Loading...
BAWA Resolution 2020-12 RESOLUTION NO. 2020-12 A RESOLUTION OF THE BOARD OF DIRECTORS OF THE BAYTOWN AREA WATER AUTHORITY AUTHORIZING CHANGE ORDER NO. 11 WITH PEPPER LAWSON WATERWORKS, LLC, FOR THE BAWA 6 MGD SURFACE WATER TREATMENT PLANT PROJECT IN THE AMOUNT OF ONE HUNDRED EIGHTY-EIGHT THOUSAND TWO HUNDRED SIXTEEN AND 36/100 DOLLARS ($188,216.36); AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. BE IT RESOLVED BY THE BOARD OF DIRECTORS OF THE BAYTOWN AREA WATER AUTHORITY: Section 1: That the Board of Directors of the Baytown Area Water Authority does hereby authorize Change Order No. 1 1 with Pepper Lawson Waterworks, LLC, for the BAWA 6 MGD Surface Water Treatment Plant Project. A copy of said change order is attached hereto, marked Exhibit "A" and made a part hereof for all intents and purposes. Section 2: That the Board of Directors of the Baytown Area Water Authority hereby authorizes the payment of an amount not to exceed ONE HUNDRED EIGHTY-EIGHT THOUSAND TWO HUNDRED SIXTEEN AND 36/100 DOLLARS ($t88,216.36) to Pepper Lawson Waterworks, LLC, consistent with the change order authorized in Section 1. Section 3: This resolution shall take effect immediately from and after its passage by the Board of Directors of the Baytown Area Water Authority. INTRODUCED, READ and PASSED by the affirmative vote of the Board of Directors of the Baytown Area Water Authority this the 19`l' day of August, 2020. BRENDA BRADLEY SMITH, President ATT T: LETICIA BRYSCH, Assistant Secretary Y o S �y`- APPROVED AS TO FORM: �''►11 j1j 11114N�• KAREN L. HORNER, Interim General Counsel R:',.Karen Anderson\RESOLUT IONS.BA WA'2030.08.191Resolution-Change Order No. 1 l Pepper Lawson.doc Exhibit "A" BAYTOWN AREA WATER AUTHORITY to Change Order No. 11 BAYTOWN 6.0 MGD SURFACE WATER TREATMENT PLANT PO: 1806021 Date: 13-Aug-20 Brie escrfption of Changes: CO 11.1 is to request for extra cost due to City of Houston's additional flow meter signal modificaiton. CO 11.2 is for the additional cost for drain line modifications in response to RFP#013. CO 11.3 is for the shunt trip disconnect for elevator in order to meet code for inspection. CO 11.4 is for the protective separation basins required for the sodium chlorite and hydrochloric acid stored in the chemical containment area.This will ensure the safety of the occupants from chlorine gas. Add or Delete Items: Item Description Unit Ouantity Unit Price TOta 11.1 City of Houston Flow Meter Signal Modifications(PCO 073) 1 LS 9,026.80 $ 9,026.80 11.2 Drain Line Modifications(PCO 074B) 1 LS 169,163.74 $ 169,163.74 11.3 Shunt Trip Disconnect for Elevator(PCO 075) 1 LS 4,120.38 $ 4,120.38 11.4 Chemical Vat Separators(PCO 077) 1 LS 5,905.44 $ 5,905.44 Total $ 188,216.36 Contract Summa : Original Revised 1 Original Contract Price $52,186,000.00 2 Owner Contingency $0.00 Previous Change Orders This Change Order Remaining Contingency 3 Change Orders Previous Change Orders $ (3,292,800.76) This change order $ 188,216.36 4 Revised Contract Price $52,186,000.00 $49,081,415.60 Original Contract Duration 1095 Previous Extensions 0 This Change Order 0 Revised Duration-Calendar Days 1095 08/13/2020 Contractor: 2PLW Waterworks,LLC Date Director of Public Works&Engineering Date Chris Smith,Executive Vice President Frank O.Simoneaus Jr.P.E. Consultant: Jones l Carter,Inc. Date City Manager Date Richard L.Davis,ICMA-CM P [W waterworks June 24, 2020 Mrs.Andrea Brinkley Assistant Director Baytown Area Water Authority The City of Baytown 2401 Market St. Baytown,TX 77520 Re: CPR No. 73 BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. 1806021 Mrs. Brinkley, Please see attached proposal for the City of Houston Flow Meter Signal Modifications per RFP 9012. This change will result in a increase in the amount of$9,026.80 Please feel free to contact me at(713) 301-8637 with any questions or concerns. Regards, PLW Waterworks Katy Drown Project Manager Page 1 Baytown Area Rater Authority CPR No.: #073 BABA 6 MGD Surface Water Treatment Plant Date: 06/2.1/20 BAWA Job No.1906021 PLW Job No.: P3T City of Houston Flow Meter Signal Modifications Scone or W ork City ofHoustun Flow Meter Signal Modifications Non-Tried Labor Material S,bnnnraa Taaed Mafl/E ai Item Unit Total Unit Total Cni, Total Unit Total No. Description Ow Unit Con Cost Cost Cost Cnss Cast Cost Cost 1 City of Houston Flow Meter Modifications Ll P riL ffer and Sons&Prime Camels I LS S - S - S - S - S 7,62077 S 7.620.77 S - S - Direet Cost Sablotal 7,2077 - Small Tools(rd5.0% - n/a - niI u Equipment Burden @ 50.0% na n'a a a n Tax(118.25% na n'a ua Subtotal - - 7,620 77 Ovalwad&Kato a 15 0°0 1.1 11 12 Subtotal - - 976189 - Bonds&lmomncc Irr.3.0°a 16292 Subtotal 4 9.026 80 Total of all culunnu 9.02680 Odscr Grand Total Cost 9,026.80 Page 2 J O N E S CARTER RFP NO.: 012 REQUEST FOR PROPOSAL (RFP) 1. PROJECT NAME: 6 MGD Surface Water Treatment Plant 2. AC PROJECT NO.: 09986-0002-00 3. CONTRACTOR: Pepper Lawson Waterworks 4. SUBMITTED TO: Katy Drown 5. SUBJECT: City of Houston Flow Signal 6. REFERENCE: 7. REF.DWG.NO.: 2-E-1 8. REF.SPEC.NO.:N/A 9. DESCRIPTION OF WORK: The Contractor is requested to furnish a price proposal for the below described work. Please complete,sign,date,and return a proposal at your earliest convenience. Please attach a detailed cost breakdown to your proposal. BAWA has requested that the flow signal from the City of Houston flow meter be added and implemented to the Plant Overall SCADA system. Please provide a cost for the following items: 1. NEMA 4X enclosure that includes all ancillary items to connect to City of Houston flow meter signal. 2. Conduit from new enclosure to stubbed-up conduit 2-001-1007. 3. Signal wiring from new enclosure to 24-PLC-001 through conduit 2-001-1007. 11. Requestor's Name&Signature: Larry Weppler Date: 6/9/20 The Contractor acknowledges that this RFP is to be used to request pricing information only,and does NOT constitute a contract modification. The Contractor is NOT AUTHORIZED/DIRECTED to perform this work UNTIL/PRIOR TO written notification that a contract modification is approved. I:wp\Eccs\coot\Forms\fi or rfp\rfpform.doc REV 9/14/00 PFEIFFER & SON, LTD. Electrical Contractors PHONE-(281)471-4222 * FAX-(281)471-6856 116 N. 16TH ST. * P.O.BOX 1116 LA PORTE,TEXAS 77572 jonathan c)pfeifferandson.com CHANGE ORDER BID DATE: JUNE 23,2020 TO: PLW WATERWORKS ATTN: LAIRS.KATY DROWN PROJECT: BAWA 6 MGD SURFACE WATER TREATMENT PLANT We request,as discussed,the below listed change order for the BAWA 6 MGD SWTP project. Please see the price below for your consideration and reference the below list of exclusions and clarifications as well as the attached documents. We propose to furnish all material,labor,equipment,and supervision in a safe and skillful manner for a complete and functioning system. RFP 12 ELECTRICAL—2-FE/FIT-001 SIGNAL SPLITTER ENCLOSURE $7,620.77 To avoid confusion,we offer the following clarifications: 1. Above price includes provision and installation of NEMA 4X signal splitter enclosure and all conduit and conductors for connection of that equipment for transmission of the flow signal from the splitter enclosure to 24-PLC-001 2. Pricing includes required programming modifications to make flow signal from 2-FE/FIT-001 visible in plant SCADA system. 3. See attached subcontractor quote and pricing breakdown for additional detail. 4. Bond is included. 5. We will provide insurance coverage in accordance with the specifications. Builder's Risk insurance covering our scope of work is not included,as this should be the General Contractor's responsibility, and therefore we assume no responsibility for theft or vandalism of installed material. Additional coverage specifically required by the contractor may necessitate additional premium charges. We appreciate this opportunity to quote on this project. If you have any questions or need additional clarifications,please call me at(281)471-4222. Sincerely, PFEIFFER&SON,LTD. Jonathan Pfeiffer RL'(GIPLATED BY Till.II:XAS 011'AR I MINI IW LICENSING AND REW T.AI ION CO MRACT()R S I.ICL'NSE k 18259 P U BOX 12157•AtISTIN.TX 79-11 Ix0(1))q)3.92D9•4512)463-6599 hcensc stale Inc u.,lconipla)nts ADOPTED ADMINISMA'MRIR.LS 7351 N)I:LLC7RICM CONTRACl'ORJ'Rl-'VONSIBITITIFS PFEIFFER SON, LTD. Electrical & Telecommunication Contractors PFEIFFER AND SON JOB#4200119 CHANGE ORDER REQUEST Date: 6/23/2020 Project: BAWA 6MGD SWTP Description: Installation of signal splitter enclosure and modifications to plant SCADA for monitoring of 2-FE/FIT-001 1 General Labor 30.00 hours x$ 29.9 897.00 2 Supervisory Labor 3.00 hours x$ 55.0 165.00 3 Subtotal items 1 and 2 1,062.00 4 Labor Burden 55%x Item 3 584.10 5 Cost of Materials 1,460.54 6 Equipment 195.00 7 Cost of Transportation 0.00 8 Subcontractor 2,895.00 9 Subtotal items 3,4,5,6 and 7 6,196.64 10 Cost of Insurance 4%x item 8 247.87 11 Cost of Bonds (7.4.2.2.4) 182.24 12 Subtotal lines 8,9 and 10 6,626.75 13 Overhead 10% 662.68 14 Profit 5% 331.34 15 Not Used 0.00 16 Total change order amount items, items 11,12,13 and 14 $ 7,620.77 Page 1 PRIME CONROM 12144 DAIRY ASHFORD, BLDG 3 • SUGAR LAND, TX 77478 PHONE 713.244-9747 0 FAX 713-244-9717 June 18, 2020 To: Pfeiffer&Sons 116 N 16th St La Porte,TX 77571 Attn: Jonathan Pfeiffer Mark Antley Ref: BAWA 6 MGD Surface Water Treatment Plant Project Work Authorization No. 265 Prime Controls Change Order No.: PCO-008 PRIME CONTROLS PROPOSAL Prime Controls is pleased to offer this proposed change order(PCO)to add the City of Houston Flowmeter Signal into the SCADA System as per RFP-12 with the referenced Baytown Area Water Authority 6 MGD Surface Water Treatment Plant project as described hereafter. Our Scope of Work shall include applicable products and services specified to be provided in the following bid specifications: The offering is complete with the exception of those items specifically excluded within the"Exclusions" section of this proposal. Equipment and Materials to be provided by Prime Controls include the following major items: ITEM EQUIPMENT 1. One (1) NEMA 4X Wall Mount Enclosure and Backpanel (Panel size to match City of Houston Enclosure) 2. One (1) 24VDC Surge Suppressor 3. Lot terminal blocks,wire tags,tie wraps,etc. Services to be provided by Prime Controls include the following major items: ITEM SERVICES 1. VTSCADA HMI Programming Mods to add the City of Houston Flowmeter Signal to HMI AB PanelView HMI Programming Mods to add the City of Houston Flowmeter Signal to Local HMI on 2' PLC Panel 3. PLC Programming Mods to add the City of Houston Flowmeter Signal to Local HMI on PLC Panel 4. Field terminations within City of Houston Flowmeter and new enclosure for pulse output signal S. Field terminations with PLC Panel to add new signal Page 1 of 2 PRIME Cm PROPOSAL CLARIFICATIONS ITEM CLARIFICATION 1. Prior to commencement of work, Prime Controls requests an executed copy of this change order request.We expect this change will be accepted in a timely manner. Prime Controls is not liable for schedule delays associated with this change in the scope of work. 2. Pricing shall be valid for 30 days only from proposal date. 3. Acceptance of an order shall be subject to the attached General Terms&Conditions.These General Terms and Conditions are superseded by current Master Service Agreements (MSAs),Contracts, Subcontracts and/or Blanket Purchase Orders that authorize this work. EXCLUSION ITEM EXCLUSION 1. Conduit and wiring additions 2. Physical installation of control panel (to be provided by Pfeiffer) PROPOSED CHANGE ORDER PRICING ITEM DESCRIPTION PRICING 1 City of Houston Flowmeter Signal Addition $2,895.00 Proposal Approval Approved by(print): Signature: Date: We sincerely appreciate this opportunity and look forward to being of service for this work. Thanks again and please feel free to call if there are any questions. Sincerely, Prime Controls, LP �-40 Michael Nivong Project Manager 713-244-9747 m.nivong@prime-controls.com Prime Controls Proposal Page 2 of 2 PIW waterworks August 7, 2020 Mr. Andrea Brinkley Assistant Director Baytown Area Water Authority The City of Baytown 2401 Market St. Baytown,TX 77520 Re: CPR No. 74 BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. 