Ordinance No. 12,156 AGREEMENT
BETWEEN CITY AND CONTRACTOR
FOR USA GENERAL SERVICES ADMINISTRATION PURCHASE
STATE OF TEXAS §
COUNTY OF HARRIS §
THIS AGREEMENT is entered into by and between the City of Baytown (the "City") and General Contractor
Services,Inc. (the"Contractor")for the Hydro-Stop Roofing Projects detailed herein.
1. SCOPE OF WORK: This scope of work shall entail the complete turnkey construction of roofing at the
following locations:
a. Baytown Municipal Service Center at 2123 Market Street,Baytown, Texas;
b. City Hall Annex and Museum at 2200 W.Defee,Baytown,Texas;
c. Sterling Municipal Library at Mary Elizabeth Wilbanks Avenue,Baytown,Texas; and
d. Baytown Utility Billing at 2505 Market,Baytown, Texas.
The turnkey job will consist of all necessary parts, materials, equipment, freight, delivery, installation, labor,
travel time, mileage, cleanup, and any other related costs to complete the above-referenced roofmg projects
together with design and inspection services by a professional engineer licensed in the state of Texas (the
"Work"). The work includes a ten-year renewable warranty for each building and shall include, but not be
limited to the following:
Services Cost Not to Exceed
.
H
-�?�� � ' B`XyfO'kyin'IqilnlGlpA'iSe2'SFi4'e,L_'_Sliter a�a =� '' � ti
➢ Remove existing blisters throughout entire roof
> Power wash entire roof surface to remove dirt and contaminates
> Apply Hydro-Stop Barrier Guard into voids to level substrate
> Apply ten(10)year Hydro-Stop Premium Roof System over entire roof $78,925.00
surface,leaving existing foam system in place
> Install 12 permanent one way vents at designed areas to allow any
captured moisture to escape from beneath system
Modif,iedaRoof„-West'Side N F y ,.
> Power wash entire roof surface to remove dirt and contaminates
> Apply ten(10)year Hydro-Stop Premium Roof System over entire roof
surface
> Install base coat with reinforcing fabric layer $97,881.00
> Detail all transitions and flashings with base coat and fabric
> Install intermediate coat of Hydro-Stop"Premium Coat"over base coat
> Install intermediate coat of Hydro-Stop"Premium Coat"to complete the
system
` ri r „Engineering Services.prodded by:TSI`SerYicsAte....4 ..
> Review manufacturer's procedure for installation of fully adhered Hydro-
Stop roof covering to existing modified bitumen and foam roof based on
130 mph 3 second gust design pressure $1,500.00
> Provide inspection services to document contractor's adherence to
manufacturer's required installation method
„, .a City IlallAnne%'and"Museum s ki.3.�... . . .. .... F'..Hydro-Stop Premium Roof:Coat System , ;; 4 x
➢ Remove loose gravel from entire roof surface
> Apply Hydro-Stop Barrier Guard at low areas to level
> Install Dens Deck Recovery Board onto entire roof surface using heavy $179,832.00
duty fasteners
> Install tapered insulation using heavy duty fasteners at areas between roof
drains to divert water.
City of Baytown,Texas
Hydro-Stop Roofing Projects
> Apply Hydro-Stop Premium Foundation Coat onto entire roof surface
> Embed Hydro-Stop Reinforcement Fabric and apply second layer of
foundation coat
> Apply two(2)layers of Hydro-stop Premium Finish coat onto entire roof
surface
> Install metal counter flashing at lower roof edge and encapsulate with
fabric and finish coat
fi: s Engineering S,ervices{`provided`byxTSI seiwices,LLC ,k s y` r ' 3 'e `
> Review City-provided existing roof drawings and provide the following
engineering services:
> Installation design drawings of Iso-Board and Hydro-Stop roof
covering based upon 130 mph 3 second gust design pressure $2,500.00
> Witness fastener pull-out testing and verify fastener spacing and
selection to meet design pressures
> Based upon selection of an approved installation method,drawings
specific to the services rendered will be stamped
> Perform 4 to 5 individual windstorm inspections $1,500.00
Sterlin Munici` al Lib a ry
Hydro-Stopyremium Hoof Coat.System..,,i r310� s ;;.,;s,° ME
> Remove loose gravel at small modified roof surface
> Power wash entire single ply roof surface
> Install Dens Deck Recovery Board onto modified roof surface using
heavy duty fasteners
> Apply Hydro-Stop Premium Foundation Coat onto entire roof surface $407,423.00
> Embed Hydro-Stop Reinforcement Fabric into foundation coat and apply
second layer
> Apply two(2)layers of Hydro-Stop Premium Finish coat onto entire roof
surface
,.r_.,.. Engineering Services aprovided by TSI Sei ices,:LLC x
> Review roof drawings provided by the City to design fastener spacing
and review manufacturer's installation procedure for installation over
modified bitumen
> Fastener spacing of Iso-Board installation over Video Section of Library
only
> Hydro-stop roof covering entire roof including Video Section as well as
modified bitumen $3,500.00
> Fastener spacing design and fully adhered specifications based on 130
mph 3 second gust design pressure
> Witness fastener pull-out testing and verify fastener spacing and selection
to meet design pressures
> Based on selection of an approved installation method,drawings specific
to services rendered will be stamped.
> Perform 4 to 5 individual windstorm inspections $1,500.00
Ba
p�l1 town,Utili
� s Hydro-Stop Premiu n:Roof Coat System;... .ear F �` n
> Remove existing loose gravel from roof surface.
> Attach dens deck board onto roof using fasteners through metal roof pan.
> Attach roof edge metal flashing. $60,351.00
> Apply Hydro-Stop Premium Roof Coat System onto entire roof surface.
> Apply walk path material onto roof to A/C Equipment.
Engineering Services provided by`;TSI\Sere ces:LI:C.,. .: :< , .... :< .
> Review City-provided existing roof drawings,if any,and provide the $2,500.00
following engineering services:
> Installation design drawings of Iso-Board and Hydro-Stop roof
2
City of Baytown,Texas
Hydro-Stop Roofing Projects
covering based upon 130 mph 3 second gust design pressure
> Witness fastener pull-out testing and verify fastener spacing and
selection to meet design pressures
> Based upon selection of an approved installation method,drawings
specific to the services rendered will be stamped
➢ Perform 4 to 5 individual windstorm inspections
4:,5` S e r *,iSi fi =fit - ft rl'a^g : `, 71 " t
: Performance Bond
' Payment Bond :.
➢; MaintenanceBonds« $7,978 00
➢ . Insurance
Total Cost Not to Exceed $845,390.00
Such services shall be performed for a cost not to exceed EIGHT HUNDRED FORTY-FIVE THOUSAND
THREE HUNDRED NINETY AND NO/100 DOLLARS ($845,390.00)based upon the pricing schedule
from GSA#GS-07F5988R included hereinbelow:
SIN Product Name Coverage Item# GSA Price
563-4 PremiumCoat Fabric 4" 2004-004 $28.50
563-4 PremiumCoat Fabric 6" 2004-006 $32.28
563-4 PremiumCoat Fabric 8" 2004-008 $39.36
563-4 PremiumCoat Fabric 12" 2004-012 $57.18
563-4 PremiumCoat Fabric 16" 2004-016 $71.15
563-4 PremiumCoat Fabric 20" 2004-020 $87.98
563-4 PremiumCoat Fabric 24" 2004-024 $104.19
563-4 PremiumCoat Fabric 40" 1000 ft Lapped 2004-040 $162.91
563-4 Pre-Cut PremiumCoat Fabric 40" 2005-400 $10.21
563-4 PremiumCoat Foundation Coat 40 fi/gallon 2002-001 $33.51
563-4 PremiumCoat Foundation Coat 2002-005 $133.68
563-4 PremiumCoat Finish Coat Battleship Grey- 1 gallon 70 ftvgallon 2003-041 $40.59
563-4 PremiumCoat Finish Coat Battleship Grey-5 gallon 70 ftvgallon 2003-045 $154.60
563-4 PremiumCoat Finish Coat Brown-1 gallon 70 ftvgallon 2003-071 $40.59
563-4 PremiumCoat Finish Coat Brown-5 gallon 70 ftvgallon 2003-075 $154.92
563-4 PremiumCoat Finish Coat Charcoal-1 gallon 70 ftvgallon 2003-021 S40.59
563-4 PremiumCoat Finish Coat Charcoal-5 gallon 70 ftvgallon 2003-025 $154.92
563-4 PremiumCoat Finish Coat Cotton -1 gallon 70 ft gallon 2003-121 $40.59
563-4 PremiumCoat Finish Coat Cotton-5 gallon 70 ftvgallon 2003-125 $154.92
563-4 PremiumCoat Finish Coat Charleston Green—1 gallon 70 ft gallon 2003-061 $40.59
563-4 PremiumCoat Finish Coat Charleston Green—5gallon 70 ft gallon 2003-065 $154.92
563-4 PremiumCoat Finish Coat Desert Sand—1 gallon 70 fegallon 2003-101 $40.59
563-4 PremiumCoat Finish Coat Desert Sand-5 gallon 70 ft21gallon 2003-105 $154.92
563-4 PremiumCoat Finish Coat Patina Green-1 gallon 70 ft gallon 2003-051 $40.59
563-4 PremiumCoat Finish Coat Patina Green-5 gallon 70 ftvgallon 2003-055 $154.92
563-4 PremiumCoat Finish Coat Terra Cotta-1 gallon 70 ft2igallon. 2003-081 $40.59
563-4 PremiumCoat Finish Coat Terra Cotta-5 gallon 70 ftvgallon 2003-085 $154.92
563-4 Premium<:oat Finish Coat Tinners Red- 1 gallon 70 ftvgallon 2003-091 $40.59
563-4 PremiumCoat Finish Coat Tinners Red-5 gallon 70 ftvgallon 2003-095 $154.92
563-4 PremiumCoat Finish Coat Dove Grey-1 gallon 70 ftvgallon 2003-031 $40.59
•
City of Baytown,Texas
Hydro-Stop Roofing Projects
SIN Product Name Coverage Item# GSA Price
563-4 PremiumCoat Finish Coat Dove Grey-5 gallon 70 ft gallon 2003-035 $154.92
563-4 PremiumCoat Finish Coat White-1 gallon 70 ft gallon 2003-011 $40.16
563-4 PremiumCoat Finish Coat White-5 gallon 70 ft'gallon 2003-015 $150.02
563-4 PremiumCoat Deep Tone Base(White)- 1 gallon 70 ft gallon 2002-100 $34.85
563-4 PremiumCoat Deep Tone Base(White)-5 gallon 70 ft gallon 2002-500 $146.79
563-4 PremiumCoat Deep Tone Base(tinted)-1 gallon 70 ft gallon 2002-100 $40.59
TINT
563-4 PremiumCoat Deep Tone Base(tinted)-5 gallon 70 fl gallon 2002-500 $154.92
TINT
563-29 Brush-Flashing 4"-5 gallon 9010-004 $3.11
563-29 Brush Hand Roof 4" 9011-002 $4.10
563-29 Brush 6"Roof 9010-006 $4.26
563-29 Brush 10"Roof 9010-010 $7.98
563-29 Brush Handle 9011-001 $5.72
563-29 Roller-9"Roller Frame 9050-001 $5.24
563-29 Roller Cover 1 1/4 Nap 9055-001 $2.62
563-29 Roller Handle 60" 9060-001 $6.41
563-29 HydroFiber-5 gallon TBA 1100-800 $40.10
563-29 HydroCaps-box 1296/box 1100-500 $124.74
563-29 Pail Opener 9012-001 $22.24
563-29 Rilem Test Tube 10000-001 $52.25
563-29 24"Push Broom 9040-001 $17.87
563-29 BarrierGuard-1 gallon 50-60 ft2/gallon 4000-001 $46.79
563-29 BarrierGuard-5 gallon 4000-005 $168.69
563-29 Clearguard Plus-1 gallon 80-200 ft2/gallon 5002-001 $34.15
563-29 Clearguard Plus-5 gallon 5002-005 $170.76
563-29 Flexcoat-White-1 gallon 180 f1/gallon 3000-001 $34.95
563-29 Flexcoat -White-5 gallon 3000-005 $122.29
563-29 Flexcoat-White Tint Base-TINTED 180 ft2/gallon 3000-011 $39.10
563-29 Flexcoat-White Tint Base-TINTED 3000-015 $136.03
563-29 Flexcoat-Tinted- 1 gallon 180 ft/gallon 3000-021 $34.95
563-29 Flexcoat-Tinted-5 gallon 3000-025 $122.29
563-29 Flexcoat-Deep Tone Base-TINTED 180 ft2/gallon 3000-031 $39.10
563-29 Flexcoat-Deep Tone Base-TINTED 3000-035 $136.03
563-4 CleanAct-EPDM- 1 gallon 200 ft/gallon 2010-001 $33.40
563-4 CleanAct-EPDM-5 gallon 2010-005 $152.90
563-4 Stablerust Primer- 1 gallon 200 ft2/gallon 2001-001 $49.19
563-4 Stablerust Primer-5 gallon 2001-005 $195.87
563-4 Surebond Primer- 1 gallon 200 ft2/gallon 2000-001 $30.71
563-4 Surebond Primer-5 gallon 2000-005 $108.96
563-4 Traffic Coat-White- 1 gallon 125 ft2/gallon 1000-001 $42.51
563-4 Traffic Coat-White-5 gallon 1000-005 $173.25
563-4 Traffic Coat-Deck Grey- 1 gallon 125 ft2/gallon 1000-011 $42.51
563-4 Traffic Coat-Deck Grey-5 gallon 1000-015 $173.25
563-4 Traffic Coat-Deck Tan-1 gallon 125 ft2/gallon 1000-016 $42.51
563-4 Traffic Coat-Deck Tan-5 gallon 1000-017 $173.25
563-4 Traffic Coat. Slate Grey-1 gallon 125 ft2/gallon 1000-018 $42.51
563-4 Traffic Coat. Slate Grey-5 gallon 1000-019 $173.25
4 1
City of Baytown,Texas
Hydro-Stop Roofing Projects
2. CONTRACT DOCUMENTS: The contract documents shall consist of the following documents, which are
listed in the order of priority of interpretation should there be a conflict:
a) Addenda to this Agreement,
b) Agreement,
c) Plans, if any,
d) Technical Specifications, and
e) Performance,Payment and Maintenance Bonds.
