CC Resolution No. 545 .mk1 799
RESOLUTION NO. 545
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS, RESOLVING THAT THE WEST DISTRICT SANITARY SEWER
IMPROVEMENTS WILL BE COMPLETED PURSUANT TO THE LAWS,
RULES, AND REGULATIONS OF THE FEDERAL WATER POLLUTION
CONTROL ACT AMENDMENTS OF 1972, PUBLIC LAW 92-500; AND
IN ACCORDANCE WITH THE SCHEDULE SET FORTH IN THE RESOLUTION;
AND FURTHER RESOLVING THAT NO CHANGE ORDER WILL BE
AUTHORIZED WITHOUT APPROVAL OF THE TEXAS WATER QUALITY
BOARD AND THE ENVIRONMENTAL PROTECTION AGENCY.
WHEREAS, heretofore on the 22nd day of August , 1974,
the City Council of the City of Baytown adopted Resolution
No. 478, setting a schedule for construction of certain
sewer facilities for the West Sewer District (WPC-Tex-1151
Job No. 044-OC-109) being constructed partially with federal
grant funds; and
WHEREAS, after the adoption of said Resolution No. 478,
on the 27th day of May, 1976, the Texas Water Quality Board
entered its Enforcement Order No. 76-31 requiring performance
of a systematic sewer system evaluation survey and changing
certain task dates such as those dates relating to submission
of the Facility Plan and an Environmental Assessment to the
Texas Water Quality Board; and
WHEREAS, because of these requirements it is necessary
for the City Council of the City of Baytown, Texas to approve
a new project schedule relative to the construction of sewer
facilities for the West Sewer District , under EPA Grant No.
WPC-Tex-1151; NOW THEREFORE,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
BAYTOWN, TEXAS :
Section 1: That the projected time schedule for the
completion of sewer treatment facilities for the West Sewer
800
District under EPA Grant No. WPC-Tex-1151 , Job No. 004-OC-
109 will be constructed to completion in accordance with the
laws, rules, and regulations and with the project schedule
which is attached hereto marked Exhibit "A, " and made a part
hereof for all intents and purposes.
Section 2 : Be it further resolved, that the City of
Baytown understands that the attached project schedule must
be approved by the Texas Water Quality Board and the Environ-
mental Protection Agency, and that once a project schedule
has been approved, no changes will be authorized without
first receiving approval of the change from the Texas Water
Quality Board and the Environmental Protection Agency.
INTRODUCED, READ and PASSED by the affirmative vote of
the City Council of the City of Baytown, this 23rd day
Of— September , 1976.
TOM GENTRY, Mayor
ATT-EST:
EILEEN P. HALL, City Clerk
APPROVED:
NEEL R/ICH DSON, City Attorney
-2-
I
sax
EXHIB IT "A"
802
PROJECTED TIME SCHEDULE �-
_ FOR x > N
WPC-TEX-1151-:
CITY OF BAYTOWN,-WEST SEWER- DISTRICT
f JOB NO.' 044-OC,-109 _
:"L Afu af• t- /'� Y�IY� .r. y - :• ci kit ,j 1yN emu.
4 DATE PERFORMER ITEM'
�09-01-76 LEI- 'Begin FaciIity .Plan and Environmental Assessment.
1.^\.� • . - _ - . •� -... ,.U�.. , .. f'..,.. "
}: 10-01-76 . City Finalize selection of treatment plant site. .
`10-01-76 LEI Begin application for amendment to�TWQB Permi-t.-No' 10395, p.5.
10-12-76. _ LEI Complete draft application for amendment to TWQB permit,
submit to City.
..-10-14-76 City Approve TWQB permit amendment application.
G-10-15-76 LEI . Submit permit amendment application to TWQB.
11-09-76 LEI Complete draft copies of .Facility Plan and Environmental
=_. Assessment,. submit to City Council
11-11-76 City --.Approve draft Facility Plan and Environmental Assessment,
:. set public hearing on same..