1806021 Mrs. Brinkley, Please see attached proposal for the storm drain line modifications and re-route of chemical containment/storm lines,per RFP #013. Total Construction duration will be approximately 4 weeks. This change will result in a increase in the amount of$169,163.74. Please feel free to contact me at (713)301-8637 with any questions or concerns. Regards, PLW Waterworks Katy Drown Project Manager Page 1 Bartonn Area Water Authority CPR No.: 0074 BA WA 6 N1GD Surface Water Treatment Plant Date: 08/07/20 BAWA Job No.1806021 PLW Job No.: P3T Sanitary Drain Line Modifications Scone of Work Chemical Area Drainage Modifications Nan-Taxed Lot r Material Solar ract Taxed Mat'pE ui Item Unit rural Unit Total Unit Total Unit Tom1 No. Description of, Unit Cost Cast Con Cost Cost Cost Cost Cast 1 Project SmR(4 Weeks Total Construction Activities) Senior Prajet Manager 50 FIRS S 145.00 S 7,250.00 S - $ - S - $ - $ - S - Superintendent 80 FIRS S 121.00 S 9,680.00 S - S - $ - S - $ - S - Project Engineer 20 FIRS S 35.00 S 1,700AO S - 5 - S - 4 - S - b - 2 Loading Dock Type"A"Inlet Modifications It Weeks Straight Time) 2.1 Foreman 40 FIRS S 65.00 S 2,600.00 S - 5 - S - S - $ - S - 2.2 Sax cut appros.150'x 6'section of pavemem and haul on I LS S . S . S - S - S - S - S 9.734.00 S 9,734.00 2.3 Operator and Mini Excavator(removal ofc-sand) 60 FIRS S 50.00 S 3.000.00 S - S - S - $ - S 37.50 S 2.250.00 2.4 (2)laborers shoveling and breaking up c-sand 110 FIRS S 39.00 S 4,180.00 $ - S - $ - S - S - S - 2.5 Core 8"We in existing manhole I LS S . S - S - 3 - S - S - included above S - 2.6 Place low strength grout(PLW purchase,order pricing) 6 YDS S 38.00 S 140.00 S - S - S - S - S S - 2.7 Install 8"PVC(2 Pipe Filters,5 Days) Pipe comes in'-O'sections,cut.6t and timing we on pipe 80 FIRS IF 45.00 3 3,600.00 S J,'_94.73 S 4?94.]3 $ - $ - $ - S - 2.8 Supply and Install Bank Sand 34 C%TSS S 38.00 S 304.00 S 12.50 S 425.00 S - S - S S - 2.9 Supply and install c-sand and compact 243 TONS S 38.00 S 1,520.00 S 27.50 S 6,682.50 S - S - S 225.00 S 1,125.00 2.10 Lull and Operator Unload and assist in plaong pipe 50 IIRS 3 50.00 $ 2,400.00 S . S . $ - S - S 81.25 3 3,250.00 2.11 Fort Pad(2 Carpenters,4 flours) 8 FIRS S 45.00 S 360.00 S 109.00 $ 2,189.00 S - S - S - 3 - a-.12 Four,Place and Finish Concrete 972 SOFT S - S - $ - S - $ 10.00 S 9,720.00 $ 250.00 $ -50.00 2.13 Road Plans(including Ddivep/Pickup) I MO $ - $ - S - S - E - S - S 1200.00 3 1,200.00 3 Chemical CmhJ near Drainage Lim Modifrcatiom(2 Weeks Straight Time) 3.1 Foreman 110 [IRS S 65.00 S 7350.00 $ - S - $ - $ - S - 3 3.2 Sawed approz 135'x 6'scction ofpaxing 1 LS S . $ . S - S - $ - $ - ncluded above S - 3.3 Operator and Mini Excavator(removal ofe-sand) 40 FIRS $ 55.00 $ 2,200.00 S - S - $ - $ - S 37.50 $ 1,500.00 3A Operator and Mini Excavator bournimn time) 20 FIRS $ 82.50 $ 1,650,00 S - S - $ - S - S 37.50 3 750,00 3.5 (2)Laborers shoveling and breaking up wand 100 IIRS $ 35.00 S 3,500.00 $ - S - $ - $ - $ . $ - 3.6 Excsamrand Operator 60 FIRS S 65.00 S 3,900.00 S - S - $ - $ - $ 148,08 3 8,894.80 3.7 Delivery/Pickup 2 EA S S - $ - $ - S - $ - S 500.00 S 1,000.00 3.8 Supply and Install Bank Sand 90 CYDS S 38.00 S 1,520.00 S 12.50 S 1,125.00 S - S - S 225.00 S 1,350.00 3.9 being 8"PVC(2 Pipe Filters,5 Days) 400 LF S 15.00 3 6,000.00 Included Above b - S - S - S S - Pipe comes in 20'sections,cut,fit and innall ace on pipe 3.10 Install c-sand and compact 210 TONS S 35.00 S 1.400.00 S 27.50 S 5,775.00 S - $ - S 225.00 S 1,350.00 3.11 Form,Place and Finish Concrete 834 SOFT S - S - S - S - $ 10.00 S 8,340.00 S 250.00 S 250.00 3.12 Street Sweeper 2 WKS S - S - $ - S - S - S . S 600.00 S 1200.00 Direct Cost Subtotal 64,054.00 20,591.23 18,060.00 34,093-80 Snell Tools m.5.0% 3.202.70 ma - Na Na Equipment Burden rt 50,09a Na Na n(a Na Tox w 8.25'. Na ma Ida 2.812.74 Subiotal2 67_156.70 20,591.23 18,060.00 36,906.54 Overheads P1.Bt 1. 15.0P. 10,088.51 3,088.68 2,709.00 5.535-99 Subtotal 3 77,345.21 23,679,91 20,769.00 42,442.52 Bonds s lnsurance,a 3.0% 2,320.36 710.40 623.07 1�27328 Subtotal 79.665.56 24,390.31 21,392.07 43.715.79 Total of all colmms 169J6374 Other Grand Total Cost 169,163.74 Page 2 0 1 J O N E S CARTER RFP NO.: 013 Amendment REQUEST FOR PROPOSAL (RFP) 1. PROJECT NAME: 6 MGD Surface Water Treatment Plant 2. AC PROJECT NO.: 09986-0002-00 3. CONTRACTOR: Pepper Lawson Waterworks 4. SUBMITTED TO: Katy Drown 5. SUBJECT: Chemical Area Drainage Modifications 6. REFERENCE:Attached Markups 7. REF. DWG.NO.: N/A 8. REF.SPEC. NO.: 9. DESCRIPTION OF WORK: The Contractor is requested to furnish a price proposal for the below described work. Please complete,sign,date,and return a proposal at your earliest convenience. Please attach a detailed cost breakdown to your proposal. r3peenoill Way Type"A" Inlet Medifi eat i ens MaFkupq 2. Loading Dock Type"A" Inlet Modifications a. Grout fill the manhole to an elevation of 26.46 with lightweight or low strength grout b. Core through manhole and install 155.5 LF of 8" PVC stormwater pipe at a 0.33°%slope as shown in the attached markups c. Route the pipe as shown in the attached markups d. Install a 4'x 3'x 4"concrete pad at discharge of pipe as shown e. Remove and replace concrete pavement per detail sheet 0-C-12 Amendment: 3. Chemical Containment Drainage Line Modifications a. Cut and plug the 12" DI-SS line at an elevation of 24.5 as shown in the attached markups b. Install a 45°Bend at location of cut and route 375.5 LF of 8"PVC chemical pipe at a 0.33%slope as shown in the attached markups c. Core through Manhole No.2 located next to the Backwash Equalization Basin d. Remove and replace concrete as needed for installation of the 8"PVC line per detail sheet 0-C-1 11. Requestor's Name&Signature: Larry Weppler Date: 6/9/20 The Contractor acknowledges that this RFP is to be used to request pricing information only,and does NOT constitute a contract modification. The Contractor is NOT AUTHORIZED/DIRECTED to perform this work UNTIL/PRIOR TO written notification that a contract modification is approved. I:wp\docs\cans[\forms\di or Hp\rfpformdoc REV 9/I1i00 JR1L3_ 4i 1 6 ..-ova+_T_ J G • 1I) e 7 <. y =L�IQ' �� 'fil1Oil O; i � `I v r..e --------- IL 1. I � •�� 1 II v �� � II m._ �_ i _ ..r .. . _ 1 _ i /II ( 1 �y ��� II P.s,� � h ,9 . .. II I � � I I •.M m:�w:�a II1 Po eaEErT PIPIN4 T L, ii ,li_T 1 / .,(➢ s s or is it /ri '' `' S • � y\ J�JONEB C/�RT6R ut)C//[/NC SN.O yYywG LY. 1-G-35 S� °�. Aggregate Technologies, Inc. Quote dog 10700 Tower Oaks Blvd. Quote: 02473 Houston, TX 77070 (281) 579-7229 Quote Date: 7 Aug 2020 Toll Free: 877-SLABSAW Quote Expires: 9 Sep 2020 Job Name: CEDAR PORT AGGREGATES TERMINAL Task Type(s): DSS,CD Sales Rep: CHRISTOPHER ALLEN (832) 621-6291 Prepared For Job Site Address PEPPER-LAWSON WATERWORKS 5341 E Grand Pkwy S Baytown, TX 77523 1725 HUGHES LANDING BLVD SUITE 1200 The Woodlands, TX 77380 Qty Description Price Total 1 SAWING-SLAB Length: 9,484.00 EACH 9,484.00 Depth: Slab Sawing and Removal of two trenches (1) 150'x6' and (1) 135' x 6', Concrete is based on being 6"thick. All Sawing and Removal to be done in one mobilization. 2 CORE DRILLING Diameter: 125.00 EACH 250.00 Depth: Core Drilling (2) 8" holes in 6" paving price is per hole. Work is based on being completed at the same time as saw cutting and demo. If work is done in a separate mobilization price will be a min charge of$550. 9,734.00 Exclusions: Layout of any sawing, trench covers, access, permits, water control, dust control, barricading, traffic control, escorting, breaking, protection of any properties, damage to any unmarked utilities, final cleanup of work area and concrete pour back. TERMS: DUE UPON RECEIPT I A 1.5% PER MONTH(18%PER ANNUM)SERVICE CHARGE WILL BE ADDED TO PAST DUE INVOICES •`•WE ASSUME NO RESPONSIBILITY FOR LAYOUT••• Invoices calculated at measured quantities. ASSUMPTIONS:UNLESS OTHERWISE NOTED,CUSTOMER IS IT IS EXPRESSLY AGREED AND UNDERSTOOD THAT ATI IS NOT RESPONSIBLE TO PROVIDE: RESPONSIBLE FOR: -Clean work area free of any obstructions. -Traffic control,purchase or pulling of any permits -Water control(including clean-up)or any protection of property. -Any damage to buried structures,utilities or post tension cables. -Lift or scaffolding. -Barricading openings or safeguarding work performed. Printed: 08/07/2020 01:46:32 PM www.aggregatetechnologies.com Page 1 of 2 izml Bid Proposal for Baytown - Drain Pipe Amendment #13 PEPPER LAWSON WATERWORKS LLC Job 3701 KIRBY DR 41133 Baytown - Drain Pipe Amendment#13 HOUSTON,TX 77098 Bid Date: 07/07/2020 Bid #: 1402543 Sales Representative Core & Main Greg Arentz 7620 Grissom Rd (M) 210-379-7606 San Antonio, TX 78251 (T) 210-657-1632 (T) 210-684-1150 (F) 210-657-2321 Greg.Arentz@coreandmain.com 07/06/2020-9:12 PM Actual taxes may vary Page 1 of 2 izm Bid Proposal for Baytown - Drain Pipe Amendment #13 PEPPER LAWSON WATERWORKS LLC Core&Main Bid Date:07/07/2020 7620 Grissom Rd Core& Main 1402543 San Antonio,TX 78251 Phone:210-684-1150 Fax: 210-684-5521 Seq# QtY Description Units Price Ext Price 60 LOADING DOCK TYPE A 70 168 8 PVC SDR26 HW SWR PIPE(G) 14' FT 4.45 747.601 80 _ 2 8 HW SWR SDR26 45 GXG EA _ 71.53 143.06 90 1 12 LINK SEALLS-475-SS EA 15.91 