No amendments to this Agreement shall be effective and binding until it is reduced to writing and signed by the
duly authorized representatives of both parties. Contract Documents shall be distributed by the Contractor to its
subcontractors as necessary and must be kept and be accessible at the work site. The plans and specifications
must be returned to the City on request at the completion of the work.
3. CITY'S REPRESENTATIVE: The project shall be administered by the City's Representative, whose duties
shall include,but not be limited to,the following:
a) periodically review and inspect the Contractor's work;
b) issue instructions and directives to the Contractor, with which Contractor is obligated to comply,
provided such directions and instructions are consistent with the obligations of this Agreement;
c) make visits to the site at intervals appropriate to the various stages of construction, appropriate to
observe as an experienced and qualified design professional the progress and quality of the Work; and
d) keep City informed of the progress of the Work.
4. COMMUNICATIONS: The Contractor shall forward all communications, written or oral, to the City through
the City's Representative. Written notice shall be deemed to have been duly served if delivered in person to the
individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered
at or sent by telecopier, overnight or facsimile transmission or if delivered or sent by certified or registered mail
to the last business address as indicated herein. Each party will have the right to change its business address by
giving at least thirty (30) calendar days' written notice to the other party of such change.Notice given by mail
shall be deemed given three(3)calendar days after the date of the mailing thereof.
5. COMMENCEMENT AND COMPLETION OF WORK: Once the bonds and the certificate of insurance
have been submitted to and approved by the City, the Contractor shall perform the work in the most expedient
manner possible. The work shall commence as soon as possible,but no later than ten (10)calendar days of the
date specified in the notice to proceed. Engineering design services shall be completed within twenty (20)
calendar days of the date specified in the notice to proceed. Completion of the construction services shall be
within one hundred eighty (180) calendar days of the date specified in the notice to proceed. Time is of the
essence in this Agreement and the date of beginning and the date for fmal completion of work as specified in
this Agreement are essential conditions of this Agreement. Contractor has submitted its quote in full recognition
of the time required for the completion of this Work taking into consideration all factors, including, but not
limited to, the average climatic range, industry conditions, and liquidated damages. At fmal completion of the
Work, a certificate of fmal completion shall be issued by the Director of Engineering.
6. WORK. The Contractor shall complete the work described in the contract documents in strict conformity
therewith. The Contractor shall:
a) provide and pay for all materials, supplies, machinery, equipment, tools, superintendents, laborers,
insurance, fuel, transportation, and all other facilities and utilities necessary for the execution and
completion of the Work;
b) secure and pay all permits, fees, licenses, and inspections necessary for the proper execution and
completion of the work;
5
City of Baytown,Texas
Hydro-Stop Roofing Projects
c) give all notices required by law and comply with all laws, ordinances, regulations, codes, rules and
lawful orders of all public authorities bearing on the performance of the work;
d) pay sales, consumer,use and similar taxes as legally required; and
e) provide shop drawings and schedules to the City's Representative and secure the City's
Representative's approval of the same, which approval shall not relieve Contractor from responsibility
for errors.
7. EXTENSIONS AND DELAYS:
a) EXTENSIONS. Within seven (7) calendar days of any act or incident that the Contractor reasonably
believes may justify an extension of time for final completion, the Contractor may apply in writing for
an extension of such time, submitting therewith all written justification as may be required by City.
Thereafter, the City's Representative, within seven (7) calendar days after receipt of a written request
for an extension of time from the Contractor, which is supported by all requested documentation, shall
then grant or deny such written request; provided that the request for an extension is not based upon
weather conditions. Should an extension be requested within the seven (7) calendar-day period based
upon weather conditions, the CITY'S REPRESENTATIVE shall grant or deny such a written request
upon Final Completion of the Work based upon any variation from the average climatic range.
b) DELAYS. The Contractor, in undertaking to complete the work within the time herein fixed, has taken
into consideration and made allowance for all hindrances and delays incident to such work, whether
growing out of delays in securing material or workmen or weather or otherwise. No charge whatsoever
shall be made for hindrances or delays from any cause whatever, except where the work is stopped by
order of the City or by extraordinary causes. Any extension shall not exceed the time actually lost by
Contractor.
8. PAYMENT: The Contractor agrees to perform the Work for the unit prices specified herein, which the City
shall pay upon final completion and acceptance of the Work, subject to any adjustment allowed herein. The
Contractor shall never be entitled to anticipated or lost profits on the deleted or reduced portion of a job whether
bid on a unit price or lump sum basis. The Contractor shall not have the right to obligate the City to make any
payments to another party.
If the actual amount of the work to be done and the materials to be furnished differ from the estimate, then
payment shall be for the actual amount of accepted work done and materials incorporated into the project.
Reduction in the scope or quantity of work on unit price items shall merely reduce the number of units.
No changes shall be made and no bills for changes, alterations, modifications, deviations, and extra orders shall
be recognized or paid for except upon a written change order signed by the Contractor and the City. Any
change shall not affect the validity of any bonds. Any requests by the Contractor for a change in original
Payment Amount shall be made prior to the beginning of the work covered by the proposed change or the right
to payment for Extra Work shall be waived.
9. INDEPENDENT CONTRACTOR: In all activities or services performed hereunder, the Contractor is and at
all times shall remain an independent contractor, not an agent or employee of the City. The Contractor, as an
independent contractor, shall be solely responsible for the fmal product contemplated under this Agreement. It
shall be the responsibility of the Contractor to furnish a completed work product that meets the requirements of
the City. Any additional work, material, or equipment needed to meet the intent of this specification shall be
supplied by the Contractor without claim for additional payment, even though not specifically mentioned herein.
6
City of Baytown,Texas
Hydro-Stop Roofing Projects
10. DISORDERLY EMPLOYEES: The Contractor agrees to employ only orderly and competent persons, skillful
in the performance of the type of work required under this contract,to do the Work. The Contractor shall retain
personal control and shall give its personal attention to the faithful prosecution and completion of the work and
fulfillment of this Agreement. The Contractor shall appoint and keep on the project during the progress of the
Work a competent Project Superintendent-Manager and any necessary assistants, all satisfactory to City to
supervise its employees and subcontractors. Adequate supervision by Contractor is essential to the proper
performance of the Work, and lack of such supervision shall be grounds for suspending the operations of the
Contractor and declaring Contractor in breach of this Agreement. Whenever the City or the City's
Representative shall inform the Contractor in writing that any person or persons performing any of the requisite
work are, in the opinion of the City or the City's Representative, incompetent, unfaithful or disorderly, such
person or persons shall be discharged and shall not again be employed to perform any work on the project
without prior written consent of the City or the City's Representative.
11. NATURE OF THE WORK: It is understood and agreed that the Contractor has, by careful examination,
satisfied itself as to the nature and location of the work, the confirmation of the ground and soil, the nature of
any structures, including surface and subsurface utilities,the character, quality and quantity of the material to be
utilized, the character of equipment and facilities needed for and during the prosecution of the work, the time
needed to complete the work, Contractor's ability to meet all deadlines and schedules required by this
Agreement, the general and local conditions, and all other matters that in any way affect the work under this
Agreement.
12. PROGRESS OF WORK: The Contractor may prosecute its work at such time and sessions, in such order of
precedence, and in such manner as shall be most conducive to the economy of the project; provided; however,
that the order and time of prosecution shall be such that the work shall be finally completed as a whole, in
accordance with this Agreement. Further,the parties shall be subject to the following:
a) The City reserves the right to enter the property by such employee(s) or agent(s) as it may elect for the
purpose of inspecting the work;
b) The Project Superintendent/Manager shall coordinate its activities and work with the City. If required
by the City, the Contractor shall provide a weekly schedule of planned activities, which may be
reviewed on a daily basis. In the case of any completed work or material that is to be covered over by
other material,the Project Superintendent/Manager shall provide notice to the City no later than twenty-
four (24) hours before the anticipated cover-up of the previously completed work or material. In the
event, however, that such notice is provided on a Friday the City will have until the following Monday
afternoon to approve the previously completed work and its cover-up and the Contractor shall take no
action until such approval is given by City;
c) The Contractor shall submit,at such time as may reasonably be requested by City, further schedules that
shall list the order in which the Contractor proposes to carry on the work with dates at which the
Contractor will start the several parts of the work and the estimated dates of completion of the several
parts; and
d) The Contractor shall attend additional meetings called by the City or the City's Representative upon
twenty-four(24)hours' notice unless otherwise agreed by the parties.
13. SITE CONDITIONS AND MANAGEMENT: Throughout the progress of the work,the Contractor shall keep
the working area free from debris of all types, and remove from premises all rubbish, resulting from any work
being done by it. At the completion of the work, the Contractor shall leave the premises in a clean and finished
condition. Any failure to do so may be remedied by the City or its designee and charged back to the Contractor.
Where the Contractor is working around or in existing structures, it shall verify conditions at the site, including,
but not limited to, roads, easements, door openings, passages, and other existing site conditions. Any items
constructed or manufactured off-site or outside of buildings shall be done so that they are not too bulky for
7
City of Baytown,Texas
Hydro-Stop Roofing Projects
existing facilities. The Contractor shall provide special apparatus as required to handle any such items. All
special handling equipment charges shall be at the Contractor's sole cost and expense.
Where gas,water, and sewer lines exist in the vicinity,the Contractor shall assume that service connections exist
to each building and exercise appropriate caution during excavation. It is the Contractor's responsibility to
notify various owners in advance when excavation is to be done in the vicinity of their underground lines and
structures. Damage to such underground lines and structures, whether or not shown on the plans, shall be the
responsibility of the Contractor and it shall bear the cost of necessary repair or replacement of damaged parts.
The Contractor shall be responsible for verifying all conditions at the site prior to performing the Work. As
such, the Contractor understands and agrees that it shall be responsible for conditions encountered at the site,
including, but not limited to, (i) subsurface or otherwise concealed physical conditions which differ from those
indicated in the Contract Documents, and (ii) unknown physical conditions, which differ from those ordinarily
found to exist and generally recognized as inherent in construction activities of the character provided for in the
Contract Documents. No additional compensation shall be afforded to the Contractor for differing site
conditions. Any information provided by the City, including, but not limited to geotechnical information, shall
be for the Contractor's convenience only and the City does not guarantee the accuracy or correctness of any
information so provided.
14. LAYOUT OF WORK: The Contractor shall lay out all work in a manner acceptable to the City in accordance
with applicable codes and ordinances of the city, county and state. The City's Representative will review the
Contractor's layout of all structures and any other layout work done by the Contractor, but this review does not
relieve the Contractor of the responsibility of accurately locating all work in accordance with the specifications
and Contract Documents.
15. CONTRACTOR'S STRUCTURES: Whenever the Contractor erects, installs, or uses additional structures on
the property for the storage, maintenance of materials or use of employees and subcontractors, such structure
shall not damage the property and the Contractor shall maintain sanitary conditions in and about such structures
at all times in a manner satisfactory to the City. The Contractor shall provide and maintain necessary sanitary
conveniences for the use of laborers on the work. Such conveniences shall be properly secluded from public
observation and shall be in a location approved by the City's Representative. The City may charge the
Contractor for any damage or injury to the City, its property or third persons as a result of the location or use of
any of Contractor's structures.
16. MATERIALS:
a) Materials or work described in words which when so applied have well-known technical or trade meaning shall be
held to refer to such recognized standards. All work shall be done and all materials furnished in strict conformity
with the Contract Documents and recognized industry standards.
b) Materials and supplies utilized in the fmal product that will be turned over to the City shall be new and of
good quality. Upon request,the Contractor shall supply proof of quality and manufacturer.
c) No refurbished, reconditioned or other previously utilized materials or supplies will be used without the
signed authorization of the City.
d) Where the product is to be turned over to the City, the Contractor may utilize substitutes of equal quality and
function as provided for in the specifications.
e) The City shall have full and fmal decision over the use of substitute materials and supplies.
f) The Contractor shall certify to the City that all materials installed are free from asbestos containing material.
17. OBSERVATION,INSPECTIONS,TESTS:
a) The City and the City's Representative reserve the right to enter the property by such employee(s) or
agent(s) as he may elect for the purpose of inspecting the work. In accordance therewith, the Contractor
8
City of Baytown,Texas
Hydro-Stop Roofing Projects
shall supply the City or the City's Representative,upon request,with any keys or information necessary for
the City or the City's Representative to have access to the property. The City and the City's Representative
shall have the right to enter the property or location of the work for the purpose of performing such
collateral work as the City or the City's Representative deems necessary or appropriate.
b) The City and the City's Representative shall have the right, at any reasonable time, to observe and test the
work. The Contractor shall make necessary arrangements and provide proper facilities and access for such
observation and testing at any location wherever the work or any part thereof is in preparation or progress.
The Contractor shall ascertain the scope of any observation that may be contemplated by the City or the
City's Representative and shall give ample notice as to the time each part of the work will be ready for such
observation.
c) The City or the City's Representative may reject any work found to be defective or not in accordance with the
Contract Documents, regardless of the state of its completion or the time or place of its discovery regardless
of whether the City or the City's Representative has previously accepted the work through oversight or
otherwise. Neither observations by the City or the City's Representative nor inspections, tests, or approvals
made by the City or the City's Representative, or persons authorized under this Agreement to make such
inspections, tests, or approvals, shall relieve the Contractor from its obligation to perform the work in
accordance with the requirements of the Contract Documents.
d) The City or the City's Representative upon approval of the City may require the Contractor to remove,
dismantle or uncover work completed. In the event that the Contractor has failed to perform the work as
required by the specifications, or drawings, or other Contract Documents, Contractor shall assume and pay the
costs of repair and restoration of the work required to be removed, dismantled,or uncovered. In the event that
the Contractor has performed the work correctly to specifications, City shall assume and pay the cost of
restoration of the construction to the point that the City has required the work to be uncovered or dismantled.
