USN6,MGD Surface Water Treatmeal Plant Date. MlIN20
RAW:A Jab No.1806021 PLWJob No.: P3T
CN11f OH Change
Saone of Work
CNIU OH Doof Choate
N -T..d
Labor Muten'tl Sularm—1 Taed plal'1/E u
Item Ilan Tnlal Uail Total Unll Total bob TmA
No. Destri lion Dnll Taal Cast Cnsl Co.' Cast Cm. Cnil Cnnt
1 0111111]Dour Cbm,
I Mambo,h1o6i0calioln I LS $ 5 - S - S - S 4,5.W 5 4,5.1181 S - 5 -
Ld M. I LS S d5U.o0 S 2511110 $ - 5 - $ - 5 - S - S
1.3 Scaffold., 1 LS S. - S - S - S - S - 5 - $ Out. S 115,1111,
Dimal Cast Sohmul 25.011 1500.00 Off)()
Snnll Tools o iM Is 30 Nn - We Na
E9uipaoia Darden 115LL11•: Na Ne Na
Tao a e.?5% aln/n oo 51ol
Sablotal E 111511 - O,SMI'ba 'llli 63
Iherlw-d R Profil SI 15115L iv If (r75110 11t5.54
Subtotal3 :nl ae - 5.I151111 8.9.0
now,k b¢uc nca,03JDf Sub Iss25 24.28
Smoo,l 1 iIa11 5.11a JS a04f
Total of all mlunue 11474 oI
alar
Grand Total Coat 6.I74.63
Papa_
AkN RFI #148
Jones&Carter,Inc. Project:09986-0001-00-SAWA 6 MGD Surface Water Treatment Plant
6330 West Loop S#150 Project
Bellaire,Texas 77401 5359 E Grand Parkway S
Phone:(713)777-5337 Baytown,Texas 77520
Phone:2814228281
Overhead Door Column Location Conflict
TO: Larry Weppler(JonesCarter,Houston) FROM: Antonio Ibarra(Pepper Lawson Waterworks)
DATE INITIATED: 10/17/2019 3701 Kirby,Suite 1133
Houston,Texas 77098
LOCATION: STATUS: Closed
PROJECT STAGE: DUE DATE: 10/20/2019
SUB JOB: COST CODE:
COSTIMPACT: Yes(Unknown)
SCHEDULE IMPACT:
DRAWING NUMBER:
SPEC SECTION:
LINKED DRAWINGS:
REFERENCE:
RECEIVED FROM: Antonio Ibarra(Pepper Lawson Waterworks)
COPIES TO:
Andrea Brinkley(City of Baytown),Brian Buttry(Pepper Lawson Waterworks),Cole Buttry(Pepper Lawson Waterworks),Dana Buttry(Pepper
Lawson Waterworks),Katy Drown(Pepper Lawson Waterworks),James Harris(Aecom),Dale Hughes(City of Baytown),Antonio Ibarra(Pepper
Lawson Waterworks),Jose Luis Lopez(Pepper Lawson Waterworks),Joseph(Joey)Tocci(Pepper Lawson Waterworks),Vikki Unsell(Pepper
Lawson Waterworks),Oiang(Dennis)Wang(Pepper Lawson Waterworks)
Question from Antonio lbarra (Pepper Lawson Waterworks)at 05:24 PM on 10/17/2019
Per the prefabricated metal building submittal 160 response,the added steel column at gridline B.8 and 1 is causing clearance conflict with the
overhead coiling door.There is an 8"clearance requirement needed for the Trolley Rail System that connects to the edge of the overhead door frame.
Due to the CMU column addition,the overhead door cannot be installed in that location.PLW is proposing two options.Please see the attachments to
get more clarity on the proposed options.
Please be advised,a change order will be forthcoming depending on the choice of option.
Attachments:
Submittal 166A-Overhead Coiling Doors(2).pdf RFIRFI 148pdf
Official Response:(Katie)Xuan Zheng(Aecom)responded on Monday,November4th,2019 at 3:51PM CST
Please find the attached for the response.
Attachments:
RFI#148 Overhead Door Column Location ConflictRFI#148 Overhead Door Column Location Conflict-Resoonseodf
Official Response: Ryan Stephan(Joiner Architects)responded on Monday, October 28th,2019 at 8:42AM CDT
Architect confirms option 1 is acceptable.
Attachments:
All Replies:
;Response from (Katie)Xuan Zheng (Aecom)at 111104/2019
Please find the attached for the response.
Attachments:
RFI#148 Overhead Door Column Location Conflict-Response f
Jones&Carter,Inc. Page 1 of 2 Printed On: 11/14/2019 09:11 AM
RFI #148
,Response • Stephan t.... _ .- —i
Architect confirms option 1 is acceptable.
Attachments:
BY DATE COPIES TO
Jones&Carter,Inc. Page 2 of 2 Printed On: 11/14/2019 09:11 AM