190.92 12 LINK F/8" HW IN 12 HOLE 120 _ CHEM CONTAINMENT DRAIN 130 392 8 PVC SDR26 HW SWR PIPE(G) 14' FT 4.45 1,744.40 --- 140 _ 1 8 PRESS-SEAL B00T F/CONC MH EA 55.00 55.00 160 6 8 HW SWR SDR26 45 GXG EA 71.53 429.18 j 170 2 8X8 HW SWR SDR26 WYE GXG _ EA 129.88 _ 259.76 190 - 2 8 SDR35 CLEANOUTADPT HXF L/PL EA _ 61.58 123.16 200 2 8 PVC SWR CLEANOUT PLUG MIPT _ EA 44 93 _ _ 89,86 230_ 2 12 PVC SDR35 SWR SPIGOT PLUG _ — —EA Sub 6.101 4,172.20 85 _ Tax 0.001 Total —4,734.85 ' Branch Terms: 4,294.71) UNLESS OTHERWISE SPECIFIED HEREIN,PRICES QUOTED ARE VALID IF ACCEPTED BY CUSTOMER AND PRODUCTS ARE RELEASED BY CUSTOMER FOR MANUFACTURE WITHIN THIRTY(30)CALENDAR DAYS FROM THE DATE OF THIS QUOTATION.CORE&MAIN LP RESERVES THE RIGHTTO INCREASE PRICES UPON THIRTY(30)CALENDAR DAYS'NOTICE TO ADDRESS FACTORS,INCLUDING BUT NOT LIMITED TO,GOVERNMENT REGULATIONS,TARIFFS,TRANSPORTATION,FUEL AND RAW MATERIAL COSTS. DELIVERY WILL COMMENCE BASED UPON MANUFACTURER LEAD TIMES.ANY MATERIAL DELIVERIES DELAYED BEYOND MANUFACTURER LEAD TIMES MAY BE SUBJECT TO PRICE INCREASES AND/OR APPLICABLE STORAGE FEES.THIS BID PROPOSAL IS CONTINGENT UPON BUYER'S ACCEPTANCE OF SELLER'S TERMS AND CONDITIONS OF SALE,AS MODIFIED FROM TIME TO TIME,WHICH CAN BE FOUND AT: https://coreandmain.com/TandC/ 07/06/2020-9:12 PM Actual taxes may vary Page 2 of 2 I & A CONSTRUCTION 19691 Lazy Lane Porter,Tx 77365 Tel: 832-752-2859 Fax: 281-987-2025 ribarraconstruction CcDvahoo.com July 7, 2020 To whom it may concern, I&A Construction proposes to Prep and Pour(Labor& Material)the following areas at the BAWA 6 MGD Surface Water Treatment Plant Project in Baytown,TX: First item removed -$3,718.89 during latest revision Loading Dock (Approx. 972sf @ $10.00 a square foot) _$9,720.00 Containment Area (Approx.834sf @ $10.00 a square foot) _$8,340.00 Total Proposal Price: $2,jCS7 O 90 $18,060 This proposal excludes the following items: Electrical Power for Vibrators Formwork Systems Curing Compound Material & Labor Concrete Pump Truck and Hose I&A will provide full insurance and workers compensation for all employees. Thank You for this opportunity. Please feel free to contact me if you have any questions or concerns. We look forward hearing back from you. Best Regards, Refugio Ibarra I&A Construction P [W waterworks July 7,2020 Mrs.Andrea Brinkley Assistant Director Baytown Area Water Authority The City of Baytown 2401 Market St. Baytown,TX 77520 Re: CPR No. 75 BAWA 6 MGD Surface BAWA Job No. 1806021 Mrs. Brinkley, Please see attached proposal for shunt trip breaker and disconnect in order to meet code for elevator inspection. This change will result in a increase in the amount of$4,120.38. Please feel free to contact me at(713)301-8637 with any questions or concerns. Regards, PLW Waterworks Katy Drown Project Manager Page 1 Baytown Area water Authority CPR No.: #075 BA WA 6 DIGD Surface Water Treatment Plant Date: 07/0720 BAWA Job No.1806021 PLW Job No.: P3T Elevator Disconnect Scene of Wark Shunt Trip Disconnect for Elevator Non-Taxed Labor binterial Subcontract Taxed Mat'UF.t ui s Item Unit Total Unit Total Unit Total Unit 'I'wal No. Descri lion Unit Cost Cost Cost Cost Cost Cost Cost Cost I Disconnect Required to meet NFPA Code 1.1 Advantage I LS $ - S - 5 - 5 - S 2,127.00 S 2.127,00 S - s - 2.2 P&S I LS S - S - S - S - S 1,351.58 S 1.351,58 S - S - Direct Cam Subtotal - 3.478.58 - Small Tools @ 5.0% - Na - Na MI. Equipment Burden 0, 500'. Na Na oda wa Too,(P825°e Nu Na Na Subtotal - - 3.479,59 Overhead 8 Profit 0 I S W. 521.79 Snlaota13 - 4,000.37 - Doads K lasumace(it,3.0"0 120.01 Subtota14 4.120.38 Taml of all columns 4,120.38 Other Grand Total Cost 4,120.38 Pege 2 PFEIFFER SON, LTD. Electrical & Telecommunication Contractors PFEIFFER AND SON JOB#4200119 CHANGE ORDER REQUEST Date: 6/23/2020 Project: BAWA 6MGD SWTP Description: Installation of Shunt Trip Disconnect for Elevator 1 General Labor 8.00 hours x$ 29.9 239.20 2 Supervisory Labor 1.00 hours x$ 55.0 55.00 3 Subtotal items 1 and 2 294.20 4 Labor Burden 55%x Item 3 161.81 5 Cost of Materials 578.00 6 Equipment 65.00 7 Cost of Transportation 0.00 8 Subcontractor 0.00 9 Subtotal items 3,4,5,6 and 7 1,099.01 10 Cost of Insurance 4% x item 8 43.96 11 Cost of Bonds (7.4.2.2.4) 32.32 12 Subtotal lines 8,9 and 10 1,175.29 13 Overhead 10% 117.53 14 Profit 5% 58.76 15 Not Used 0.00 16 Total change order amount items, items 11,12,13 and 14 $ 1,351.58 Page 1 L.VIA, � 7840 West Little York Phone: (713)983-7253 INMEAI //E Houston, Texas 77040 Fax: (713) 983-7292 �L w Web:www.advantagefireorotection.com INTERESTS INCORPORATED cbrvson(a)advantaoefireorotection.com m PRUfB(.TNYi I SBCURIIY I SYSr8F1 PrCEGRATDN PROJECT CORRESPONDENCE (External) TO: PLW Waterworks Project No. 18-092 5359 E. Grand Parkway S. Baytown,TX 77523 Date: June 23, 2020 ATTN: Joseph Tocci PROJECT: BAWA Plant SUBJECT: Change Request 4 (CR004-1100) Fire Alarm/ Elevator Shunt Trip Breaker Advantage Interests is pleased to offer for your consideration the following change request proposal for the above referenced project. Our proposal is outlined in the following sections: I. Bill of Material II. Scope of Work III. Exclusions IV. General Terms and Conditions Thank you for the opportunity to provide quality equipment and services for your fire protection needs. If you have any questions or require additional information,please do not hesitate to call. Respectfully, Craig Bryson Account Manager Accepted by: Date: Page I oft I. BILL OF MATERIAL 1. Fire Alarm System t . Description 1 ea Power Supply 1 ea Addressable Relay Module 2 ea Addressable Monitor Module 1 ea Control Relay, DPDT I OA Contacts 1 lot Programming 1 lot Installation Labor and Materials Our price for this scope of work is: $2,127.00 II. SCOPE OF WORK 1.1 Provide and install equipment and devices to interface the fire alarm system with the elevator shunt trip breaker. 1.2 Provide and install approximately 20 feet ''/a" EMT conduit and wire for connection to the fire alarm system. 1.3 Provide programming, final test and addition to as-built plans. III. EXCLUSIONS 1.1 Providing and installing 120vac to the power supply. 1.2 Providing, installing and terminating circuit to shunt trip breaker. We are providing a relay as a point of connection for the electrician. IV. GENERAL TERMS and CONDITIONS 1 Delivery Point 1.1 The delivery point shall be F.O.B. Jobsite. 2 Terms of Payment 2.1 Terms are net 30 days from invoice date. 3 Taxes 3.1 Taxes on materials and labor are not included. The project is tax exempt. V�OVAA" Page 2 of 2 SUPPLEMENT 2 Interfacing Fire Alarm Systems and Elevator Controls Bruce Fraser SimplexGrinnell, L.P. Editor's Note: The relationship hetroeen fire ahom s_vsterrt.s and elevator control ss'slems, and how these systems interface with each other: has had a long history, one that is still evolving. This supplement sununaizes the historical development of these relalionshipa and proride.s insight into the requirements for firefighters' recall and elevator shutdown. HISTORICAL PERSPECTIVE OF building occupants using elevators during a fire, it was FIREFIGHTERS' RECALL AND important to prevent those occupants and visitors of the ELEVATOR SHUTDOWN building from using elevators during a fire.It was believed that the safer option was for everyone physically capable Background of using the stairs to exit the building to do so.This strategy Safe operation of elevators has always been paramount to would also make elevators available to firefighters for stag- the elevator industry. In the late 1960s and early 1970s, ing their equipment on floors closer to the fire floor and attention was drawn to the impact of fire on elevator safety. for evacuating those individuals incapable of self-rescue. Thought was given to human behavioral actions as well as the electrical and mechanical aspects. In a high-rise Conflicting Codes building fire, for instance, passengers overcrowding an elevator in their panic to leave the building might disable Many individuals who must deal with the coordination of an elevator, or the elevator might actually be called to the building codes and standards understand that it is difficult fire floor by the actuation of a call button that has shorted to keep the building elevator, sprinkler, and fire alarm or by one that reacts to heat. People unaware of the fire codes in step with each other — initially because of a condition on an upper floor might continue to use the general lack of coordination between the various code com- elevators to access the building. It was generally agreed minces. Today, there is a concerted effort for cooperation that because of the various unsafe conditions faced by with the code-making bodies and the fire services. Still,it Bruce Fraser of SimplexGrinnell in Westminster,Massachusetts,is a member of the Technical Correlat- ing Committee on Signaling Systems for the Protection of Life and Property. He also serves as a member of the NFPA Technical Committees on Supervising Station Fire Alarm Systems, Safety to Life,Building Code,Telecommunications.Clean Rooms-,and Premises Security.In addition,Mr.Fraser is a member of ASME A17.1 Safe), Code for Elevators and Escalators, Emergency Operations Committee. 721 722 Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls is easy to get out of sync because of the differences in ASME A]7.1, 1984 edition,produced the requirement code cycles and the edition dates of the various codes that that only the elevator lobby and the elevator machine room jurisdictions adopt.For instance,NFPA 72"',National Fire smoke detectors were to be used to automatically recall Alarm Codeb1, has operated on a 3-year cycle (e.g., 1996, elevators. 