18. WORK STOPPAGE: The City or the City's Representative shall have the right to order the work of the
Contractor or any subcontractor wholly or partially stopped immediately under any one or more of the following
conditions:
a) the work may be ordered stopped immediately if in the judgment of the City or the City's Representative, any
of the materials furnished or the work being done is not in strict accordance with this Agreement;
b) the work may be ordered stopped immediately until any objectionable person or material is removed from the
premises; or
c) the work may be ordered stopped immediately if any portion of the work is being performed so as to create a
hazardous condition.
Such stoppage or suspension shall neither invalidate any of the Contractor's performance obligations under this
Agreement, including time of performance and deadlines therefor,nor will extra charge be allowed the Contractor
by reason of such stoppage or suspension.
19. REJECTED WORK: The City or the City's Representative, in its discretion,may reject any and all work that is
found to be defective or deemed not in conformity with this Agreement. The City or the City's Representative
may reject said work or any portion thereof regardless of the stage of its completion or time or place of discovery
of such errors. Further, the City or the City's Representative may reject said work regardless of whether the City
or the City's Representative has previously accepted the work through oversight or otherwise. Neither
observations by the City or the City's Representative nor inspections, tests, certificates or approvals made by the
City or the City's Representative, or persons authorized under this Agreement to make such inspections, tests,
certificates or approvals, shall relieve the Contractor from its obligation to perform the work in accordance with
the requirements of this Agreement and the other Contract Documents. In the event that any work or any part
thereof is rejected by the City or the City's Representative, the Contractor shall, at its sole expense and after
receipt of written notice thereof from the City or the City's Representative remove such material and rebuild or
otherwise remedy such work so that it shall be in full compliance with this Agreement and the other Contract
Documents, as follows:
a) At the option of the City, the Contractor may be required to remedy such work so that it shall be in full
compliance with this Agreement. As soon as possible but not later than seven (7) calendar days after receipt
of notice from the City or the City's Representative or such other period of time specified by the City's
9
City of Baytown,Texas
Hydro-Stop Roofing Projects
Representative in writing, the Contractor shall, at its sole expense, replace or repair all rejected work or
materials so as to conform with this Agreement.
b) If the City or the City's Representative in its discretion deems it inexpedient to correct work damaged or not
done in accordance with this Agreement, an equitable deduction for the Payment Amount may be made by the
City.
c) If the Contractor does not remove or replace any rejected work within the time specified in Section in
subsection (a) hereof, then the City or the City's Representative may have the work removed, replaced or
repaired at the Contractor's expense.
20. SUBCONTRACTORS: The Contractor shall retain personal control and give its personal, utmost attention to
the faithful prosecution and completion of the work and fulfillment of this Agreement. The subletting of any
portion or feature of the work or materials required in the performance of this Agreement shall not relieve the
Contractor from its obligations to the City under this Agreement. All subcontractors must be approved by the
City's Representative prior to performing any work on the Project. If the City's Representative judges any
subcontractor to be failing to perform the work in strict accordance with the drawings and specifications, the
Contractor shall discharge the same, but this shall in no way release the Contractor from its obligations and
responsibility under this Agreement. Every subcontractor shall be bound by the terms and provisions of this
Agreement as far as applicable to its work. The Contractor shall be fully responsible to the City and the City's
Representative for the acts and omissions of its subcontractors.
The Contractor shall be solely and exclusively responsible for compensating any of the Contractor's employees,
subcontractors, materialmen and/or suppliers of any type or nature whatsoever. The Contractor shall further be
exclusively responsible for ensuring that no claims or liens of any type are filed against any property owned by
the City arising out of or incidental to the performance of any services performed pursuant to this Agreement. In
the event a statutory lien notice is sent to the City or the City's Representative, the Contractor shall, where no
payment bond covers the work, upon written notice from the City or the City's Representative, immediately
obtain bond at the Contractor's sole expense and hold the City harmless from any losses that may result from the
filing or enforcement of any said lien notice. In the event that the Contractor defaults in the provision of the bond,
the City may withhold such funds as are necessary to ensure the payment of such claim until litigation determines
to whom payment shall be made.
21. POSSESSION AND USE OF COMPLETED PORTIONS: The City shall have the right to take possession of
and use any completed or partially completed portions of the work, notwithstanding the time for completing the
entire work or such portions may not have expired, but such taking possession and use shall not be deemed an
acceptance of any work not completed in accordance with the Contract Documents.
22. PERMITS AND CERTIFICATES: The Contractor shall secure and pay for all necessary permits, licenses
and/or certificates issued by the state, municipality or other authorities and submit the same to the City's
Representative. The City may withhold any payments due under this Agreement or that may become due under
this Agreement until the necessary permits, licenses and/or certificates are procured and delivered. The
Contractor will not, however, be required to pay for any permit fees for permits to be issued by the City, which
will be waived in conjunction with this Agreement.
23. FAULTY WORKMANSHIP: Neither the fmal payment nor any acceptance nor certificate nor any provision of
this Agreement shall relieve the Contractor of any responsibility for faulty workmanship or materials. At the
option of the City, as provided in this Agreement,the Contractor shall remedy any defects thereto and pay for any
damage to other work resulting therefrom,which may appear after fmal acceptance of the work.
24. WARRANTY: Upon acceptance of the work by the City, the Contractor warrants for a period of ten (10)
calendar years from the date thereof that all materials provided to the City under this Agreement shall be new
unless otherwise approved in writing by the City's Representative and that all materials and work will be of good
quality, free from faults and defects, and in conformance with this Agreement. All work not conforming to these
requirements, including,but not limited to, substitutions not properly approved and authorized,may be considered
10
City of Baytown,Texas
Hydro-Stop Roofing Projects
defective. This warranty is in addition to any rights or warranties expressed or implied by law and consumer
protection claims arising from misrepresentations by the Contractor. Where a longer warranty is specified for
individual products, work or materials, the longer warranty shall govern. This warranty obligation shall be
covered by any performance or payment bonds tendered in compliance with this Agreement.
-25. DEFECTIVE WORK DISCOVERED DURING WARRANTY PERIOD: If within ten (10) calendar years
after the date of acceptance by the City of designated equipment or within such longer period of time as may be
prescribed by law or by the terms of any applicable special warranty required by this Agreement, any of the work
is found or determined to be defective, including obvious defects, or otherwise not in accordance with this
Agreement,the Contractor shall correct it PROMPTLY.
a) After receipt of written notice from the City to begin corrective work,the Contractor shall promptly begin the
corrective work. This obligation shall survive the termination of this Agreement. The guarantee shall not
constitute the exclusive remedy of the City,nor shall other remedies be limited to either warranty or guarantee
period.
b) If within seven (7) calendar days after the City has notified the Contractor of a defect, failure or abnormality
in the work, the Contractor has not started to make the necessary corrections or adjustments, the City is
hereby authorized to make the corrections or adjustments, or to order the work to be done by a third party.
The cost of the work shall be paid by the Contractor.
c) The cost of all materials, parts, labor, transportation, supervision, special instruments, and supplies required
for replacement or repair of parts and for correction of defects, shall be paid by the Contractor or by the
surety.
d) The ten (10) calendar years warranty shall cover all work, equipment, and materials that are part of this
project,whether or not a warranty is specified in the individual section prescribing that particular aspect of the
work.
26. LIQUIDATED DAMAGES: It is expressly understood and agreed by the parties that time is of the essence to
this Agreement and that the date set for the fmal completion of the work described herein is an essential condition
of this Agreement. It is further understood and agreed that the date for fmal completion of the work is reasonable
dates for the completion of the project, taking into consideration all conditions, including, but not limited to, the
average climatic change and conditions and usual industrial conditions prevailing in this locality. If the
Contractor should neglect, fail, or refuse to complete the work required for fmal completion within the date
specified in this Agreement, or any proper extension that is granted in writing by the City, then the Contractor
hereby agrees, as a part of the consideration for the awarding of this Agreement, that the City may withhold
permanently from the Contractor's total Payment Amount the sum of FIVE HUNDRED AND NO/100
DOLLARS ($500.00) for each and every calendar day that the Contractor is in default after the date stipulated
for fmal completion,not as a penalty, but as liquidated damages for the breach of the Agreement. The amount of
liquidated damages for the Contractor's failure to meet the deadline for fmal completion is fixed and agreed on by
the Contractor because of the impracticability and extreme difficulty in fixing and ascertaining actual damages
that the City would in such an event sustain. The amounts to be charged are agreed to be the damages that the
City would sustain and may, at the option of the City, be retained from fmal payment or any other payment made
hereunder.
27. WITHHOLD PAYMENT AND CONTRACTOR'S PAYMENT: Regardless of any bond, the City may, on
account of subsequently discovered evidence,withhold payment or nullify the whole or part of any acceptance or
certificate to such extent as may be necessary to protect the City from loss on account of:
a) Defective work or work that is not in strict accordance with the terms of this Agreement, the Specifications,
or the other Contract Documents;
b) Claims filed or reasonable evidence indicating probable filing of claims, as determined at the sole discretion
of the City;
c) Failure of the Contractor to make prompt payments to subcontractors or for material or labor or materialmen;
d) Claims filed or reasonable evidence, as determined at the sole discretion of the City, of damage to another
Contractor or a third party, including adjacent property owners;
11
City of Baytown,Texas
Hydro-Stop Roofing Projects
e) Reasonable doubt, as determined at the sole discretion of the City, that the work can be completed for the
unpaid balance of the contract amount;
fj Reasonable indication, as determined at the sole discretion of the City, that the work will not be completed
within the contract time;
g) Liquidated damages and administrative charges,as determined by the City at its sole discretion;
h) Charges made for repairs to the Contractor's defective work or repairs made by the City to correct damage to
other property;
i) Claims filed or reasonable evidence as determined at the sole discretion of the City indicating unremedied
damage to property owned by the City;or
j) Other amounts authorized under this Agreement.
Whenever the Contractor and/or its surety is required to make a payment under this Agreement, it is expressly
understood and agreed that such payment shall be due within 15 days after receipt of an invoice therefore unless
expressly stated otherwise. Payments required by Contractor and/or its surety, which are not timely made, shall
accrue interest at a rate of one percent per month.
28. CHARGES FOR INJURY OR REPAIRS:
a) REPAIRS. The Contractor shall be liable and responsible for any damages incurred or repairs made
necessary by reason of its work and/or caused by it. Repairs of any kind required by the City or the City's
Representative will be made and charged to the Contractor by the City. The Contractor shall take the
necessary precautions to protect any areas adjacent to its work. The work specified consists of all work,
materials and labor required by the City or the City's Representative to repair any damage to the property of
the City, including,but not limited to, structures, roadways, curbs,parking areas and sidewalks,to an equal or
better condition than before such property was damaged.
b) INJURY. The Contractor shall at all times exercise reasonable precautions for the safety of employees and
others on or near the work and shall comply with all applicable provisions of Federal, State, and Municipal
safety laws and building and construction codes. All machinery and equipment and other physical hazards
shall be guarded in accordance with the "Manual of Accident Prevention in Construction" of the Associated
General Contractors of America except where incompatible with Federal, State, or Municipal laws or
regulations. The Contractor shall provide such machinery guards, safe walkways, ladders, bridges,
gangplanks, and other safety devices. The safety precautions actually taken and their adequacy shall be the
sole responsibility of the Contractor, acting at his discretion as an independent Contractor.
29. PAYMENT OF EMPLOYEES AND FOR MATERIALS: Wage rates paid on this project shall not be less
than specified in the schedule of general prevailing rates of per diem rates attached hereto as Exhibit "A" and
incorporated herein for all intents and purposes. Should the Contractor or any of its subcontractors fail to pay the
general prevailing rate to a worker performing work on the project, the Contractor shall pay to the City SIXTY
AND NO/100 DOLLARS ($60.00) for each worker employed for each calendar day or part of the day that the
worker is paid less than the wage rates stipulated in this Contract. The Contractor and each of the subcontractors
shall pay each of its employees engaged in work on the project under this Agreement in full(less mandatory legal
deductions), in cash or by check readily cashable, without discount, no less than once every two (2)weeks. The
City or City's Representative may, prior to final acceptance of the project, require the Contractor to execute an
affidavit in legal form stating that all bills for labor, materials, and incidentals incurred have been paid in full and
that there are no claims pending of which the Contractor has been notified.
30. INSURANCE REQUIREMENTS:
Contractor shall procure and maintain at its sole cost and expense for the duration of the Agreement, insurance
against claims for injuries to person or damages to property which may arise from or in connection with the
performance of the Work hereunder by Contractor, its agents, representatives, volunteers, employees or
subconsultants.
12
City of Baytown,Texas
Hydro-Stop Roofing Projects
a. Contractor's insurance coverage shall be primary insurance with respect to the City, its officials, employees
and agents. Any insurance or self-insurance maintained by the City, its officials, employees or agents shall be
considered in excess of Contractor's insurance and shall not contribute to it. Further, Contractor shall include
all subconsultants, agents and assigns as additional insured under its policy or shall furnish separate
certificates and endorsements for each such person or entity. All coverage's for subconsultants and assigns
shall be subject to all of the requirements stated herein.
The following is a list of standard insurance policies along with their respective minimum coverage amounts
required in this Agreement:
1. Commercial General Liability
• General Aggregate: $2,000,000
• Products&Completed Operations Aggregate: $2,000,000
• Personal&Advertising Injury: $1,000,000
• Per Occurrence: $1,000,000
• Fire Damage: $300,000
• Coverage shall be at least as broad as ISO CG 00 02 12 07
• No coverage shall be deleted from standard policy without notification of individual
exclusions being attached for review and acceptance.