11-15-76 LEI "Publish notice of public hearing, mail copies of draft
., . to appropriate agencies, begin Step-2 application-,,
11-29-76 LEI Submit Step i reports,'' including I/I Analysis, Systematic
Sewer System-Evaluation -Survey Report, draft Facility
Plan :and draft Environmental Assessment to HGAC for review._..-;:_,_:�-
12-09-76 City Approve Step 2 application, submit to HGAC for review. :v `
12-16-76 City Hold public hearing on Facility Plan and Environmental
Assessment.
12-29-76 LEI Complete hearing transcript, finalize Facility Plan and
Environmental -Assessment, submit to HGAC.
01-04-77 HGAC Approval by project review committee.
803
PROJECTED TIME SCHEDULE i _ r,t • "
_FOR WPC-TEX4151
'"'JOB NO. 044 OC-109 (Cont'd) _ .
1 .i '.1 r � t•Y ��4l + 1 t 4 t • �.t �iQ• 4
.QL +.r t"z... .-. ..": c ,�••� .•• .%Y r • a tr.O<a•FG',' r Mnr••. :, Z:.
'fx• „ DATE• 'PERFORMER ' .� >: �Il'EM' �, 'r'#• rsi . �.
07-07-77 LEI. Su6mi t:fina-1 aci l i ty Plan,*- Environmental Assessment;-Step
.2 Grant Application to -TWQB.. - -
01-26-77 TWQB Issue amendment.to TWQB-.permit no: ;10395, p. 5 .
02-01-77 TWQB Cut off date for submittal-:of data-•••for- consideration on
-April 1977 Priority Rating List.
7. 03-07-77 TWQB/EPA Authorize beginning of Step 2 work.
03-07-77 'LEI Begin preparation of plans and specifications.
- .04-01-77 TWQB Establish April 1977 Priority Rating List
06-07-77 LEI Begin Step 3 application. 7.
N -
_. 06-20-77 LEI. Complete' plans'and specifications-and Step 3 application, +TM
Submit. to City for approval .--- w.� L
-06-23-77. ,- City Approve plans and ;Specifications- and_'Step 3 application.
06-24-77 LEI. Submit plans and specifications and Step 3 application to °►
HGAC for•:review and approval r `
n •
♦+ . .. - , ,• .. -.j adtT•'y�•'Z- -• '. �•• ..`^ - •...... 1 ...%. '' �..7�y. .� J r fret ,
07-08-77 LEI' Submit plansand specifications and Step 3 application to
= TWQB/EPA.
08-01-77 TWQB Cut off date -for submittal of data -for consideration on , -
October 1977.Priority Rating List.
10-01-77 TWQB Establish October 1977 Priority Rating List.
10-10-77 TWQB/EPA Authorize beginning of Step 3 work and advertisement for
bids.
804
! •' - h dry.•�
^
PROJECTED TIME SCHEDULE ' s nF,y.
`:FOR WPO-TEX-1151
=•J0B NO. 044-OC-109 (Cont'd)
;•..
<. �r'rll� VDATE rPERFORMER ITEM y r
'Vale 1T •y`�ra.1 - L• _ r'' !'1c
' LEI Advertise
for bids. _ r
r`� '- �� - : -, ••� ;� :,•.��� bids:
11-10-77, City Receive and review ,
11-18-77 , LEI Submit• bidder: list and recommendations .for award to.TWQB/EPA
for. approval..'.
• 01-10-78 TWQB/EPA Authorize award.of contract. :.
~ -` • t .,01-12-78. City Award Contract.
01-13-78 LEI Issue work order. >;
01-23-78 Contractor Start construction. _
06-01-78 LEI Begin NPDES application`:
06-20-78 LEI__ Submit NPDES,application to City.
06-22-78 city Approve NPDESapplication,• submitto- EPA.. ` •'' .
' 12-31-78 Contractor Complete construction*