1999,2002,2007;the exception being from 2002 to 2007), During this time, smoke detectors had no specific in- whereas ASME A17.1,Safety Code for Elevators and Es- stallation requirements other than ASME A]7.1 referenc- calators, has operated on a multiple-year code cycle with ing that smoke detectors be installed in accordance with published yearly addenda or supplements that can be NFPA 72E, Automatic Fire Detectors, Chapter 4. Smoke adopted by jurisdictions (e.g., 2000, 2002[aj. 2003[b], detection technology was still in its relatively early stages, 2004, 2005[a], 2005[S]). ASME A17.1, 2004 edition, is so the building owners continued to experience difficulties the 17th edition of the Safety Codefor Elevators and Esca- with instances of elevators returning (being recalled) as a lators; its current supplement was issued on August 12, result of unwarranted smoke detector actuation. These 2005,and is referenced as ASME Al7.11S], 2005 supple- events were responsible for a groundswell reaction from ment, which was effective as of February 12, 2006. building owners to disconnect the recall function, and it also led to installation of systems with questionable relia- Firefighters' Recall Introduced bility. Various configurations of smoke detectors were being installed using different wiring methods and even In 1973, ASME A17.1 b,Supplement to the 1971 Elevator intermixing of single station smoke alarms and system Code, introduced a new rule (Rule 211.3) that contained, smoke detectors. Coordination between electrical contrac- among other things, a requirement for "Firefighters' Re- tors and elevator contractors didn't happen on a regular call."The new rule applied to all automatic non-designated basis, and installation guidance was sorely lacking. attendant elevators that traveled 25 It above or below the designated level. Elevators having to comply with ASME NFPA's Involvement A]7.1 were now required to be "recalled" to a specific "designated" floor upon actuation of either a "3-position, NFPA's first mention of smoke detectors used for firetight- key switch" (manual recall),or by smoke detectors located ers' recall appeared in the 1987 edition of NFPA 72A, in elevator lobbies(automatic recall).The designated floor Installation,Maintenance and Use of Local Protective Sig- was usually the ground floor because that was usually the ncding Systems.The section was titled"Elevator Recall for location where first-arriving firefighters entered the build- Firefighters' Service,"and it required that smoke detectors ing to evaluate the situation.Firefighters were to be the only located in elevator lobbies and elevator machine rooms individuals to have access to the keys for the 3-position key used to initiate firefighters' service recall be connected switch. They would use this feature to capture and gain to the building fire alarm system. And, unless otherwise control over the elevator(s) for their use in fire fighting permitted by the authority having jurisdiction, only those and assisting those not capable of evacuating on their own. detectors could be used to recall the elevators. The feeling During this time period, smoke detectors were not was that as long as the elevators were not in danger from nearly as reliable and stable as they are today and the fire (as determined by elevator lobby and machine room industry was plagued with unnecessary smoke detector smoke detectors), they could continue to operate for use actuations and recalled elevators. In the 1970s, smoking of building occupants. And, of course, the other reason was not frowned upon or prohibited in buildings as is the was that there would be less risk of incuning nuisance common practice today. Ashtrays were often placed right alarms that would be disruptive to building occupants and under o in close proximity to the elevator lobby smoke bad public relations for the building owner. detectors.Passengers would take their last puff and deposit The actuated detector, in addition to initiating recall, their smoking material in the ashtray prior to boarding the was required to initiate an alarm condition on the fire alarm elevator— that last puff often led to trash in the ashtray system and annunciate the zone from which the alarm ieniting and a quick tide down to the designated level! originated. ASME Al 7.1, 1981 edition,introduced recall of eleva- Both acceptance testing and periodic testing were per- tors to an "alternate' level. This requirement called for a formed in accordance with requirements in NFPA 72E, smoke detector in the main lobby to cause recall to an 1987 edition,and NFPA 72H,Testing ProcedaresforLocal, alternate level(other than the designated floor).Also intro- Auxiliary, Remote Station, and Proprietm,p Protective Sig- duced was a new requirement for smoke detectors in the haling Systems, 1988 edition. elevator machine room to recall the elevators to the"desig- NFPA 72A, 1987 edition, also required that for each nated" floor, group of elevators within the building, two elevator zone 2007 National Fire Alarm Code Handbook Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls 723 circuits be terminated at the elevator controller.The opera- 72F, tnstollotion. ,Yloinlenunce and Use of Emergence tion had to be in accordance with ANSUASME A17.1 Voice/Alarm Communication S\-wens. 1985 edition), into Rules 211.3-211.8. Essentially, the smoke detector in the a single publication,NFPA 72, htstallation, Maintenance, designated lobby of recall would actuate the first circuit, and Use of Protective Signaling Systems. 1990 edition. and the smoke detectors in the remaining lobbies and eleva- There were no changes made to the paragraphs relating to for machine room would actuate the second circuit. The elevators in NFPA 72A, 1987 edition. reason for the two circuits was to be able to differentiate The ASME A17.1, 1990 edition,added a requirement the signal coming from the smoke detectorat thedesignated for all elevator cars to be provided with an illuminated elevator landing from all the other smoke detectors at the visual and audible signal system(firefighter's helmet sym- other elevator lobbies and elevator machine room. If that bol).The light would illuminate during recall to alert pas- detectorat the designated level actuated,it would be indica- sengers that the car is returning nonstop to the designated tive of fire conditions in that area, so the elevators would level.in reality,unless passengers were taught orotherwise then be recalled to an "alternate" level. The "alternate" shown what the light meant, it was doubtful as to the level would be determined at the discretion or the authority value this feature provided the average elevator passenger. having jurisdiction (usually the local fire department). Exhibit 52.1 shows an illustration of the frefighter's he]- Smoke detectors for elevator recall were also required met symbol. Later, this visual symbol will be discussed in to initiate an alarm even with all other initiating devices another application. on the circuit in an alarm state.The reason for this require- ment was to ensure the reliability of the recall operation because some fire alarm initiating device circuits could not support having all devices in alarm at one time and zs man z5 mm still guarantee the smoke detector used for elevator recall (1 in.) LLI (t in.) min. min. would operate. IV �J Two examples(drawings)were placed in the appendix of NFPA 72A recommending wiring configuration for the 25 mm(1 in.)min. smoke detector for a new installation as well as for an elevator retrofit situation. The standards at this time did General note:Grid is for scaling purposes only. not require electrical supervision of these control circuits. Fig.2.27.3.1.6(h)VISUAL SIGNAL In 1989,ASME A 17.1 b addressed smoke detectors in hoistways. Smoke detectors were allowed to be installed EXHIBIT 52.1 Firefighter's Helmet Symbol. (Reprinted in any hoistway, but they were required to be installed from ASMEA17.la,2005,by permission of the American in hcistw:rys that were sprinklered. The hoistway smoke Society of Mechanical Engineers. All rights reserved.) detectors,when actuated,were to cause recall to the desia The 25 ft travel criterion was dropped from ASME rated level. Also, the elevators must react only to the first A17.1b, 1992 supplement,so the Firefighters' Service Re- recall signal. In other words, if the detector at the desig- call then applied to all automatic non-designated attendant nated level actuated and then shortly after the third Floor elevators regardless of the travel distance. elevator lobby detector actuated,the car would be recalled to the alternate Floor of recall and not the designated level ASME At7.1 [19931 (14th Edition) because the detector at the designated level was the first to actuate. This requirement was added because it was In 1993 liaisons between the NFPA 72 Technical Commit- believed that the first detector to operate would have a tee on Prulecied Premises Fire Alarm Systems and the high probability of sensing a fire in its vicinity, whereas ASME A 17.1 Emergency Operations Committee were es- there would be a fairchance of the smoke migrating to other tablished and were effectively communicating to coordi- locations and tripping the detectors and giving conflicting nate their code activities. Requirements were more instructions to the elevator controller. complex,and it was essential this communication and co- In 1990, NFPA consolidated some of the signaling operation continue. More specific application details were standards(NFPA 72A,Installation, Maintenance, and Use surfacing, such as the requirement that smoke detectors in of Local Protective Signaling Snvems, 1987 edition;NFPA the hoistway might be installed below the lowest recall 72p.Alcliliury Protective Signaling Systentsfor Fire Alarm level and when actuated,those detectors would now cause Service, 1986 edition; NFPA 72C, Rentote Station Protec- the elevator car to be sent to the upper level of recall. rive Signaling Systems, 1986 edition;NFPA 72D, Praprie- Reasoning for that change was to keep the car away from tan•Protective Signmling Systems, 1986 edition;and NFPA the fire. National Fire Alarm Code Handbook 2007 724 Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls NFPA 72 Changes [1993] when actuated. will send the car to the alternate level. In 1993 NFPA further consolidated the signaling standards Again. the reasoning was to use the recall level furthest to form what is now NFPA 72, National Fire Alornt Corte. from the fire condition. Reference to hoistway smoke detectors was added in this NFPA 72 Changes [1996] edition to correlate with ASME A17.1, 1990 edition. The result required hoistway detectors to cause recall of eleva- In the 1996 edition of NFPA 72, smoke detectors in tors to the designated level. hoistways were prohibited unless the top of the hoistway The 1993 edition of NFPA 72 also, for the first time, had a sprinkler. If the top of the hoistway was sprinklered. addressed elevatorrecatlinbuildingsthat were not required then ASME A17.1b, 1995 supplement, required a smoke to have a fire alarm system.Those buildings having eleva- detector to be installed to initiate recall prior to having the tors and no building fire alarm systems and having to main line power shut down. comply with ANSI/ASME A17.1 must now have an "Ele- The reason for not wanting smoke detectors in vator Recall and Supervisory Panel." This panel is essen- hoistways is obvious. The adverse environmental condi- tially a fire alarm control unit(now defined as a"dedicated Lions of most elevator hoistways, with dirt and contami- function fire alarm control unit")specifically used to pro- rants and varying air velocities caused by elevator