2. Business Automobile Policy
■ Combined Single Limits: $500,000
■ Coverage for"Any Auto"
3. Workers' Compensation
■ Statutory Limits
• Employer's Liability: $500,000
• Waiver of Subrogation required.
4. Errors and Omissions
• Limit: $1,000,000 for this project
• For all architects, engineers, and/or design companies
■ Claims-made form is acceptable.
■ Coverage will be in force for one(1)year after construction of the Project is completed.
b. The following shall be applicable to all policies of insurance required herein.
1. Insurance carrier must have an A.M.Best Rating of B+:VIII or better.
2. Only insurance carriers licensed and admitted to do business in the State of Texas will be accepted.
3. Liability policies must be on occurrence form.
4. Each insurance policy shall be endorsed to state that coverage shall not be suspended,voided, canceled or
reduced in coverage or in limits except after thirty(30)days' prior written notice by certified mail, return
receipt requested,has been given to the City.
5. The City, its officers, agents and employees are to be added as Additional Insured to all liability policies.
6. Upon request and without cost to the City, a certified copy of all insurance polices and/or certificates of
insurance shall be furnished to the City.
7. Upon request and without cost to the City, loss runs(claims listing)of any and/or all insurance coverage's
shall be furnished to the City.
8. All insurance required herein shall be secured and maintained in a company or companies satisfactory to
the City,and shall be carried in the name of Contractor.
9. The Contractor shall comply with Section 110.110 of Title 28 of the Texas Administrative Code,which is
incorporated herein by this reference for all intents and purposes. However, it is expressly understood
and agreed that in the event of a conflict between the provisions of this section and the provision
13
City of Baytown,Texas
Hydro-Stop Roofing Projects
contained in Section 110.110 of Title 28 of the Texas Administrative Code, the more stringent shall
control
31. BONDING: Both the Contractor and the City agree that the Contractor will execute performance, payment
and maintenance bonds, each in the sum of one hundred percent (100%) of the total contract price, in standard
forms for this purpose, guaranteeing faithful performance of the contract, faithful performance of work during the
warranty period and faithful payment to all persons supplying labor and materials or furnishing any equipment in
the execution of the Agreement. It is agreed that this Contract shall not be in effect until such bonds are furnished
and approved by the City. The cost of the premium for the bonds have been included in the Contractor's quote.
The bonds shall be executed by the Contractor and by a corporate surety, the qualifications of which shall be as
required below. The bond required herein shall remain in effect throughout the term of this Agreement and for a
period of one (1) year after the completion of the work and shall be extended for any warranty work to cover the
warranty period. If at any time during the execution of this Agreement or in the required period thereafter,the bond
becomes invalid or ineffective for any reason, the Contractor shall promptly supply within ten(10) days such other
bond, which bond shall assure payment as required. Such replacement bond(s) shall be issued by a surety
acceptable to the City.
Changes and alterations in the work herein contemplated, or any part thereof, does not affecting the validity of this
Agreement and any accompanying bond.
32. PROJECT UNDER CONTRACTOR'S CONTROL: Any injury or damage caused to the Contractor or the
project prior to and including the date of fmal completion caused by an act of God, natural cause, a party or entity
not privy to this Agreement,or other force majeure shall be assumed and borne by the Contractor.
33. COMPLIANCE WITH LAWS: Contractor shall comply with all Federal and State laws and City Ordinances
and Codes applicable to the Contractor's operation under this contract. Violations will be corrected at
Contractor's expense. The Contractor will pay for all applicable royalties, permits, and license fees and defend
all suits and claims of infringements of any rights.
34. SAFETY PRECAUTIONS: Safety precautions at the site are a part of the construction techniques and
processes for which the Contractor shall be solely responsible. The Contractor is solely responsible for handling
and use of hazardous materials or waste, and informing employees of any such hazardous materials or waste.
The Contractor has the sole obligation to protect or warn any individual of potential hazards created by the
performance of the work set forth herein. The Contractor shall, at its on expense, take such precautionary
measures for the protection of persons,property and the work as may be necessary. The safety of the public and
convenience of traffic shall be regarded as prime importance during construction.
a) During normal construction, the Contractor shall not hinder or inconvenience travel of streets or intersecting
alleys for more than two blocks at any one time. The Contractor shall use warning signs as necessary to
adequately protect the traffic. If the City or other appropriate entity approves a street closure, the Contractor
shall furnish and maintain at each end of the closed section,at all intersecting streets within the section,and in
all intersecting streets at a distance of one block on each side of the work, properly worded signs and
barricades announcing the closure to the public. The Contractor shall not be allowed to start any operation
that will close a street or streets until the required barricades are in place. Barricades and warning signs shall
meet the specifications as shown in the plans and/or specifications. Warning lights shall be kept burning from
sunset to sunrise. When a street is to be closed,the Contractor must notify the City's Engineering and Public
Works Departments 48 hours in advance of the closure.
b) The Contractor shall remove, as soon as practicable, accumulated rubbish, surplus dirt, etc., from the
construction site,thereby opening each block for public use. Use by the public, however, of any portion of a
street where work has been done, shall not constitute in itself acceptance of the work done therein. The
Contractor shall backfill and shape trenches across street intersections or driveways to permit safe usage at
night. If trenches must be left open for any length of time, the Contractor shall span with wooden mats or
bridges to permit traffic flow and prevent injury to the public. When driveways are cut, the City may direct
14
City of Baytown,Texas
Hydro-Stop Roofing Projects
the immediate placement of mats for ingress and egress of vehicles if, in the City's Representative or City's
opinion,undue hardship to property owners would otherwise result.
c) The Contractor shall not block ditches, inlets, fire hydrants, etc. The Contractor shall provide temporary
drainage where necessary or as directed by the City's Representative or the City.
d) When persons or equipment are working in streets open to moving traffic, or if otherwise ordered by the
City's Representative, the Contractor shall furnish flagmen for direction of traffic to protect both the moving
traffic and the Contractor's operations. The flagmen.shall wear an orange fluorescent vest over their normal
work clothes.
The Contractor shall be held responsible for all damages to property, personal injuries and/or death due to failure
to use safety devices of any type or nature that may be required to protect or warn any individual of potential
hazards created by the performance of the work; and when any property damage is incurred,the damaged portion
shall immediately be replaced or compensated for by the Contractor at its own cost and expense.
35. RELEASE: By this Agreement, the City does not consent to litigation and expressly revokes any consent to
litigation that it may have granted by the terms of this Agreement, any charter, or applicable state law. The
Contractor assumes full responsibility for the work to be performed and releases, relinquishes, and discharges the
City, its officers, agents and employees from all claims,demands and causes of action of every kind and character
for any injury to, including, but not limited to, death of any person (whether third persons, the Contractor, or
employees of either of the parties). This release includes the cost of defense of any claim and any loss of or
damage to property (whether property of the parties or of third parties) that is caused by or alleged to be caused
by, arising out of, or in connection with the Contractor's work to be performed under this Agreement whether or
not said claims,demands, and causes of action are covered in whole or in part by insurance.
36. INDEMNITY AGREEMENT:
THE CONTRACTOR HEREBY AGREES TO AND SHALL INDEMNIFY, HOLD
HARMLESS, AND DEFEND THE CITY, ITS OFFICERS, AGENTS AND
EMPLOYEES FROM AND AGAINST ANY AND ALL CLAIMS, LOSSES,
DAMAGES, DEMANDS, CAUSES OF ACTION, SUITS AND LIABILITY OF EVERY
KIND, INCLUDING ALL EXPENSES OF LITIGATION, COURT COSTS AND
ATTORNEYS' FEES, FOR INJURY TO OR DEATH OF ANY PERSON, FOR LOSS
OF USE OR REVENUE, OR FOR DAMAGE TO ANY PROPERTY ARISING OUT
OF OR IN CONNECTION WITH THE ACTUAL OR ALLEGED MALFUNCTION,
DESIGN OR WORKMANSHIP IN THE MANUFACTURE OF EQUIPMENT, THE
FULFILLMENT OF CONTRACT, OR THE BREACH OF ANY EXPRESS OR
IMPLIED WARRANTIES UNDER THIS CONTRACT. SUCH INDEMNITY SHALL
APPLY WHERE THE CLAIMS, LOSSES, DAMAGES, CAUSES OF ACTION, SUITS
OR LIABILITY ARISE IN PART FROM (I) THE JOINT NEGLIGENCE OF THE
CITY AND THE CONTRACTOR,. AND/OR THEIR RESPECTIVE OFFICERS,
AGENTS AND/OR EMPLOYEES OR (II) THE SOLE NEGLIGENCE OF THE
CONTRACTOR, ITS OFFICERS, AGENTS AND EMPLOYEES. IT IS THE
EXPRESSED INTENTION OF THE PARTIES HERETO, BOTH CONTRACTOR
AND THE CITY, THAT THE INDEMNITY PROVIDED FOR IN THIS PARAGRAPH
IS INDEMNITY BY CONTRACTOR TO INDEMNIFY AND PROTECT THE CITY
FROM THE CONSEQUENCE OF (I) THE CITY'S OWN NEGLIGENCE WHERE
THAT NEGLIGENCE IS A CONCURRING CAUSE WITH THAT OF THE
CONTRACTOR OF THE INJURY, DEATH OR DAMAGE AND/OR (II) THE
CONTRACTOR'S OWN NEGLIGENCE WHERE THAT NEGLIGENCE IS THE
15
City of Baytown,Texas
Hydro-Stop Roofing Projects
SOLE CAUSE OF THE INJURY, DEATH, OR DAMAGE. FURTHERMORE, THE
INDEMNITY PROVIDED FOR IN THIS PARAGRAPH SHALL HAVE NO
APPLICATION TO ANY CLAIM, LOSS, DAMAGE, CAUSE OF ACTION, SUIT
AND LIABILITY WHERE IN INJURY, DEATH OR DAMAGE RESULTS FROM
THE SOLE NEGLIGENCE OF THE CITY UNMIXED WITH THE FAULT OF ANY
OTHER PERSON OR ENTITY. IN THE EVENT ANY ACTION OR PROCEEDING
IS BROUGHT AGAINST THE CITY BY REASON OF ANY OF THE ABOVE, THE
CONTRACTOR AGREES AND COVENANTS TO DEFEND THE ACTION OR
PROCEEDING BY COUNSEL ACCEPTABLE TO THE CITY. THE INDEMNITY
PROVIDED FOR HEREIN SHALL SURVIVE THE TERMINATION OR
EXPIRATION OF THIS AGREEMENT.
37. ABANDONMENT: In case the Contractor should abandon, fail or refuse to resume work within ten (10) days
after written notification from the City or the City's Representative, or if the Contractor fails to comply with the
orders of the City or the City's Representative, when such orders are consistent with the Contract Documents,
then,and in that case,where performance and payment bonds exist,the sureties on these bonds shall be notified in
writing and directed to complete the work, and a copy of said notice shall be delivered to the Contractor. After
receiving said notice of abandonment, the Contractor shall not remove from the work any machinery, equipment,
tools, materials, or supplies then on the job, but the same, together with any materials and equipment under
contract for the work, may be held for use on the work by the City or the surety on the performance bond, or
another Contractor in completion of the work; and the Contractor shall not receive any rental or credit therefor, it
being understood that the use of such equipment and materials will ultimately reduce the cost to complete the
work and be reflected in the fmal settlement.
38. BREACH OF CONTRACT: The City shall have the right to declare the Contractor in breach of this Agreement
for cause when the City determines that this Agreement is not being performed according to its understanding of
the intent and meaning of this Agreement. Such breach shall not in any way invalidate, abrogate or terminate the
Contractor's obligation under this Agreement.
39. TERNIINATION: If this Agreement is terminated for cause, the City shall have the right but shall not be
obligated to complete the work either itself or by others; and to this end, the City shall be entitled to take
possession of and use such equipment and materials as may be on the job site and to exercise all rights, options
and privileges of the Contractor under its subcontracts, purchase orders or otherwise; and the Contractor shall
promptly assign such rights, options, and privileges to the City. If the City elects to complete the work itself or by
others, pursuant to the foregoing, then the Contractor will reimburse the City for all costs incurred by the City's
Representative, (including, without limitation, applicable, general and administrative expenses, and field
overhead, and the cost of necessary equipment, materials and field labor) in correcting work by the Contractor
that fails to meet the requirements of the Contact Documents.
After receipt of a notice of termination, whether with or without cause, the Contractor shall, in good faith and to
the best of its ability, do all things necessary in light of such notice to assure the efficient and proper close-out of
the terminated work(including, but not limited to,the protection of the City's property). Among other things the
Contractor shall, except as otherwise directed or approved by the City, do the following:
a) Stop the work on the date and to the extent specified in the notice of termination;
b) Place no further orders or subcontracts for services, equipment, or material, except as may be necessary for
completion of such portion of the work as is not terminated;
c) Immediately terminate all orders and subcontracts to the extent that they relate to the performance of the work
terminated by the notice of termination;
d) Assign to the City, in the manner and to the extent directed by it, all of the right, title and interest of the
Contractor under the orders or subcontracts so terminated in which case, the City shall have the right to settle
or pay any or all claims arising out of the termination of such orders and subcontracts;
16
City of Baytown,Texas
Hydro-Stop Roofing Projects
e) With the approval of the City, settle all outstanding liabilities and all claims arising out of such termination,
orders and subcontracts;
f) Deliver to the City, when directed by the City, all documents and all property, which if the work had been
completed, the Contractor would have been required to account for or deliver to the City, and transfer title to
such property to the City to the extent not already transferred; and/or
g) Take actions necessary or as otherwise directed by the City's Representative or the City for the protection and
preservation of the work.
In the event of such termination, there shall be an equitable reduction of the Payment Amount to reflect the
reduction in the work. Costs incurred after the effective date of the notice of termination shall not be treated as
reimbursable costs unless they relate to carrying out the unterminated portion or taking close-out measures.
