Ordinance No. 12,082ORDINANCE NO. 12,082
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
AUTHORIZING CHANGE ORDER NO. 5 WITH T &C CONSTRUCTION, LTD., FOR
THE STEINMAN LIFT STATION PROJECT; AUTHORIZING PAYMENT BY THE
CITY OF BAYTOWN, THE SUM OF ONE HUNDRED EIGHTY -SEVEN THOUSAND
SIX HUNDRED NINETY -EIGHT AND 36/100 DOLLARS ($187,698.36); AND
PROVIDING FOR THE EFFECTIVE DATE THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the City Council does hereby authorize Change Order No. 5 with T &C
Construction, Ltd., for the Steinman Lift Station Project. A copy of said change order is attached hereto,
marked Exhibit "A" and made a part hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby authorizes the payment of ONE
HUNDRED EIGHTY -SEVEN THOUSAND SIX HUNDRED NINETY -EIGHT AND 36/100 DOLLARS
($187,698.36) to T &C Construction, Ltd., for Change Order No. 5 for the Steinman Lift Station Project.
Section 3: This ordinance shall take effect immediately from and after its passage by the City
Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the Council of the City of
Baytown this the 11'' day of October, 2012.
APPROVED AS TO FORM:
R:TCa nWiles \City Council \0rdin=ces\2012 \0ctober II \CbengeOrderNo5T &CCons uction4Steinin =LiftSmtionProject.doc
Mayor
Exhibit "A"
CITY OF BAYTOWN
Change Order No. 5
Steinman Lift Station and Force Main
3 -Oct -12
Brief Description of Changes: Continue utilizing bypass pumping and flow thru plug, applying a sealant to the
roof of the lift station, installation of aluminum hand railing at access hatch and HVAC unit, removing &
replacing a portion of the street and box culvert at Spur 330 and removing & replacing the existing sanitary
sever manhole at 1 -10.
Add or Delete Items:
Item
Description
Unit
Quantity
Unit Price
Total
46
Rental cost of bypass pumping equipment.
MO
4
S13.046.30
$52,185.20
52
Rental cost of flow -thru plugs.
MO
5
51,700.00
58,500.00
53
Apply water - proofing sealant to the lift station
roof.
LS
1
52,200.00
$2,200.00
Install alumnum safety hand railing at the
54
access hatch and HVAC unit.
L. F.
33
$90.00
52,970.00
55
Removal & replacement of a portion of the
street and storm box at Spur 330.
LS
1
S101,669.92
$101,669.92
56
Removal & replacement of existing sanitary
sewer manhole @ 1 -10
LS
1
$20,173.24
S20,173.24
Total
Contract Summary:
S187,698.36
Original Contract Price
S3,771,905.40
Previous Change Orders
$115,651.50
This Change Order
1
Revised Contract Price
$4,075,255.26
Original Contract Duration - Calendar Days
300
Previous Time Extensions
0
This Change Order
20
Revised Contract Duration - Calendar Days
T &C Construction, LTD
Director of Finance Date
Dray Crow. P.E. / Date
Jones & Carter, Inc.
Director of Engineering Dale
City Manager Date
320