piston vide signals to the elevator controller to initiate elevator action, initiated many unwarranted or "nuisance" recalls. recall, but not notify the occupants of the building or the Because smoke detectors in hoistways were(and still are) fire department. Additionally, this control unit was used difficult to service and to perform periodic testing on, to initiate removal of elevator main line power prior to smoke detectors were often sadly neglected,allowing them sprinkler operation should the building have sprinklers in to become dirty, overly sensitive, and prone to causing the elevator machine room or hoistway. The main reason nuisance recalls. for this requirement was to ensure these critical elevator Another section added to the 1996 edition of NFPA recall systems were installed with the reliability of building 72 allowed other appropriate automatic fire detection to fire alarm systems,which included the supervision (moni- be used in place of smoke detectors in those situations toring for the integrity) of circuit wiring and secondary where the environment was unsuitable forsmoke detectors, power meeting the requirements of NFPA 72. such as unheated elevator lobbies commonly found in Also in the 1993 edition, the temt fire safer- control northern climates. functions was introduced.The section on fire safety control A "third" control circuit was added to the existing functions addressed those components and interfaces that "designated" Floor of recall and "alternate" Floor of recall are meant to increase the level of life safety and property circuits. This third circuit was to operate when a hoistway protection in buildings. The following are examples of or machine room smoke detector actuated. It was to annun- such fire safety control functions: door holding, door re- ciate separately at the fire alarm control unit and other leasing, door unlocking, elevator recall, shunt trip, fan required annunciators.The purpose was to alert firefighters control, smoke hatches, and stairway ventilation.The sec- and other emergency personnel of it potential problem that tion on fire safety control functions reinforced the require- might cause unsafe elevator operation and, indeed, they ment that the circuits from the fire alarm system to the may soon lose elevator power. elevator controller(s) had to be monitored for integrity. At this time there was confusion in the industry be- A section on shutdown of main elevator power was cause ASME A 17.1 had not yet introduced the third circuit also added in the 1993 edition of NFPA 72 primarily as a as an elevator requirement. in the works was a proposal result of the ASME 17.1 requirements that now addressed to ASME A17.1 that would cause the Firefighter's helmet the concerns of sprinklers in elevator machine rooms and symbol in the elevator car to flash to indicate impending hoistways. These sprinkler requirements were driven by danger if firefighters were to continue to use the car under national building codes.This subject is discussed in greater "Phase 11—Emergency In-car Operation." Under"Phase detail later under the topic "Main Line Power Disconnect II,"" the elevator is controlled by firefighters by way of a — Shunt Trip." special key that permits firefighters to override other safety controls. The firefighters can then use the elevator for ASME A17.1b [19951 staging their equipment and for evacuating people. ASME A17.Ib, 1995 supplement,included a new require- ASME A17.1a [1997] ment addressing the condition (as with many hydraulic elevators)where the elevator machine room is on the desig- Some fairly substantial changes were made in terminology nated level.Smoke detectors in the elevator machine room, in the 1997 supplement of ASME A 17.1.The title of sec- 2007 National Fire Alarm Code Handbook Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls 725 tion "2113b Smoke Detectors" was changed to "211.3b mechanisms, etc.) were customarily installed in spaces Phase 1 Fire Alarm Activation." Also, the term fire alarm called machine rooms. Recent elevator technology has led initiating devices replaced the previously used term smoke to what is now referred to as"machine room-less"elevator detectors. This change was intended to recognize that systems.Some elevators today have the equipment in other smoke detectors may not be the most appropriate choice spaces,such as mounted on the elevator car itself.So,now, of detection to initiate elevator recall when environmental when referring to locations where smoke detectors are conditions exceed those for which the smoke detector is installed for the purpose of initiating recall (elevator lob- suitable, hies, elevator hoistways, and elevator machine rooms), additional reference is made to elevator machine rooms ASME A17.1b [19981 "including machine space, control room, and control space." A new paragraph was added to the 1998 supplement of Where NFPA 72, 1999 edition, addressed three sepa- ASME A17.1 requiring that the actuation of a fire alarm rate circuits per each group of elevators within a building initiating device in the elevator machine room or in the for the purpose of interfacing the fire alarm system with hoistway cause the visual signal (firefighter's helmet) in the elevator system,NFPA 72,2002 edition, addressed the the affected elevator car to flash. This addition provided the change needed for correlation with the "third circuit" potential of having more than three circuits. Wording was requirement added in the 1996 edition of NFPA 72. changed from "three separate elevator control circuits" to "a minimum of three separate elevator control circuits." NFPA 72 Changes [1999] The reason for that change was that in some instances,two (or more)separate hoistways could share the same common There were no substantive changes related to elevator recall elevator machine room. An ASME A17.1 requirement is in the 1999 edition of NFPA 72. See changes to power to provide a danger signal to elevator cars(by flashing the disconnect requirements later in the section on "Elevator firefighter helmet symbol) if there is fire in an elevator Shutdown and Sprinklers." hoistway or an elevator machine room. The reasoning be- hind the change was that if the fire was in one hoistway, ASME Al7.1 [2000] (16th Edition) the signal should not be given to the elevator car in the The 2000 edition of ASME A17.1 was harmonized with other hoistway where there may be no immediate danger. the Canadian CAN/CSA B44 Elevator Safety Standard. In Of course, if the fire occurred in the common machine addition, the entire code was reformatted and renumbered room,the signal would be sent to the cars in both hoistways. Annex material was added to advise against installing using a decimal numbering system. smoke detectors in outdoor locations or locations that are Some heading changes were made,for instance, "Fire- exposed to weather, such as unenclosed elevator lobbies fighters' Service—Automatic Elevators" was changed to "Firefighters' Emergency Operation — Automatic Eleva- in open parking structures, because those g and further tors."And, "Phase i Fire Alarm Activation" was changed can exceed the parameters of detector listing and further could result i unwanted alarms and unnecessary recall of to "Phase I Emergency Recall Operation by Fire Alarm elevators. If Initiating Devices." But,the content did not change essen- tially. Some rewording and paragraph modifications were subsequent lisss smoke as acceptable for the anticipated environ- made to accommodate the differences that still exist be- [pent,then,of course,that device would be appropriate for tween the United States and Canada. Where differences installation in that case. exist between ASME A17.1 and CAN/CSA B44, there ASME Al7.1a [2002] Supplement is wording such as "In jurisdictions not erfowing the NBCC . . .". The NBCC refers to the National Building There were no changes in requirements to the emergency Code of Canada, so used in that context, that particular recall operation in this first addendum to the 2000 edition code requirement would apply to the United States. of ASME A17.1. NFPA 72 Changes [20021 ASME A17.1b [20031 Supplement Several correlation changes occurred in the 2002 edition There were no substantive changes in requirements for of NFPA 72. Wording was added to include consideration emergency recall, but wording was modified to reaffirm for new elevator technology that alters the way we have the intent of where fire alarm initiating devices used for traditionally thought of elevators.Various elevator compo- the purpose of initiating emergency recall were to be in- nents and equipment (drive motors, controllers, braking stalled. The fire alarm initiating devices were required to National Fire Alarm Code Handbook 2007 726 Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls be installed in conformance with NFPA 72 and located as edition. The reference to "shunt trip" is used because it follows: (1)at each floor served by the elevator; (2)in the is that method that is predominantly used to disconnect associated elevator machine room; and(3) in the elevator the elevator main line power. hoistway, when sprinklers are located in those hoistways. When the term main line power is used here, it does not mean "complete"or"total"power.It means the power ASME All7.1 [20041 17th Edition that drives the elevator itself. Those circuits that would No new requirements were introduced to the existing emer- not be shut down would include the following: gency recall requirements. • Branch circuits for car lighting,receptacle(s), ventila- tion, heating, and air conditioning ASME A17.1a [2005] Supplement • Branch circuit for machine room/machinery space No new requirements were introduced to the existing emer- lighting and receptacle(s) gency recall requirements. • Branch circuit for hoistway pit lighting and recepta- cle(s) ASME A17AS [2005] "Special" Supplement Because of the potential danger from water shorting This release is a "special" supplement that was published and bridging electrical components and because it is tun- as a result of an ad hoc committee tasked with addressing sidered hazardous to have water on the elevator brake the issues associated with the advancement of new techno- (braking system)of traction elevators,especially when the logies being used in today's design and construction of car is in motion,the requirement to disconnect the elevator elevator equipment. The committee looked at the various main line power prior to the release of water from the safety aspects of the new equipment and its installation, sprinkler system was included in ASME 17.1, 1984edition. and recommendations were put forth in proposals that