40. TERMINATION FOR CAUSE: Without prejudice to any other legal or equitable right or remedy that the City
would otherwise possess hereunder or as a matter of law,the City, upon giving the Contractor five(5) days' prior
written notice, shall be entitled to terminate this Agreement in its entirety at any time for the following:
a) If the Contractor becomes insolvent, commits any act of bankruptcy, makes a general assignment for the
benefit of creditors, or becomes the subject of any proceeding commenced under any statute or law for the
relief of debtors;
b) If a receiver,trustee or liquidator of any of the property or income of the Contractor shall be appointed;
c) If the Contractor shall fail to prosecute the work or any part thereof with diligence necessary to ensure its
progress and completion as prescribed by the time schedules;
d) If within five (5) calendar days after written notice thereof from the City or the City's Representative, the
Contractor shall fail to remedy any defective work or work that does not conform to the requirements of this
Agreement, specifications, and other Contract Documents, or any other default under any of the terms,
provisions, conditions, or covenants contained in this Agreement or any other current agreement between the
Contractor and another City for similar construction work on other property; or
e) If the Contractor shall fail for any reason other than the failure by the City to make payment called upon when
due.
In the event of such termination for cause, the Contractor shall only be paid its reimbursable costs incurred prior
to the effective date of the termination and shall not be entitled to receive any further payment hereunder and shall
be further subject to any claim that the City's Representative or the City may have against the Contractor under
the provisions of this Agreement or as a matter of law, including the refund of any overpayments of reimbursable
costs or other payments.
41. TERMINATION FOR CONVENIENCE: The performance of the work may be terminated at any time in
whole or in part, by the City's Representative for its convenience. Any such termination shall be effected by
delivery to the Contractor of a written notice (notice of termination) specifying the extent to which performance
of the work is terminated and the date upon which termination becomes effective. If, for whatever reason, this
contract is terminated for cause, which is later determined not to exist, the parties agree that the contract will be
deemed to be terminated for convenience. In the event of termination for convenience, the Contractor shall only
be paid its reimbursable costs incurred prior to the effective date of the termination notice and shall not be entitled
to receive any further payment hereunder and shall be further subject to any claim the City may have against the
Contractor under other provisions of this Agreement or as a matter of law, including the refund of any
overpayment of reimbursable costs and/or other payment.
42. COMPLETION AFTER ABANDONMENT OR TERMINATION: In the event that the Contractor has
abandoned the project or the City has terminated the contract for cause and where there is no performance bond
provided or where there is a surety but such surety, within seven (7) calendar days after the notice demanding
completion is sent, fails to commence the completion and diligent prosecution of the work in compliance with this
Agreement, then the City may AT ITS OPTION provide for completion of the work in either of the following
elective manners:
a) The City may employ such force of men and use such machinery, equipment,tools, materials, and supplies as
said City may deem necessary to complete the work and charge the expense of such labor, machinery,
equipment, tools, materials, and supplies to said Contractor, and expense so charged shall be deducted and
17
City of Baytown,Texas
Hydro-Stop Roofing Projects
paid by the City out of such monies as may be due, or that may thereafter at any time become due to the
Contractor under and by virtue of this Agreement. In case such expense is less than the sum which would
have been payable under this contract, if the same had been completed by the Contractor,then said Contractor
and/or its surety hereby waives any and all privileges, rights, and claims to receive the difference. In case
such expense is greater than the sum which would have been payable under this contract, if the same had been
completed by said Contractor, then the Contractor and/or its surety shall, within seven(7) calendar days, pay
the amount of such excess to the City.
b) The City, under sealed bids, after notice published as required by law at least twice in a newspaper having
general circulation in the city, may let the contract for the completion of the work under substantially the
same terms and conditions which are provided in this contract. In case any increase in cost to the City under
the new contract as compared to what would have been the cost under this contract, such increase shall be
charged to the Contractor and the surety shall be and remain bound therefor. However, should the cost to
complete any such new contract prove to be less than what would have been the cost to complete under this
contract, the Contractor and/or its surety hereby waives any and all privileges, rights and claims to such
excess.
In the event of abandonment by the Contractor, the Contractor shall assign to the City, in the manner and to the
extent directed by the City, all of the right, title, and interest of the Contractor in and to any and all materials
located on the property and any subcontracts for work to be performed on the property; in which case the City
shall have the right to settle or pay all claims arising out of the termination of such orders and subcontracts.
43. DAMAGES: Without prejudice to any other legal or equitable right or remedy that the City would otherwise
possess hereunder or as a matter of law, the City upon giving the Contractor five (5) days' prior written notice
shall be entitled to damages for breach of contract,upon but not limited to the following occurrences:
a) If the Contractor shall fail to remedy any default after written notice thereof from the City or the City's
Representative;or
b) If the Contractor shall fail for any reason other than the failure by the City to make payments called upon
when due; or
c) If the Contractor commits a substantial default under any of the terms, provisions, conditions or covenants
contained in this Agreement.
44. INVALIDITY: If any provision of this Agreement shall be held to be invalid, illegal or unenforceable by a court
or other tribunal of competent jurisdiction, the validity, legality and enforceability of the remaining provisions
shall not in any way be affected or impaired thereby. The parties shall use their best efforts to replace the
respective provisions or provisions of this Agreement with the legal terms and conditions approximating the
original intent of the parties.
45. ENTIRE AGREEMENT: It is understood that this Agreement contains the entire agreement between the parties
and supersedes any and all prior agreements, arrangements or understandings between the parties relating to the
subject matter. There are no oral understandings, statements, promises or inducements contrary to the terms of
this Agreement. This Agreement cannot be changed or terminated orally. No verbal agreement or conversation
with any officer, agent, representative or employee of the City, either before or after the execution of this
Agreement, shall affect or modify any of the terms or obligations hereunder.
46. AMENDMENT: No amendments to this Agreement shall be effective and binding until they are reduced to
writing and signed by duly authorized representatives of both parties.
47. TEXAS LAW: This Agreement has been made under and shall be governed by the laws of the State of Texas.
48. PLACE OF PERFORMANCE: The place of making and the place of performance for all purposes shall be
Baytown,Harris County,Texas.
49. NON-WAIVER: Failure of any party, at any time, to enforce a provision of this Agreement shall in no way
constitute a waiver of that provision, nor in any way affect the validity of this Agreement or part hereof or the
18
City of Baytown,Texas
Hydro-Stop Roofing Projects
right of the City or the City's Representative thereafter to enforce each and every provision hereof. No term of
this Agreement shall be deemed waived or breach excused unless the waiver shall be in writing and signed by the
party claimed to have waived the same. Furthermore, any consent to or waiver of a breach will not constitute
consent to or waiver of or excuse of any other different or subsequent breach. Nothing contained in this
Agreement or any of the Contract Documents shall be deemed to limit or waive the sovereign immunity of the
City
50. HEADINGS: The article headings are used in this Agreement for convenience and reference purposes only and
are not intended to define,limit or describe the scope or intent of any provision of this Agreement and shall have
no meaning or effect upon its interpretation.
51. GENDER AND NUMBER: Words of any gender used in this Agreement shall be held and construed to include
any other gender, and words in the singular number shall be held to include the plural, and vice versa, unless
context requires otherwise. -
52. CONSTRUCTION OF AGREEMENT: The parties agree that this Agreement shall not be construed in favor
of or against any party on the basis that the party did or did not author this Agreement.
53. AUTHORITY TO ENTER CONTRACT: Each party has the full power and authority to enter into and
perform this Agreement, and the person signing this Agreement on behalf of each party has been properly
authorized and empowered to enter into this Agreement. The persons executing this Agreement hereby represent
that they have authorization to sign on behalf of their respective corporations and/or business entities.
54. AGREEMENT READ: The parties acknowledge that they have read,understand and intend to be bound by the
terms and conditions of this Agreement.
55. ASSIGNMENT: Contractor may not assign or otherwise transfer this Agreement or any rights or obligations
hereunder without the prior written consent of the City.
56. SUCCESSORS AND ASSIGNS: This Agreement shall inure to the benefit of and be binding upon the
Contractor and its successors and assigns.
57. MULTIPLE ORIGINALS: It is understood and agreed that this Agreement may be executed in a number of
identical counterparts each of which shall be deemed an original for all purposes.
58. SEVERABILITY: If any section,subsection,paragraph, sentence,clause,phrase or word of these requirements
or specifications shall be held invalid,such holding shall not affect the remaining portions of these requirements
and the specifications and it is hereby declared that such remaining portions would have been included in these
requirements and the specifications as though the invalid portion had been omitted.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement in multiple copies, each o hich
shall be deemed to be an original, but all of which shall constitute but one and the same Agreement on the day of
January ,2013,the date of execution by the City Manager of the City of Baytown.
GENERAL CONTRACTOR S RVICES,INC.
(Signature)
Pamela Teltschick
(Printed Name)
President
(Title)
19
City of Baytown
Hydro-Stop Roofing Projects
CITY OF BAYTOWN
ass
AST: �
OBERT D.LEIPER,City Mana er
/ Lirdc,`��r".0.
LETIC :IPY5CH rity"erk•�
,4
APPROVED rS'TQ,FORM:
ACIO RAMIREZ,SR.,Ci orney
STATE OF Texas §
§
COUNTY OF Harris §
Before me on this day personally appeared Pamela Teltschick , in his/her capacity as
President of General Contractor Services,Inc.,on behalf of such corporation,
+/ known to me;
proved to me on the oath of ;or
proved to me through his/her current {description of
identification card or other document issued by the federal government or any state government that
contains the photograph and signature of the acknowledging person)
(check one)
to be the person whose name is subscribed to the foregoing instrument,and acknowledged to me that he/she executed that
instrument for the purposes and consideration therein expressed.
Given under my hand and seal of office this7th day of January_ 2013.
o'nr!y= MARYANN TILLSON / _" -
_ . VI Notary Public,State of Texas No • Pub "c in and for the State of Texas
My Commission Expires
%;;;tore a February 15, 2015
My co a ii. sion expires: February 15, 2015
20
P.AIIIVENTSOND:
caumrtiop
.....:.
•••KNOW..•: ALL itilEN :,13.Y• THESE PRESENT& That •i]q0:rr0x•:•ea,;:p.ori.txadtoi,.:.:Ser.tr.ie.e:g,:,:
of :the City of Houston County of
Harris •..
and State of Tza .... as principal,:: -and
The Guarantee Company of North Airterica USA ••••:-
•i • ••••••• .:•-•-• •• •••••••••••••...,-- authonzed under the laws i.athei.:State
of Texas to act us surety on bonds for are held and bound unto
City of Baytown A
(Owner);: surd of
flight Hwidred ..Ior'ty itve Ihousand . . „
whereof the said Principal
ilatf::Sta..etybindithemse eirheirs,.,:a ors. e'wcutors,:successors and,assigusjoint Tan severally by
these presents
WHEREAS g\OL
.hdncipa1 has::entere nto a certain written cofltract with the Owner dated the ......
day of ,( 44fLL1,r
„ contract..............,........ referred. ...... ........
-,to which
is
ereby
part hereof
as yand•-,to::thhame exten4s if copied atlengthhereuv
'•.,•NOW. .THEREPOREi-THECONI7ITIONOP.:THES,:ipEtVATION'TsS400;thatIf 0004itt:Ptilioh)4vt141 **:a11.
claimants supplying labor and material tdif:diilliiiM:itiiit6tiieliiithipreSentirtrittriftheiWodrvioilidetttkiitiairttontract::...:...... ...........:....:....
Then,this obligation shall be void,otherwise:tatemainin?Ml force.:411 Oct
PRQVIDO:VHOVitArE tt::lhififiiitiiiiii•'U'ikitited:pursuantliiitlie:provision.Tof Chapter 2253-iiiif Texas Government
Code as amended and all liabilities on this lond shall be deternirned as accordance with the provisions of said Chapter to
the:.saineextent•tts,if it werwCopied:titlengthhereim
.
Surety for value received,stipulates ar&agreethattio:.Changeextensiortlit time,alterationor addition to
the contract, or to the work performed thereunder, or the plans,specifications or drawings accornpanyrng the same,shall
in anywise affbct its oblietiou on this bond, and it does hereby waive notice of any,sUchchange.-.:..exteaSzorkiot
alteektin.Oeedrittinifth.;:thelettriki;.-oftheCOritritet;i:Cettithe*Orkteilie*ifferinedtherefindek:::
•
IN WITNESS WHEREOF, the said Principal and Surety have signed and scaled this instrument this
�P day of At ,20 1 .
The Guarantee Company of
General Contractor Services, Inc. North America USA
Principal Surety
By N2r Gt s.e, By
Kevin Quain
Title .0 e2�7` Title Attorney-'n-Fact
Address 8400 LaPorte Road Address 12600 Northborough, Suite 190
Houston, TX 77012 Houston, TX 77067
The name,address,and telephone number of the Resident Agent of Surety is:
Ag States Agency, LLC dba CHS Surety
200 Valleywood Dr. , Ste. B100, The Woodlands, TX 77380
„•
. .
Bond 'No. 700.-18'..36'-,a.0::
'.-PERFORIVIANCE130NR.
:::::::::::...: .......:. :,......:,.:::........... ...-.. ........,.........:
STA TROFTE)CAS. : —
...:: -
§:
.:...COUNTY..-.0f.::-.,f...::. ,:-: • .: .g ,
KNO.7y1A14Viqa11:8Y::-..-a7f-f.Esa:.0-RES.ENTS'..--:: tiii--..-::'0';i' -' 1•J--::::C6.i.ii.'6;:6-:6;$iq .;46e,'0 ::-,,.."...-; 6;'i •ti'f- the•CitY:'-:bi
Ti,.9:4p-.0t-i.":--.-:•: ::<::-i:::::::":::.::::":.".....":.::":....:.-"..... .."...•.:.-":...":::"":".'..."'..::"::::.:•:,:-:::::-.--.. C--:-:tb.un:ty - '-t....,.....,„ .::.„„.Harris...:....—L
:'.an....t .tOte Of
Tie.Cupyapte0zcompany of: North :::-....::.,::: :,::
•.,.......:..::7...c.?ca.:0 .. .... .• .. .........•..• ••••••:.-.-,,-...es...,piincii...fal:;aiid• America USA •.,. ...;•-••-:','',-',.•:---•... . ..•:••.. .. ,-:-...„itiuthtititddi,tildee-:.