ad- The concept was to remove main line power from the dressed equipment located in traditional hoistways and elevator to stop the car and prevent it from moving prior machine rooms as well as what is now termed "machinery to a sprinkler releasing water that could get onto elevator spaces, control spaces" that may be found either inside or electrical components or the elevator brake. There was a outside the hoistway. concern that "shorting"of control and safety circuits could No new requirements were introduced to the existing result in dangerous situations such as uncontrollable mo- emergency recall requirements. tion and running of the elevator with doors open, and so on. On traction elevators there is the additional concern of NFPA 72 Changes [2007] getting water on the brake while the car is moving, which could result in uncontrolled braking and failure to stop A significant rewrite of some of the paragraphs of the safely. Elevator Recall for Firefighters' Service section was made The original theory for elevator shutdown was to use with the intent of improving clarity,readability, and conti- a heal detector as the means to actuate shunt nip. The nuity. following sequence was intended: The section is now arranged with general requirements leading in to three distinct sections specific to the output 1. A smoke detector used for elevator recall would sense sienals from the fire alarm system to the elevator control smoke and initiate recall. system, namely. Designated Level Recall, Alternate Level 2, The elevators would be recalled immediately (with or Recall, and Visual Warning. without passengers)to the floor of recall and doors open. 3. Heat buildup causes heat detector to actuate, which ELEVATOR SHUTDOWN AND SPRINKLERS initiates main line power shutdown. 4. Power is removed from elevator and the car cannot be Since its inception, the requirement in ASME A17.1 for used until power is manually restored. shutdown of elevator main line power has been the cause 5. Further heat buildup causes sprinkler to fuse, releasing for confusion in the industry and also has been very contro- water to control fire. versial,The following paragraphs try to provide some back- In ASME A l T l a, 1994 supplement, the wording ground and insight on the subject, changed to "upon or prior to the application of water Main Line Power Disconnect— "Shunt Trip" from sprinklers." Effectively, the rewording now allowed sprinkler waterflow switches to initiate main line power Main line power disconnect, commonly referred to as disconnect in addition to the previously used heat detectors. "shunt trip," was first required by ASME A17.1, 1984 Built-in delays were not allowed in the waterflow switch 2007 National Fire Alarm Code Handbook Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls 727 (such as the retard mechanism furnished with many flow mechanism, which is exactly the condition that is trying switches that could be set to provide as much as a 90 second to be avoided. delay in initiating a signal). The reason Flow switches are Heat detectors also had to be installed within 2 It of provided with built-in delays is to prevent false tripping each sprinkler head in the elevator machine room and from "water hammer" caused by changes in pressure in hoistway. This spacing was to ensure the heat detector the water supply. At this time, the heat detector appeared sampled, as nearly as practicable, the temperature that the to be the most widely used as well as preferred option sprinkler was sensing. because waterflow switches (without retard mechanisms) The second area for confusion was a requirement in were prone to causing unwanted and unwarranted recall NFPA 72A, 1987 edition, hisialladun, Maintenance and of elevators. Today, the use of more reliable check valves Use of Local Protective Signaling Sisions, under the sec- has minimized this problem. tion for "Installation and Design" that stated "The performance of automatic control functions shall not inter- fere with power for lighting or for operating elevators." System This requirement remains in NFPA 72, 2007 edition, as paragraph 6.16.2.1. Elevator main line power shutdown is Confusion existed for years over a couple of code sections. a fire safety control function,and the operation is intention- one on a sentence in earlier editions of the National Electri- ally designed as such. This operation does not interfere cal Cnde°, Article 620(Elevators),under the section cov- with operating power for the elevators: it instead controls ering "Disconnecting Means and Control." It stated that the power shutdown. "nor shall circuit breakers be opened automatically by a NFPA 72 Elevator Shutdown (1999) fire alarm system." Some interpreted this as a requirement that the heat detector used to actuate shunt trip could not A weak link in the reliability of "shunt trip" was recog- be associated with or connected to the fire alarm system. nized and addressed by NFPA 72. 1999 edition. It was In fact, what was intended was that the elevator power often found during periodic testing ol'the shunt trip feature should not be shirt down when the fire alarm system was that the power needed to trip the shunt trip breaker was activated by just tiny fire alarm initiating device in the not available. This lack of power was usually because a building. Many were not aware of the programming capa- circuit breaker that supplies the needed power was in the bilities that fire alarm systems have that allow for maMxing off position. The requirement for supervising that power of various inputs and outputs. So, for years, a separate was established in NFPA 72, 1999 edition. Absence of the circuit, not connected to the fire alarm system, was com- power required a supervisory signal to be indicated at monly used to accomplish elevator main line powerdiscon- the fire alarm control unit and required annunciators. An nett.Unfortunately,much of the time the circuit conductors example of a typical method of providing the elevator were not monitored for integrity (supervised). This over- power shunt trip supervisory signal was included in the sight meant that a broken wire or open circuit could go Appendix. undetected until testing revealed the problem and also NFPA 72 Elevator Shutdown (2002) meant the circuit could be out of commission when needed in an emergency. These instances emphasize the need for In NFPA 72, 2002 edition, it was made clear that the critical circuits to be monitored for integrity. as is the case initiating devices (heat detectors and flow switches) used with fire alann initiating device circuits. to initiate main line power disconnect (shunt trip) are re- In the 1993 edition of NFPA 70, National Electrical quired to be monitored for integrity by the fire alarm control Code, the troublesome reference to the fire alarm system unit.As mentioned previously,if the initiating devices were was removed to avoid the confusion. The requirements not connected to the fire alarm system, a broken wire, for regarding the means to achieve elevator shutdown were instance, could disable the circuit and go unnoticed until also more clearly defined in NFPA 72 119931. If heat detec- found during periodic testing. This requirement increases tors were used to shut down elevator power prior to sprin- the operational reliability of the circuit and helps to ensure kler operation, the heat detector was required to have a the shunt trip feature will operate properly when called on lower temperature rating and higher sensitivity when com- in an emergency. pared to the sprinkler. Obviously, in order to accomplish ASME A17.1a [2005] Supplement the desired sequence,the heat detector must actuate earlier than the sprinkler under the fire condition. If the sequence In this supplement,wording was added to require that heat somehow occun ed in reverse order,water could be released detectors and sprinkler Flow switches used to initiate power on live electrical components as well as on the braking removal comply with the requirements of NFPA 72. National Fire Alarm Code Handbook 2007 728 Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls ASME Al7.1S [20051 "Special" Supplement fluids. NFPA 13 does not require sprinklers at the bottom This special supplement included significant rewrites of of the hoistway (discussed further below). If no sprinklers certain chapters. Unfortunately,when a large modification are installed anywhere in the hoistway(including the eleva- is made to it code, there is the potential for something for pit) then there is no requirement for initiating devices ..slipping through the cracks" or the undoing of some to be installed anywhere in the hoistway for either recall previously coordinated efforts. The following issue may or shutdown. It is important to recognize that this applies because for some confusion until it is addressed in a future to passenger elevators only and not to freight elevators. edition. So, for freight elevators, the sprinkler at the top of the Previous editions of ASME A 17.1 exempt the power hoistway is still required and, therefore, so is the smoke removal requirements for sprinklers in the pit if the installa- detector (or other automatic initiating device), as well as the heat detector used for power disconnect. tion complies with the NFPA 13 requirement for installa- tion of sprinklers at or less than 24 in. from the bottom of NFPA 13 requires each el spray sprinklers to be re the pit. The new wording is in more of a performance stalled 61 the bottom of each elevator hoistway not more language and makes the decision very subjective. A com- than 0.61 nt xe p above the floor of the pit. However, there is an exemption for the sprinkler requirement for parison of the wording follows: enclosed, noncombustible elevator shafts that do not con- Wording prior to A/7.IS /20051 tain combustible hydraulic fluids.Realistically,this exemp- , means shall be provided to automatically dis- connect the main line power supply to the affected elevator bon is rarely observed and more than likely,sprinklers will be installed in elevator pits. In addition,the ASME A 17.1 upon or prior to the application of water from sprinklers located in the machine room or in the hoistway more than [199 and 2004 codes and supplements ASME A main 24 inches above the pi[ Floor." 1997] through ASME A17.1a [20051 indicate that main Wording of A]7.IS/2005/ line power disconnect is not required if those sprinklers . . . .where elevator equipment is located or its enclo- are installed no more than 0.61 m (2 ft) from the floor of sure isconfigured such that application of water from the pit. However, this prescriptive exemption has been sprinklers could cause unsafe elevator operation, means replaced in ASME A 17.1 S[20051 Special Supplement with shall be provided to automatically disconnect the main line subjective language and not the clear exemption that earlier power supply to the affected elevator upon or prior to the editions provided. (Refer to previous section ASME de- application of water." Note: there is no longer mention of ta 17.I S [is the05] -Special- Supplement for additional hat sprinklers installed 24 inches or less from the bottom of tails.) It is therefore extremely1sinf important to know what the pit. edition of ASME A17.1 is in farce. In any event, current requirements for elevator recall Sprinklers and Fire Alarm Initiating Devices in initiated from the pit allow initiation front either a sprinkler Hoistways waterflow device or from an automatic fire detection ini- tiating device (usually a heat detector). A review of the requirements of ASME A17.1, Safety Maintaining a high degree of reliability for the fire Codefor Elevalors and Escalators;NFPA 72,Notional Fire alarm system is fundamental to the purpose of the National Alm to Code;and NFPA 13.Standard for the/nsvallation of Fire Alann Code. For that reason, paragraph 6.16.3.7 of Sprinkler.Systems, considered collectively, would suggest the 2007 edition permits the use of other automatic fire that there may be no need to install fire alarm initiating detection devices where ambient conditions prevent the devices for the purpose of initiating main line power dis- reliable use of smoke detectors. Elevator hoistways are connect (shunt trip) in hoistways of passenger elevators. often locations where ambient conditions exceed those for If the hoistway of a passenger elevator is noncombustible which the smoke detectors have been tested and listed. and the car enclosure materials meet the requirements of When automatic fire detection devices are needed within ASME A17.1 (which should be the case with all new a hoistway, the selection of the devices must consider elevator installations), then NFPA 13 does not require system reliability as well as the performance needed to sprinklers at the top of the hoistway.Thus,with respect to provide the intended system operation. requirements for the top of the hoistway, if the sprinkler In summary,when sprinklers are installed in an eleva- is not needed, then the corresponding requirement for the for hoistway(either at the top or bottom),appropriate auto- smoke detector that would be used for recall goes away as matic fire detection devices are required to provide elevator well as the corresponding requirement for the heat detector recall. (See 6.16.3.12.1 and 6.13.3.12.2 of the Code.) If used for power disconnect. Further, if the noncombustible any of these installed sprinklers are located more than 0.61 elevator hoistway does not contain combustible hydraulic m (2 ft) from the floor of the pit (ASME A17.1a [20051 2007 National Fire Alarm Code Handbook Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls 729 and earlier), or where elevator equipment is located or its tion to building occupants/emergency responders; and the enclosure is configured such that application of water from use of compartmented and pressurized lobbies/vestibules. sprinklers (in any location) could cause unsafe elevator Consistent themes relative to the needed process in- operation (ASME A17.IS [20051), appropriate automatic eluded utilizing a risk/hazard analysis, involving firefight- fire detection devices are required to provide power shut- ers in the decision making, and involving the appropriate down. Requirements for elevator shutdown are addressed committees (A17.1, B44, model building and fire codes, separately from those for elevator recall,and ASME A 17.1 and NFPA Codes and standards). prohibits the use of smoke detectors for the purpose of The two active task groups resulting from the work- power shutdown. It is worthwhile to note that main line shop efforts (Task Group on the Use of Elevators by Fire- elevator power shutdown is always required when sprin- fighters and Task Group on the Use of Elevators for klers are installed in the elevator machine room. Occupant Egress) are performing comprehensive risk/ hazard analyses of various emergency scenarios plus the Workshop on Emergency Use of Elevators residual hazards and the mitigation of the hazards. The task groups have estimated completion sometime late 2007 In March 2004, a workshop co-sponsored by ASME, to early 2008.The groups will then put forth their conclu- NFPA, NIST, ICC, IAFF, US Access Board, and others sions and outline their recommendations.The task groups, was held in Atlanta. Georgia, to consider the challenges made up of various industry components (research, fire of evacuation of high-rise buildings in fire and other emer- service, architect and engineering, codes and standards genies. It was a three-day conference with over 120 life makers, disability interests, and other industry members), safety professionals attending from various communities have embarked on a journey that will command a Hercu- concemed with high-rise safety and egress. There were lean effort. two distinct focus points, one on the use of elevators by These efforts will most certainly culminate in a signiti- firefighters and one on the use of elevators for occupants cant impact on the interface and interaction between sprin- during emergencies. The participants were split up into kler, tire alarm, and elevator systems. breakout groups to develop recommendations as to how elevators in high-rise buildings could be put to better use during emergencies. The goal was to develop proposals CONCLUSION that could be submitted to various code-writing organiza- tions for consideration. A steering committee made up a historical perspective has been given hereto help provide better understanding of both the actual code evolution and of all the sponsoring organizations reviewed the breakout a groups' recommendations and formulated plans for the some of the thought processes that went into the interface requirements for elevator and fire alarm systems. During next steps to be taken and also to identify the appropriate the past decade it became very evident that the issues faced standards-making bodies to which to direct the proposals in addressing these challenges were ones that were not Some of the consistently repeating themes were as follows: "black or white." There were, and continue to be, many • The culture change since 9-11 and the reluctance of varying shades of gray. One thing, though, is very clean. occupants to stay in place and await further instruc- There is now a spirit of willingness and cooperation be- tions tween industry, code enforcement, and the fire service to • Elevators not meant to be a substitute for stairs continue to work together to find the best solutions to • Evacuation of people with mobility impairments achieve the highest level of safety and reliability for the • Water entering hoistways passengers and emergency personnel who use elevators. • Lack of firefighter confidence in using elevators With more focus on improving building evacuation time • Entrapment caused by activation of shunt trip by rethinking and improving the egress process, with per- • Re-educating people to use elevators for egress after fonnance-based design approaches,and with new technol- years of "don't use the elevators — use the stairs" ogies providing more options, that cooperation will need instructions to continue as we face even more difficult and challenging decisions ahead. There were also repeating recommendations from the breakout groups such as mandatory adoption of ASME REFERENCES A173 everywhere; ensuring the reliability of Phase I and Phase 11 operation;better training of firefighters on elevator ANSI A17.1 A, Safely Code for Elevators, 8th edition, operation; enforcing the building emergency plan; sprin- American National Standards Institute,New York,NY, klering all buildings:the need for"real-tine"communica- 1971, National Fire Alarm Code Handbook 2007 730 Supplement 2 • Interfacing Fire Alarm Systems and Elevator Controls ANSI A17.lb, 1973 supplement to ANSi A17.1 A,Safety Snfeh,CodeforElevntorsand Escalators, 17thedition. Cade for Elevators, 8th edition. American National ASME International, New York. NY; 2004. Standards Institute, New York, NY 1971. CAN/CSA-B44, Safety Code.for Elevators,Canadian ANSUASME A 17.1,Safety Code for Elevators and Esca- Standards Association, Rexdale (Toronto), ON. Can- lalors, IOtb edition, ASME International. New York, ada. NY. 1981. NFPA 13, Standanl for the Installation QfSprinkler S1'.s- ANSUASME 17.1, Safety Codefor Elevators and Escala- terns, 2007 edition, National Fire Protection As-socia- tors, I Ith edition, ASME International. New York, tion, Quincy, MA. NY, 1984. NFPA 70, National Electrical Code", 2005 edition, Na- ANSi/ASME A17.1b, 1989 supplement to ANSi AITI, tional Fire Protection Association, Quincy. MA. Safety Codefor Elevators and Escalators, 12thedition, NFPA 72, National Fire Alann Code, 2007 edition, Na- ASME International, New York, NY, 1987. tional Fire Protection Association, Quincy, MA. ASME A 17.I, Safety Cade for Elevators and Escalators, NFPA 72". National Fire Alarm Code`"', 2002 edition,Na- 13th edition, ASME International, New York, NY, tional Fire Protection Association, Quincy, MA. 1990. NFPA 72a1,National Fire Alarm Code'"^. 1999 edition,Na- ASME A17.1b, 1992 supplement to ANSI A17.1, Safety tional Fire Protection Association. Quincy, MA. Code for Elevators and Escalators, 13th edition, NFPA 72"x,National Fire Alann Cudr 1996 edition, Na- ASME International, New York, NY, 1990. tional Fire Protection Association. Quincy, MA. ASME A 17.1a. 1994 supplement to ANSI A 17.1, Safety NFPA 72r,.National Fire Alarm Code,". 1993 edition,Na- Carle for Elevators and Escalators, 14th edition, tional Fire Protection Association, Quincy, MA. ASME International, New York, NY, 1993. NFPA 72, /nstallation,Maintenance,and Use of Protective ASME A17.1b. 1995 supplement to ANSI A17.1, Safety Signaling Sxslems, 1990 edition,National Fire Protec- Code J'or Elevators and Escalators, 14th edition, tion Association. Quincy, MA. ASME International, New York, NY, 1993. NFPA 72A, Installation, Maintenance and Use of Local ASME A17.1a. 1997 supplement to ANSI A17.1, Safety Protective Signaling Systems, 1987 edition, National Code for Elevators and Escalators, 15tb edition. Fire Protection Association, Quincy, MA. ASME International, New York, NY, 1996. NFPA 7213.Auxiliary Protecth e.S'ignaling Systentsfor Fire ASME A17.1b, 1998 supplement to ANSi A17.1, Safety Alann.Servic•e. 1986 edition, National Fire Protection Coyle for Elevators and Escalators, 15tb edition, Association, Quincy, MA. ASME International, New York, NY, 1996. NFPA 72C, Remole Station Protective Signaling Svslenns, ASME A17.1, Safety Code far Elevators and Escalators, 1986 edition, National Fire Protection Association. 