. ........„..,„:...„,„:„.........„,„„::::::„„„.„.„„„:„, .„....„:„.„,„„.:......... ..„..........
:,„ .•• .,.. •::..„-........; .........„:"....5..... :;:- ::::::::................••„..„:„ :.:.,..:-. „.....:.:..... ' - ::.... -•-• ' .. "„....::”- ....:::
tti ..:-:ia*i.:.-Ot thtStAte::tif:-.".7rdka§ tii.:-.:•act bC': titdiY):;bii:'!.F50iid '..-jftitioi.kiiriOlii410'',.4i-dhitliFdftig,fiiilY- iiiiiiiid :iitifiiiiheitSi::-"6f.
.-.•••,...„ :•:: ....... ....--... „„ .... .......• :. .... ...,.. iidif'..051.:-.P.dity"„-':',$'1itii"0:•1140,.4iiitt-„.-• Dollars(Owner),)14yl-OWilirTexo..5iiiliii ..-tEiidVgkii*iof ±hre.6--;:_11iiiiiii-6-11:.:::t,iiiiidti :,:-aiiit ::'46.ittrti-,-.:,::: ',(g#4P(?):-99')
•-• .
fcit•tlfp4yinierit::::8vhdteoft0:1ai4:...PrinCipat::•:.and Surety bind ther'n-tiVestnd:•'ttielt--.',:bdies-:•::::atirn in itcrat tirS,,•,,,:tkdtiitoit,
:-.:.66gdr ..:6ii0.-"-.0. jgr-:.'4:,-.10i0IY,"':4,04!-:.50-041;i:,1b.ytii--*.pii..-$.-o4(:..ij',
... . .. .,., ......,.., ,.....:„ .„...... ............ : .......... .. ... ............ .......,... ....., .................„,... .: .,.:, :: ........_. ....... ... ....,,,... ...„.
-wprg .,:4s; the T..!rpci.p4t :- entered 'lop 4....., coilain: •..-iy.ritt'co ]:co.ritraet -,wittv:.:thi :'-01wrker,'. dated the
clgoi
.,...„:.:....„...„ .........„ 1, ) ..,.. „.. ...::::...... ..... .. :.:: ....„.. :::. :::' .......„ ...........:: ,
'::::.....: . - •••.... day of..-- -- : . -.:,•'2a.....••,,,...•-.„.•••...-Icvmhichivontractis:herebYroferred'Io :•:•
anct,..71pder:(;(tiat.t:..h0feofo, :fuliyitiriatiji::the.',saitieekiC. at 1
.„..
. ,
. ,
NOW„.;:::::',THEREF-011E;TliE CONDITION OF T-1711SOBLIGAT;(:)NIS:SUC}ii::'thAt if the said Principal shall
if4iiii'f.01ly 00efifitiii:• aid Contract and.-... ligtItilt11- 00.001*:.-4ii1 -.'ii*1„--:!fothfii„...11y„:::tIbetife- titid:':::'ptlibtrii-411::-.-:ith 4.:'•iiiikii14i:.•Ahei.
....... ......... „............. ...... ...... .„. vv.-.•.••„.....• .....•.•-................................... ......................
..etiVdtlantSi.:t0tOttiOn$:::.anciggr'.ceiiionts'::.".iwalitt:Wgdidi„Contii.OAMOa-...-04::,.c.:ov„oiltiof0di:by....t.h&,piiii00.0:td:i.Tiobg6iii.t4'.:Aiid
perfoOned;-104:„4ccor.444itiiittiolt.04.i,iiitpr*01411104,ig.pf.4411.'.t.:._c0i#tactita*P;Atitind'$ti. eifi0AtfOij$::hOtetwAtiridd;
.. ....„... .... . . ..................... ........... ...... . .. ............
#10kitiyi$01)44100441140*.01(41:00004$040tekiiiitiliglifoi..:00„.:Atiitff6:0;
.- :.... -- ..-.....,...- .-.-- ...-
PROVIDED;..:}10WEVEI ;•-•iht':-..t.iiii,'Ijalid,.is-„-:„:ekeetitedliuisualt...::•:tothei,„"provislonsof.Chapter::•:2253.„':>„ol:-Texas
Government Code ai.:aniendct..ittct:1111 liabilities clnihis:-.,:bottikihAil,.",iie-detetitiiii0ii1W &Obtdafidi*ititlhtitoVi§liiiitif
......::: :.: :,:: :::::.:::::: ::::„.::- :,.:: ''': ''''" -..' •:: ,
saict.',.Cliapterlii::the'„--same„"................................................................. -.
..--- • •-•.. . - .•,-. -:,-• - ••• -.••..,. ... .: ...... ... -.•-•
... ...... . ..-...... .......i. . .....
Surety, fot..valtirdtdiVdcli::.--Sipi.11-.40$ 0,04•:_•4g-t.0.0$ tri,4v#44..:.01)0.)-1-tk...•0. addition*0.0$ioy•Ajifli.frjW4404'0100:;":0u. .to:;:ft
.,....,,,:•••••••:•-•••:.,:,--••••••-• ••:,„ „..••• •••-.•:•••:.„„...::::-.•••••••i••••• •---•-:••••i i•i••-•••••••••.••• •••••••••••••••••••••••••••••••••---••••••• •••••.••-•••••••••••••••••••- - --••••-
....... ....
....„...,.„,. •:.
terms of ihe, :titat4c -:„-..Cit.-.tii:''ti:i&*dilt:•.-tifdiiriCFthdf.-dtiiidOioe-thepliiii.-„, liddificaticins;.•,•ctr::drawings„-acaompanymg-lhe
•„,•••:•••„-_•••„-: ::::: . .:::::: :.:•-.....::-.„.•:.:-..:::•-.•-.-:,•„-•::-.•„„ :::: •-.:•::•:-.••••.„• -._ •,-..„•,!•!•:•:•::::::•.„.....:„.-:.::„.,-..2„::•,.-.•:„„•,•:•„„:„... „•_:.„.!•!•!•:.•!•!!•„::„..i......_.„_,.,...-.:_:......::•••........: .-... .............
te
s
Saiii0-;•..SpAlti"..-.1ii:,„.4.0y,wo.k„'.efeat itCi131:i'Stion•„'-ti&thi -„-lititid,„.--. fid:it'does!bei-.0t*Oii*ijatC.Oi•otif:-.:keiitt..--,-0.0g0;0xte010 :-.0.f. , ... .;..:..... .;.;.;• ;;.;.. .......;.:. ..;...;.;; ......... ;;;.; . ......... ;......;;;;; ... ...;... ;.......:. ......... ........
:.:Iiillk:altetatiotiitiadclitionp:i:::thq] Fra „c i f ti*4044-4etioljcil.0.)0::,wciiiip]:b#:-.p'efformeci!tboi704tidet.
„,„:::,...„...„.„.„...:.......: ..„.....„.:.:.:.: ...........,::.:...„.:....:.....„, .._.,,,:.,:.:.:.:..„:„.:.:....,..,....... ......,,,...„.:., .........:...:.:.„..:<.:.:......,..... ......::...:.:.....:.„....,...........„.:„. ..„„.„.„.„.:.:.:.,.:.:.:.:.:.„.„.. .......„.,...„...„.„,.:.
...Rx79j .pV:„ ..:::':''jiydr.o....T'Stop ;•,TRootl.;-.4q, .:P.x!.9jep.. for Baytown :1'':iur.);.4p..,p'4,1i: S0,Kmtg0.-... Center
'..city Hall Annex alit:L"iiuseuta-,aild Sterling Municipal Libraryrand'..'vtiIity... .......
-.:-..... ...
Billing Building
1
IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this instrument this
�P day of / 4-0,,,-'t.�r1 C1 ,20 f a_ .
General Contractor Services, Inc. The Guarani0 p. y of North. America USA
PRINCIPAL — SURET /�
/�
BY: /���/Y�`1PnL'- 1�1C1C1,C'J�t�e.GC Bv'
/ Kevi McQuain
Title: kuo„,Q 4 j eL Title: Attorney-in-Fact
Address: 8400 LaPorte Road Address: 12600 Northborough, Suite 190
Houston, TX 77012 Houston, TX 77067
The name and address of the Resident Agent of Surety is:
Ag States Agency, LLC dba CHS Surety
200 Valleywood Dr. , Ste. B100, The Woodlands, TX 77380
2
Bond No. 70083G00
MAINTENANCE BONtic
STAT .:OFT.EXAS-1
COUNTY OF
. . . ....... . ............... .
KNOW ALL
MEN BY PRESENTS : General Contractor rvice3, IC.
as Principal, hereinafter called "Contractor" and the other subscriber hereto
. .
as Surety, do hereby acknowledge ourselves to be held and
firmly bound to the .
City:: sum of
ighL Hunared Forty Five Thousand
••• • ..
Three llur.dred Ninety and 00/ .00 DOLLARS ( 845,390.00 ) for the payracnt of which
sum well and truly to be made to the City of Baytown and its successors,the said Contractor and Surety do bind
themselves,
. ,
their heirs,......... .........,administrators,successors . jointly and severally.TIlE CONDITIONS OF THIS OBLIGATION ARE SUCU flEAT:
V}IEREAS. the Contractor has on or about this day executed a Contiact in writing with the City of
•
Baytown for the Hydra-Stop Roofing Projects and all of such work to be done as set out in full in said Contract
Documents therein referred to and adopted by the City
ll of which are made a part of this instrument
.......
as fully and completely as if set out in full herein.
NOW THEREFORE, if the said Contractor shall comply with the provisions of the Contract
Documents:',A1:::::cleftried...hilhAge.ternent; and correct Work not in accordance with the Contract Documents
discovered*ithi#Ii*-.-.004blisboot*otaiittperiod,then this obligation shall become null and void,and shall be
of no further force and effect;otherwise,the same is to remain in full force and effect.
Surety,for value received,stipulates and agrees that .•
t6thangetidetisiditoftliiieialt6iatioitbe4dditiom
to the terms of the contract, or to the work performed thereunder, or the plans, specifications, or drawings
. . .......... ................ ................. ...............
4cqompq0yIng:::t4e,!*mjeoliajt"-.:..4y..anyw0,r.affect.jWqb.lig*i0wp4:.-Itiktilio'cL and it 4004.::herotly:•7kai*:.#0.000i.f.::
......._
any sich change, extension
of time, alteration or addition to the terms of the contract, or to the work to he
pqrforthett:thereunder
® IN WITNESS WHEREOF, the said Principal and Surety have signed and scaled this instrument this
(a day of k!(4/Yy6,1
The Guarantee Company of
General Contractor Services, Inc. North America USA
Principal S e ty
By ��' 13 ,
Kevin Mc rain
Title 4Ap,.2P,y"t.,._ Title Attorney-in-Fact
Address 8400 LaPorte Road 12600 Northborough, Suite 190
Address
Houston, TX 77012 Houston, TX 77067
The name and address of the Resident Agent of Surety is:
Ag States Agency, LLC dba CHS Surety
200 Valleywood Dr. , Ste. B100
The Woodlands, TX 77380
2
AGREEMENT
BETWEEN CITY AND CONTRACTOR
FOR USA GENERAL SERVICES ADMINISTRATION PURCHASE
STATE OF TEXAS
COUNTY OF HARRIS
THIS AGREEMENT is entered into by and between the City of Baytown (the "City") and General Contractor
Services,Inc.(the"Contractor")for the Hydro-Stop Roofmg Projects detailed herein.
1. SCOPE OF WORK: This scope of work shall entail the complete turnkey construction of roofmg at the
following locations:
a. Baytown Municipal Service Center at 2123 Market Street,Baytown,Texas;
b. City Hall Annex and Museum at 2200 W. Defee,Baytown,Texas;
c. Sterling Municipal Library at Mary Elizabeth Wilbanks Avenue,Baytown,Texas; and
d. Baytown Utility Billing at 2505 Market,Baytown,Texas.
The turnkey job will consist of all necessary parts, materials, equipment, freight, delivery, installation, labor,
travel time, mileage, cleanup, and any other related costs to complete the above-referenced roofmg projects
together with design and inspection services by a professional engineer licensed in the state of Texas (the
Work"). The work includes a ten-year renewable warranty for each building and shall include, but not be
limited to the following:
Services Cost Not to Exceed
Baytown Municipal Service Center
Foam Roof —Middle Section—East Side
Remove existing blisters throughout entire roof
Power wash entire roof surface to remove dirt and contaminates
Apply Hydro-Stop Barrier Guard into voids to level substrate
Apply ten(10)year Hydro-Stop Premium Roof System over entire roof 78,925.00
surface,leaving existing foam system in place
Install 12 permanent one way vents at designed areas to allow any
captured moisture to escape from beneath system
Modified Roof—West Side
Power wash entire roof surface to remove dirt and contaminates
Apply ten(10)year Hydro-Stop Premium Roof System over entire roof
surface
Install base coat with reinforcing fabric layer 97,881.00
Detail all transitions and flashings with base coat and fabric
Install intermediate coat of Hydro-Stop"Premium Coat"over base coat
Install intermediate coat of Hydro-Stop"Premium Coat"to complete the
system
Engineering Services provided by TSI Services,LLC
Review manufacturer's procedure for installation of fully adhered Hydro-
Stop roof covering to existing modified bitumen and foam roof based on
130 mph 3 second gust design pressure 1,500.00
Provide inspection services to document contractor's adherence to
manufacturer's required installation method
City Hall Annex and Museum
Hydro-Stop Premium Roof Coat System
Remove loose gravel from entire roof surface
Apply Hydro-Stop Barrier Guard at low areas to level
Install Dens Deck Recovery Board onto entire roof surface using heavy 179,832.00
duty fasteners
Install tapered insulation using heavy duty fasteners at areas between roof
drains to divert water.
City of Baytown,Texas
Hydro-Stop Roofing Projects
Apply Hydro-Stop Premium Foundation Coat onto entire roof surface
Embed Hydro-Stop Reinforcement Fabric and apply second layer of
foundation coat
Apply two(2)layers of Hydro-stop Premium Finish coat onto entire roof
surface
Install metal counter flashing at lower roof edge and encapsulate with
fabric and finish coat
Engineering Services provided by TSI Services,LLC
Review City-provided existing roof drawings and provide the following
engineering services:
Installation design drawings of Iso-Board and Hydro-Stop roof
covering based upon 130 mph 3 second gust design pressure 2,500.00
Witness fastener pull-out testing and verify fastener spacing and
selection to meet design pressures
Based upon selection of an approved installation method,drawings
specific to the services rendered will be stamped
Perform 4 to 5 individual windstorm inspections 1,500.00
Sterling Municipal Library
Hydro-Stop Premium Roof Coat System
Remove loose gravel at small modified roof surface
Power wash entire single ply roof surface
Install Dens Deck Recovery Board onto modified roof surface using
heavy duty fasteners
Apply Hydro-Stop Premium Foundation Coat onto entire roof surface 407,423.00
Embed Hydro-Stop Reinforcement Fabric into foundation coat and apply
second layer
Apply two(2)layers of Hydro-Stop Premium Finish coat onto entire roof
surface
Engineering Services provided by TSI Services,LLC
Review roof drawings provided by the City to design fastener spacing
and review manufacturer's installation procedure for installation over
modified bitumen
Fastener spacing of Iso-Board installation over Video Section of Library
only
Hydro-stop roof covering entire roof including Video Section as well as
modified bitumen 3,500.00
Fastener spacing design and fully adhered specifications based on 130
mph 3 second gust design pressure
Witness fastener pull-out testing and verify fastener spacing and selection
to meet design pressures
Based on selection of an approved installation method,drawings specific
to services rendered will be stamped.
Perform 4 to 5 individual windstorm inspections 1,500.00
Baytown Utility Billing
Hydro-Stop Premium Roof Coat System
Remove existing loose gravel from roof surface.
Attach dens deck board onto roof using fasteners through metal roof pan.
Attach roof edge metal flashing. 60,351.00
Apply Hydro-Stop Premium Roof Coat System onto entire roof surface.
Apply walk path material onto roof to A/C Equipment.
Engineering Services provided by TSI Services,LLC
Review City-provided existing roof drawings,if any,and provide the 2,500.00
following engineering services:
Installation design drawings of Iso-Board and Hydro-Stop roof
2
City of Baytown,Texas
Hydro-Stop Roofing Projects
covering based upon 130 mph 3 second gust design pressure
Witness fastener pull-out testing and verify fastener spacing and
selection to meet design pressures
Based upon selection of an approved installation method,drawings
specific to the services rendered will be stamped
Perform 4 to 5 individual windstorm inspections
Bonds and Insurance
Performance Bond
Payment Bond
7,978.00
Maintenance Bonds
Insurance
Total Cost Not to Exceed 845,390.00
Such services shall be performed for a cost not to exceed EIGHT HUNDRED FORTY-FIVE THOUSAND
THREE HUNDRED NINETY AND NO/100 DOLLARS($845,390.00)based upon the pricing schedule
from GSA#GS-07F5988R included hereinbelow:
563-4 PremiumCoat Fabric 4" 2004-004 28.50
563-4 PremiumCoat Fabric 6" 2004-006 32.28
563-4 PremiumCoat Fabric 8" 2004-008 39.36
563-4 PremiumCoat Fabric 12" 2004-012 57.18
563-4 PremiumCoat Fabric 16" 2004-016 71.15
5634 PremiumCoat Fabric 20" 2004-020 87.98
563-4 PremiumCoat Fabric 24" 2004-024 104.19
563-4 PremiumCoat Fabric 40" 1000 ftLapped 2004-040 162.91
5634 Pre-Cut PremiumCoat Fabric 40" 2005400 10.21
5634 PremiumCoat Foundation Coat 40 ft/gallon 2002-001 33.51
5634 PremiumCoat Foundation Coat 2002-005 133.68
5634 PremiumCoat Finish Coat Battleship Grey- 1 gallon 70 ftgallon 2003-041 40.59
5634 PremiumCoat Finish Coat Battleship Grey-5 gallon 70 flgallon 2003-045 154.60
5634 PremiumCoat Finish Coat Brown-1 gallon 70 ftgallon 2003-071 40.59
563-4 PremiumCoat Finish Coat Brown-5 gallon 70 ftgallon 2003-075 154.92
563-4 PremiumCoat Finish Coat Charcoal-1 gallon 70 ft gallon 2003-021 S40.59
5634 PremiumCoat Finish Coat Charcoal-5 gallon 70 ftgallon 2003-025 154.92
5634 PremiumCoat Finish Coat Cotton -1 gallon 70 ftgallon 2003-121 40.59
5634 PremiumCoat Finish Coat Cotton-5 gallon 70 ftgallon 2003-125 154.92
5634 PremiumCoat Finish Coat Charleston Green—1 gallon 70 flgalIon 2003-061 40.59
5634 PremiumCoat Finish Coat Charleston Green—5gallon 70 ftgallon 2003-065 154.92
5634 PremiumCoat Finish Coat Desert Sand—1 gallon 70 ftgallon 2003-101 40.59
5634 PremiumCoat Finish Coat Desert Sand-5 gallon 70 ftgallon 2003-105 154.92
5634 PremiumCoat Finish Coat Patina Green-1 gallon 70 ftgallon 2003-051 40.59
5634 PremiumCoat Finish Coat Patina Green-5 gallon 70 ftgallon 2003-055 154.92
5634 PremiumCoat Finish Coat Terra Cotta-1 gallon 70 ftgallon 2003-081 40.59
5634 PremiumCoat Finish Coat Terra Cotta-5 gallon 70 ft gallon 2003-085 154.92
5634 Premium<:oat Finish Coat Timers Red- 1 gallon 70 ftgallon 2003-091 40.59
5634 PremiumCoat Finish Coat Timers Red-5 gallon 70 ftgallon 2003-095 154.92
5634 PremiumCoat Finish Coat Dove Grey-1 gallon 70 ftgallon 2003-031 40.59
3
City of Baytown,Texas
Hydro-Stop Roofing Projects
i Product Nmue Coverage Item#GSA Price
563-4 PremiumCoat Finish Coat Dove Grey-5 gallon 70 ft2 gallon 2003-035 154.92
5634 PremiumCoat Finish Coat White-1 gallon 70 egallon 2003-011 40.16
5634 PremiumCoat Finish Coat White-5 gallon 70 flgallon 2003-015 150.02
5634 PremiumCoat Deep Tone Base(White)- 1 gallon 70 l gallon 2002-100 34.85
5634 PremiumCoat Deep Tone Base()White)-5 gallon 70 ftgallon 2002-500 146.79
5634 PremiumCoat Deep Tone Base(tinted)-1 gallon 70 f gallon 2002-100 40.59
TINT
5634 PremiumCoat Deep Tone Base(tinted)-5 gallon 70 8,gallon 2002-500 154.92
TINT
563-29 Brush-Flashing 4"-5 gallon 9010-004 3.11
563-29 Brush Hand Roof 4" 9011-002 4.10
563-29 Brush 6"Roof 9010-006 4.26
563-29 Brush 10"Roof 9010-010 7.98
563-29 Brush Handle 9011-001 5.72
563-29 Roller-9"Roller Frame 9050-001 5.24
563-29 Roller Cover 1 1/4 Nap 9055-001 2.62
563-29 Roller Handle 60" 9060-001 6.41
563-29 HydroFiber-5 gallon TBA 1100-800 40.10
563-29 HydroCaps-box 1296/box 1100-500 124.74
563-29 Pail Opener 9012-001 22.24
563-29 Rilem Test Tube 10000-001 52.25
563-29 24"Push Broom 9040-001 17.87
563-29 BarrierGuard-1 gallon 50-60 if/gallon 4000-001 46.79
563-29 BarrierGuard-5 gallon 4000-005 168.69
563-29 Clearguard Plus-1 gallon 80-200 l/gallon 5002-001 34.15
563-29 Clearguard Plus-5 gallon 5002-005 170.76
563-29 Flexcoat-White-1 gallon 180 f/gallon 3000-001 34.95
563-29 Flexcoat -White-5 gallon 3000-005 122.29
563-29 Flexcoat-White Tint Base-TINTED 180 l/gallon 3000-011 39.10
563-29 Flexcoat-White Tint Base-TINTED 3000-015 136.03
563-29 Flexcoat-Tinted- 1 gallon 180 l/gallon 3000-021 34.95
563-29 Flexcoat-Tinted-5 gallon 3000-025 122.29
563-29 Flexcoat-Deep Tone Base-TINTED 180 l/gallon 3000-031 39.10
563-29 Flexcoat-Deep Tone Base-TINTED 3000-035 136.03
563-4 C1eanAct-EPDM- 1 gallon 200 f/gallon 2010-001 33.40
563-4 C1eanAct-EPDM-5 gallon 2010-005 152.90
5634 Stablerust Primer- 1 gallon 200 WIgallon 2001-001 49.19
5634 Stablerust Primer-5 gallon 2001-005 195.87
5634 Surebond Primer- 1 gallon 200 l/gallon 2000-001 30.71
5634 Surebond Primer-5 gallon 2000-005 108.96
5634 Traffic Coat-White- 1 gallon 125 l/gallon 1000-001 42.51
5634 Traffic Coat-White-5 gallon 1000-005 173.25
563-4 Traffic Coat-Deck Grey- 1 gallon 125 l /gallon 1000-011 42.51
5634 Traffic Coat-Deck Grey-5 gallon 1000-015 173.25
5634 Traffic Coat-Deck Tan-1 gallon 125 f/gallon 1000-016 42.51
5634 Traffic Coat-Deck Tan-5 gallon 1000-017 173.25
5634 Traffic Coat- Slate Grey-1 gallon 125 ft/gallon 1000-018 42.51
5634 Traffic Coat- Slate Grey-5 gallon 1000-019 173.25
4
City of Baytown,Texas
Hydro-Stop Roofing Projects
2.CONTRACT DOCUMENTS: The contract documents shall consist of the following documents, which are
listed in the order of priority of interpretation should there be a conflict:
a) Addenda to this Agreement,
b) Agreement,
c) Plans, if any,
d) Technical Specifications,and
e) Performance,Payment and Maintenance Bonds.
No amendments to this Agreement shall be effective and binding until it is reduced to writing and signed by the
duly authorized representatives of both parties. Contract Documents shall be distributed by the Contractor to its
subcontractors as necessary and must be kept and be accessible at the work site. The plans and specifications
must be returned to the City on request at the completion of the work.
3.CITY'S REPRESENTATIVE: The project shall be administered by the City's Representative, whose duties
shall include,but not be limited to,the following:
a) periodically review and inspect the Contractor's work;
b) issue instructions and directives to the Contractor, with which Contractor is obligated to comply,
provided such directions and instructions are consistent with the obligations of this Agreement;
c) make visits to the site at intervals appropriate to the various stages of construction, appropriate to
observe as an experienced and qualified design professional the progress and quality of the Work; and
d) keep City informed of the progress of the Work.
4.COMMUNICATIONS: The Contractor shall forward all communications, written or oral,to the City through
the City's Representative. Written notice shall be deemed to have been duly served if delivered in person to the
individual or to a member of the firm or to an officer of the corporation for whom it is intended, or if delivered
at or sent by telecopier, overnight or facsimile transmission or if delivered or sent by certified or registered mail
to the last business address as indicated herein. Each party will have the right to change its business address by
giving at least thirty (30) calendar days' written notice to the other party of such change. Notice given by mail
shall be deemed given three(3)calendar days after the date of the mailing thereof.
5.COMMENCEMENT AND COMPLETION OF WORK: Once the bonds and the certificate of insurance
have been submitted to and approved by the City, the Contractor shall perform the work in the most expedient
manner possible. The work shall commence as soon as possible,but no later than ten (10)calendar days of the
date specified in the notice to proceed. Engineering design services shall be completed within twenty (20)
calendar days of the date specified in the notice to proceed. Completion of the construction services shall be
within one hundred eighty (180) calendar days of the date specified in the notice to proceed. Time is of the
essence in this Agreement and the date of beginning and the date for final completion of work as specified in
this Agreement are essential conditions of this Agreement. Contractor has submitted its quote in full recognition
of the time required for the completion of this Work taking into consideration all factors, including, but not
limited to, the average climatic range, industry conditions, and liquidated damages. At final completion of the
Work,a certificate of final completion shall be issued by the Director of Engineering.
6.WORK. The Contractor shall complete the work described in the contract documents in strict conformity
therewith. The Contractor shall:
a) provide and pay for all materials, supplies, machinery, equipment, tools, superintendents, laborers,
insurance, fuel, transportation, and all other facilities and utilities necessary for the execution and
completion of the Work;
b) secure and pay all permits, fees, licenses, and inspections necessary for the proper execution and
completion of the work;
5
City of Baytown,Texas
Hydro-Stop Roofing Projects
c) give all notices required by law and comply with all laws, ordinances, regulations, codes, rules and
lawful orders of all public authorities bearing on the performance of the work;
d) pay sales,consumer,use and similar taxes as legally required;and
e) provide shop drawings and schedules to the City's Representative and secure the City's
Representative's approval of the same, which approval shall not relieve Contractor from responsibility
for errors.
7.EXTENSIONS AND DELAYS:
a) EXTENSIONS. Within seven (7) calendar days of any act or incident that the Contractor reasonably
believes may justify an extension of time for final completion, the Contractor may apply in writing for
an extension of such time, submitting therewith all written justification as may be required by City.