16th edition, ASME International, New York, NY, Quincy, MA. 2000. NFPA 72D, Proprietary Protective Signaling Systerns, ASME A17.1a, 2002 supplement to ANSI AITI, Safety 1986 edition, National Fire Protection Association, Code Jor Elevators and Escalators, 16th edition, Quincy. MA. ASME International, New York, NY, 2000. NFPA 72E, Automatic Fire Detectors, 1987 edition, Na- ASME A17.1b, 2003 supplement to ANSI AITi, Safety tional Fire Protection Association, Quincy. MA. Code for Elevators and Escalators, 16th edition, NFPA 72F, Installation Maintenance and Use of Emer- ASME International, New York, NY, 2000. gency Voice/Alarnr Communication Systems, 1985 edi- ASME A17.1, Safety Cade for Elevators and Escalators, tion, National Fire Protection Associaton, Quincy, 17th edition, ASME International, New York, NY, MA. 2004. NFPA 72H, Testing Procedures for Local, Auxiliaryt Re- ASME A17.1a. 2005 supplement to ANSi AITI, Solely mole Station, and Proprietary Protective Signaling Code jbr Elevators and Escalators, 17th edition, Svsiernns, 1988 edition, National Fire Protection Asso- ASME International, New York. NY, 2004. ciation. Quincy. MA. ASME A17.IS. 2005 special supplement to ANSI A17.1, 2007 National Fire Alarm Code Handbook P [W waterworks August 7, 2020 Mrs.Andrea Brinkley Assistant Director Baytown Area Water Authority The City of Baytown 2401 Market St. Baytown, TX 77520 Re: CPR No. #077 BAWA 6 MGD Surface Water Treatment Plant BAWA Job No. 1806021 Mrs. Brinkley, Please see attached proposal for the secondary containment areas in the Operations Building per RFP#015. This change will result in a increase in the amount of$5,905.44. Please feel free to contact me at(713)301-8637 with any questions or concerns. Regards, PLW Waterworks �4 l l Katy Drown Project Manager Page 1 Baytown Area Water Authority CPR No.: N077 BAWA 6 NIGD Surface Water Treatment Plant Date: 08/07/20 BAWA Job No.1806021 PLM'Job No.: P3T Chemical Containment Scene of SS'ork Secondary Chemical Containment Non-Taxed Labor Material Subcontract Taxed Mat'l/E ui Item Unit Total Unit Total Unit Total Unit Total No. Description Qty Unit Cost Cast Cast Cum Cost Cost Cost Cost I Sodium Cblorite Temporary Chemical Containment 1.1 Ulnatech IBC Containment Unit 2 EA S - S - S 250.00 S 500.00 S - S - S 1,258.00 S 2.516,00 1.2 Forklift w/Operator 8 [IRS 5 50.00 $ 40000 S $ - S - S - S 650.00 $ 650,00 1.3 Installation of cisemical cotnaioont 16 NRS S 38A0 $ 608.00 S S - $ - $ - S - S - Direct Cost Subtotal 1008.on 50000 - 3.166.00 Small Tools C,5.04b 50.40 Na - Na Na Equipmem Barden 0 50.055 Na Na Na Nx Tax 6d&25% nb Na n/a 26120 Su1aata12 105840 50000 - 3,427.20 Ovmhead&Profis a I 0% 158 76 7500 514.08 Subtota13 1217 16 57500 - 3 T11.27 Bonds&Insurance a 3.09e 36 51 1725 118.24 Su1,1mo14 1,25.3 67 592.25 4.T59.51 'I otal of all colnnsos 5.90544 Other Grand Total Cost 5,905.44 Page 2 0 1 JONES CARTER RFP NO.: 015 REQUEST FOR PROPOSAL (RFP) 1. PROJECT NAME: 6 MGD Surface Water Treatment Plant 2. AC PROJECT NO.: 09986-0002-00 3. CONTRACTOR: Pepper Lawson Waterworks 4. SUBMITTED TO: Katy Drown 5. SUBJECT: Sodium Chlorite Temporary Chemical Containment 6. REFERENCE:Attached Markups 7. REF. DWG.NO.: N/A 8. REF.SPEC. NO.: 9. DESCRIPTION OF WORK: The Contractor is requested to furnish a price proposal for the below described work. Please complete,sign,date,and return a proposal at yourearliest convenience. Please attach a detailed cost breakdown toyourproposal. 1. Contractor shall purchase and install two(2)ULTRATECH IBC Containment Unit, Uncovered, 365 gal.Spill Capacity,8500 lb from Grainger to contain the Sodium Chlorite totes and scales in the Chlorine Dioxide Generator Chemical Containment area.See attached documentation. 2. Contractor shall install additional 3/4"flexible hose as required to make the connection to the Sodium Chlorite totes. 11. Requestor's Name&Signature: Larry Weppler Date: 8/7/20 The Contractor acknowledges that this RFP is to be used to request pricing information only,and does NOT constitute a contract modification. The Contractor Is NOT AUTHORIZED/DIRECTED to perform this work UNTIL/PRIOR TO written notification that a contract modification is approved. I:wp\flocs\most\forms\rfi or rfp\rfpform.doc REV 9/I4/00 Product Categones i Safety/Spill Control Supplies/IBC and Tank Spill Containment/(Be CoreWirenenl lint,Uncovered.365 gal Spill vPrint� Emal IBC Containment Unit, Uncovered, 365 gal. Spill Capacity, 8500 lb. ten,"4LNV6 '.'r Moe. li57 .1alcg Page Y 1667 UNSF 2LGI105 Rae„a in Web Price 0 I O Confirm ZIP Code to determine 1 Add to Cart availability. $1,258.00/each IAdd to List ' 33101 Save f Thiadem,eyunea avPcial shipping addruonal chmyes may a reply Jump[o: Replacement Parts Shipping Weight 238.01bs. ) Coumryaf Cr9n USA ICountry o/Oig D/<rrochag J Nacre.Feduvruvailablry'revHimeupRalMacdn,ljus(M embnuousg:IDeV oduef wit/6e reserrN/oryou when youa'eneplere yom H." once,.Mwe Product Details IBC spill containment unit.Features polyethylene construction for chemical resistance.Will not rust or corrode.Large 52"x 526 deck with removable grates View More w Technical Specs Rein IBC Spill Containment Unit L-eP 62' IRC CemnnvnenI Produc, IBC containment Van v6dlh 62' Type C„v A/J,cdvered Uncovered Np - -Spit L r -- - — — Standards EPA 40 CFR 264.175.SPCC Cnpenl Loud SSOO b. ,ary Mmenal PalYethYlene Spill Cauchy 365ga1 Spill Cantane"in Upemng No Cover Tvpe '1 He,can we mpmeow T-hn¢al Cpecilica1.... Compliance and Restrictions None Documentation Ultratech Chemical Compatibility Guide Ultratech IBC Spill Containment Comparison Guide Ultratech IBC Spill Pallet Plus PDS Replacement Parts Need help finding replacement parts?Please use the list below or call 1-800-GRAINGER(1-800472-4643) 2 available replacement parts for model:1157 Part Description MG.Part# Itere4 Price. 0 Ship p 33101v any Pick Up of ,. 9573 40KE24 Web Price Expected to arrive Wed.Aug 12. ❑ Replacement Grate,Fits... $145.50/each ur 1156 40KEb4 Web Price Ships from supplier Expected to arrive on or Sump Fits Brand UltraT... $1,240A0/each before Tue.Aug 18. +Add to List Add to Cart Alternate Search Terms Secondary Spill Containment(862) Cpnleinmem Basns(658) IBC(Interrecalile Bulk Conlamer)5pe1 Cpniml(9,) IBCllnterm&dnueBUlp.Coala,ner,Spill Cnntml U Ia,(,a) rank Lpnlainment Wt115(98) Related Products AW Item#4LNV8 Bucket Shelf,Polyethylene, For Use With Ultra-IBC Spill Pallets)Plus,19-1/2' Length,16'Width ULTRATECH 111eb Price p $140.50/each Customers Also Purchased 111NVEM& low a� ULTRATECH EAGLE ULTRATECH PIG ULTRATECH Uncovered,605 gal.Spill Spill Containment Bucket Shelf,Polyethylene, Spill Hit/Station,Cart, Spill Tray,Polyethylene,30> Capacity Platforms,Uncovered, For Use With Ultra-IBC Spill Chemical,Hai 14 gal, gal.Spill Capacity,30" 60-1/2 gal.Spill Capacity, Pallet E Plus,19-1/2" Length,4814-3/4" 10,00011 Length,16"Width Height Item 0 3FTX1 Item 4 35U065 Item 4 4LNV8 Item 0 30RE80 Item p 3FTZ7 Web Price O Web Price O Web Price O Web Price O Web Price O $868-00;each �$260.00 r each 8140.50/each $708.00/each $126.50/eaci, dd to Cart I1 dd to Cart � Add to Cart 1(1 LJ A A Add to Cart J 171 Add to Cart 8/13/2020 Print Agenda Item Request BAYTOWN AREA WATER AUTHORITY 2. a. MEETING Meeting Date: 08/19/2020 Subject: Authorize Change Order No.11 to the BAWA 6 MGD Surface Water Treatment Plant Prepared For: Andrea Brinkley, Public Works/Engineering/BAWA Prepared By_ Linda Newsted, Public Works/Engineering/BAWA Information ITEM Consider a resolution authorizing Change Order No. 11 with Pepper Lawson Waterworks, LLC, for the BAWA 6 MGD Surface Water Treatment Plant. PREFACE The Baytown Area Water Authority ("BAWA") and the City of Baytown (the "City") approved the contract with Pepper Lawson Waterworks LLC, ("PLW") for the construction of a 6 MGD Surface Water Treatment Plant (the "Project") in May 2018. The project is on schedule, and items related to the completion of certain critical items of work related to the completion of the Operations building as well as life, safety and code issues must be addressed at this time. These items are a part of Change Order No. 11, in the amount of$188,216.36. A list of the work to be performed is described below in the following items: 1. The first item of work is an increase in the amount of$9,026.801 to add and configure the City of Houston flow meter signal to provide signal information to the Fritz Lanham Surface Water Plant. BAWA staff monitors the daily flow of raw water provided by the City of Houston via the canal, and this will allow staff to access the information in addition to the City of Houston. 2. The second item of work is an increase in the amount of$169,163.74 to re-route the chemical containment and storm drain lines away from the sanitary sewer lift station, and direct flows to the sludge lagoon. This is consistent with the Fritz Lanham Surface Water Plant, and with code. 3. The third item of work is for an increase in the amount of$4,120.38 for the Elevator shunt trip disconnect, which is required by the fire code, and not included in the original design documents, but identified during the state elevator inspection. 4. The fourth item of work is for an increase in the amount of$5,905.44 for the addition of protective separation basins to contain and maintain separation of the sodium chlorite and hydrochloric acid stored in the chemical containment area at the Operations building. The two chemicals are extremely corrosive and present a health and safety issue, if not separated and any leaks were to cause a mixing of the chemicals. This was not included in the design drawings. These changes are summarized below in the following chart: 11.1 City of Houston Flow Meter Signal 1 LS 95026.80 Modifications (PCO 073) 11.2 Drain Line Modifications (PCO 074B) 1 LS 169,163.74 11.3 Shunt Trip Disconnect for Elevator (PCO 075) 1 LS 4,120.38 11.4 Chemical Vat Separators (PCO 077) 1 LS 5,905.44 TOTAL $1889216.36 RECOMMENDATION agendas.baytown.org/live/publish/print_ag_memo.cfm?seq=19223&rev num=0&mode=External&reloaded=true&id=0 1/2 8/13/2020 Print Agenda Item Request Staff recommends approval. Fiscal Impact Fiscal Year: 2020 Acct Code: 5 1 204-8500 1-WACB l 501-85001 Source of Funds (Operating/Capital/Bonds)_Capital Funds Budgeted YIN: Y Amount Needed: $188,216.36 Fiscal Impact(Additional Information)_ Attachments Signed Fon» 2270 Signed Form 1295 agendas.baytown.org/live/publish/print_ag_memo.cfm?seq=19223&rev_num=0&mode=External&reloaded=true&id=0 2/2