Thereafter, the City's Representative, within seven (7) calendar days after receipt of a written request
for an extension of time from the Contractor, which is supported by all requested documentation, shall
then grant or deny such written request; provided that the request for an extension is not based upon
weather conditions. Should an extension be requested within the seven (7) calendar-day period based
upon weather conditions, the CITY'S REPRESENTATIVE shall grant or deny such a written request
upon Final Completion of the Work based upon any variation from the average climatic range.
b) DELAYS. The Contractor, in undertaking to complete the work within the time herein fixed, has taken
into consideration and made allowance for all hindrances and delays incident to such work, whether
growing out of delays in securing material or workmen or weather or otherwise. No charge whatsoever
shall be made for hindrances or delays from any cause whatever, except where the work is stopped by
order of the City or by extraordinary causes. Any extension shall not exceed the time actually lost by
Contractor.
8.PAYMENT: The Contractor agrees to perform the Work for the unit prices specified herein, which the City
shall pay upon final completion and acceptance of the Work, subject to any adjustment allowed herein. The
Contractor shall never be entitled to anticipated or lost profits on the deleted or reduced portion of a job whether
bid on a unit price or lump sum basis. The Contractor shall not have the right to obligate the City to make any
payments to another party.
If the actual amount of the work to be done and the materials to be furnished differ from the estimate, then
payment shall be for the actual amount of accepted work done and materials incorporated into the project.
Reduction in the scope or quantity of work on unit price items shall merely reduce the number of units.
No changes shall be made and no bills for changes, alterations, modifications, deviations, and extra orders shall
be recognized or paid for except upon a written change order signed by the Contractor and the City. Any
change shall not affect the validity of any bonds. Any requests by the Contractor for a change in original
Payment Amount shall be made prior to the beginning of the work covered by the proposed change or the right
to payment for Extra Work shall be waived.
9.INDEPENDENT CONTRACTOR: In all activities or services performed hereunder, the Contractor is and at
all times shall remain an independent contractor, not an agent or employee of the City. The Contractor, as an
independent contractor, shall be solely responsible for the final product contemplated under this Agreement. It
shall be the responsibility of the Contractor to furnish a completed work product that meets the requirements of
the City. Any additional work, material, or equipment needed to meet the intent of this specification shall be
supplied by the Contractor without claim for additional payment,even though not specifically mentioned herein.
6
City of Baytown,Texas
Hydro-Stop Roofing Projects
10. DISORDERLY EMPLOYEES: The Contractor agrees to employ only orderly and competent persons, skillful
in the performance of the type of work required under this contract,to do the Work. The Contractor shall retain
personal control and shall give its personal attention to the faithful prosecution and completion of the work and
fulfillment of this Agreement. The Contractor shall appoint and keep on the project during the progress of the
Work a competent Project Superintendent-Manager and any necessary assistants, all satisfactory to City to
supervise its employees and subcontractors. Adequate supervision by Contractor is essential to the proper
performance of the Work, and lack of such supervision shall be grounds for suspending the operations of the
Contractor and declaring Contractor in breach of this Agreement. Whenever the City or the City's
Representative shall inform the Contractor in writing that any person or persons performing any of the requisite
work are, in the opinion of the City or the City's Representative, incompetent, unfaithful or disorderly, such
person or persons shall be discharged and shall not again be employed to perform any work on the project
without prior written consent of the City or the City's Representative.
11. NATURE OF THE WORK: It is understood and agreed that the Contractor has, by careful examination,
satisfied itself as to the nature and location of the work, the confirmation of the ground and soil, the nature of
any structures, including surface and subsurface utilities,the character, quality and quantity of the material to be
utilized, the character of equipment and facilities needed for and during the prosecution of the work, the time
needed to complete the work, Contractor's ability to meet all deadlines and schedules required by this
Agreement, the general and local conditions, and all other matters that in any way affect the work under this
Agreement.
12. PROGRESS OF WORK: The Contractor may prosecute its work at such time and sessions, in such order of
precedence, and in such manner as shall be most conducive to the economy of the project; provided; however,
that the order and time of prosecution shall be such that the work shall be finally completed as a whole, in
accordance with this Agreement. Further,the parties shall be subject to the following:
a) The City reserves the right to enter the property by such employee(s) or agent(s) as it may elect for the
purpose of inspecting the work;
b) The Project Superintendent/Manager shall coordinate its activities and work with the City. If required
by the City, the Contractor shall provide a weekly schedule of planned activities, which may be
reviewed on a daily basis. In the case of any completed work or material that is to be covered over by
other material,the Project Superintendent/Manager shall provide notice to the City no later than twenty-
four (24) hours before the anticipated cover-up of the previously completed work or material. In the
event, however, that such notice is provided on a Friday the City will have until the following Monday
afternoon to approve the previously completed work and its cover-up and the Contractor shall take no
action until such approval is given by City;
c) The Contractor shall submit,at such time as may reasonably be requested by City,further schedules that
shall list the order in which the Contractor proposes to carry on the work with dates at which the
Contractor will start the several parts of the work and the estimated dates of completion of the several
parts; and
d) The Contractor shall attend additional meetings called by the City or the City's Representative upon
twenty-four(24)hours' notice unless otherwise agreed by the parties.
13. SITE CONDITIONS AND MANAGEMENT: Throughout the progress of the work,the Contractor shall keep
the working area free from debris of all types, and remove from premises all rubbish, resulting from any work
being done by it. At the completion of the work, the Contractor shall leave the premises in a clean and finished
condition. Any failure to do so may be remedied by the City or its designee and charged back to the Contractor.
Where the Contractor is working around or in existing structures, it shall verify conditions at the site, including,
but not limited to, roads, easements, door openings, passages, and other existing site conditions. Any items
constructed or manufactured off-site or outside of buildings shall be done so that they are not too bulky for
7
City of Baytown,Texas
Hydro-Stop Roofing Projects
existing facilities. The Contractor shall provide special apparatus as required to handle any such items. All
special handling equipment charges shall be at the Contractor's sole cost and expense.
Where gas,water, and sewer lines exist in the vicinity,the Contractor shall assume that service connections exist
to each building and exercise appropriate caution during excavation. It is the Contractor's responsibility to
notify various owners in advance when excavation is to be done in the vicinity of their underground lines and
structures. Damage to such underground lines and structures, whether or not shown on the plans, shall be the
responsibility of the Contractor and it shall bear the cost of necessary repair or replacement of damaged parts.
The Contractor shall be responsible for verifying all conditions at the site prior to performing the Work. As
such, the Contractor understands and agrees that it shall be responsible for conditions encountered at the site,
including, but not limited to, (i) subsurface or otherwise concealed physical conditions which differ from those
indicated in the Contract Documents, and (ii) unknown physical conditions, which differ from those ordinarily
found to exist and generally recognized as inherent in construction activities of the character provided for in the
Contract Documents. No additional compensation shall be afforded to the Contractor for differing site
conditions. Any information provided by the City, including, but not limited to geotechnical information, shall
be for the Contractor's convenience only and the City does not guarantee the accuracy or correctness of any
information so provided.
14. LAYOUT OF WORK: The Contractor shall lay out all work in a manner acceptable to the City in accordance
with applicable codes and ordinances of the city, county and state. The City's Representative will review the
Contractor's layout of all structures and any other layout work done by the Contractor, but this review does not
relieve the Contractor of the responsibility of accurately locating all work in accordance with the specifications
and Contract Documents.
15. CONTRACTOR'S STRUCTURES: Whenever the Contractor erects, installs, or uses additional structures on
the property for the storage, maintenance of materials or use of employees and subcontractors, such structure
shall not damage the property and the Contractor shall maintain sanitary conditions in and about such structures
at all times in a manner satisfactory to the City. The Contractor shall provide and maintain necessary sanitary
conveniences for the use of laborers on the work. Such conveniences shall be properly secluded from public
observation and shall be in a location approved by the City's Representative. The City may charge the
Contractor for any damage or injury to the City, its property or third persons as a result of the location or use of
any of Contractor's structures.
16. MATERIALS:
a) Materials or work described in words which when so applied have well-known technical or trade meaning shall be
held to refer to such recognized standards. All work shall be done and all materials furnished in strict conformity
with the Contract Documents and recognized industry standards.
b) Materials and supplies utilized in the final product that will be turned over to the City shall be new and of
good quality. Upon request,the Contractor shall supply proof of quality and manufacturer.
c) No refurbished, reconditioned or other previously utilized materials or supplies will be used without the
signed authorization of the City.
d) Where the product is to be turned over to the City,the Contractor may utilize substitutes of equal quality and
function as provided for in the specifications.
e) The City shall have full and final decision over the use of substitute materials and supplies.
f) The Contractor shall certify to the City that all materials installed are free from asbestos containing material.
17. OBSERVATION.INSPECTIONS.TESTS:
a) The City and the City's Representative reserve the right to enter the property by such employee(s) or
agent(s) as he may elect for the purpose of inspecting the work. In accordance therewith, the Contractor
8
City of Baytown,Texas
Hydro-Stop Roofing Projects
shall supply the City or the City's Representative,upon request, with any keys or information necessary for
the City or the City's Representative to have access to the property. The City and the City's Representative
shall have the right to enter the property or location of the work for the purpose of performing such
collateral work as the City or the City's Representative deems necessary or appropriate.
b) The City and the City's Representative shall have the right, at any reasonable time, to observe and test the
work. The Contractor shall make necessary arrangements and provide proper facilities and access for such
observation and testing at any location wherever the work or any part thereof is in preparation or progress.
The Contractor shall ascertain the scope of any observation that may be contemplated by the City or the
City's Representative and shall give ample notice as to the time each part of the work will be ready for such
observation.
c) The City or the City's Representative may reject any work found to be defective or not in accordance with the
Contract Documents, regardless of the state of its completion or the time or place of its discovery regardless
of whether the City or the City's Representative has previously accepted the work through oversight or
otherwise. Neither observations by the City or the City's Representative nor inspections, tests, or approvals
made by the City or the City's Representative, or persons authorized under this Agreement to make such
inspections, tests, or approvals, shall relieve the Contractor from its obligation to perform the work in
accordance with the requirements of the Contract Documents.
d) The City or the City's Representative upon approval of the City may require the Contractor to remove,
dismantle or uncover work completed. In the event that the Contractor has failed to perform the work as
required by the specifications,or drawings,or other Contract Documents,Contractor shall assume and pay the
costs of repair and restoration of the work required to be removed, dismantled,or uncovered. In the event that
the Contractor has performed the work correctly to specifications, City shall assume and pay the cost of
restoration of the construction to the point that the City has required the work to be uncovered or dismantled.
18. WORK STOPPAGE: The City or the City's Representative shall have the right to order the work of the
Contractor or any subcontractor wholly or partially stopped immediately under any one or more of the following
conditions:
a) the work may be ordered stopped immediately if in the judgment of the City or the City's Representative, any
of the materials furnished or the work being done is not in strict accordance with this Agreement;
b) the work may be ordered stopped immediately until any objectionable person or material is removed from the
premises;or
c) the work may be ordered stopped immediately if any portion of the work is being performed so as to create a
hazardous condition.
Such stoppage or suspension shall neither invalidate any of the Contractor's performance obligations under this
Agreement, including time of performance and deadlines therefor,nor will extra charge be allowed the Contractor
by reason of such stoppage or suspension.
19. REJECTED WORK: The City or the City's Representative, in its discretion,may reject any and all work that is
found to be defective or deemed not in conformity with this Agreement. The City or the City's Representative
may reject said work or any portion thereof regardless of the stage of its completion or time or place of discovery
of such errors. Further, the City or the City's Representative may reject said work regardless of whether the City
or the City's Representative has previously accepted the work through oversight or otherwise. Neither
observations by the City or the City's Representative nor inspections, tests, certificates or approvals made by the
City or the City's Representative, or persons authorized under this Agreement to make such inspections, tests,
certificates or approvals, shall relieve the Contractor from its obligation to perform the work in accordance with
the requirements of this Agreement and the other Contract Documents. In the event that any work or any part
thereof is rejected by the City or the City's Representative, the Contractor shall, at its sole expense and after
receipt of written notice thereof from the City or the City's Representative remove such material and rebuild or
otherwise remedy such work so that it shall be in full compliance with this Agreement and the other Contract
Documents,as follows:
a) At the option of the City, the Contractor may be required to remedy such work so that it shall be in full
compliance with this Agreement. As soon as possible but not later than seven(7) calendar days after receipt
of notice from the City or the City's Representative or such other period of time specified by the City's
9
City of Baytown,Texas
Hydro-Stop Roofing Projects
Representative in writing, the Contractor shall, at its sole expense, replace or repair all rejected work or
materials so as to conform with this Agreement.
b) If the City or the City's Representative in its discretion deems it inexpedient to correct work damaged or not
done in accordance with this Agreement,an equitable deduction for the Payment Amount may be made by the
City.
c) If the Contractor does not remove or replace any rejected work within the time specified in Section in
subsection (a) hereof, then the City or the City's Representative may have the work removed, replaced or
repaired at the Contractor's expense.
20. SUBCONTRACTORS: The Contractor shall retain personal control and give its personal, utmost attention to
the faithful prosecution and completion of the work and fulfillment of this Agreement. The subletting of any
portion or feature of the work or materials required in the performance of this Agreement shall not relieve the
Contractor from its obligations to the City under this Agreement. All subcontractors must be approved by the
City's Representative prior to performing any work on the Project. If the City's Representative judges any
subcontractor to be failing to perform the work in strict accordance with the drawings and specifications, the
Contractor shall discharge the same, but this shall in no way release the Contractor from its obligations and
responsibility under this Agreement. Every subcontractor shall be bound by the terms and provisions of this
Agreement as far as applicable to its work. The Contractor shall be fully responsible to the City and the City's
Representative for the acts and omissions of its subcontractors.
The Contractor shall be solely and exclusively responsible for compensating any of the Contractor's employees,
subcontractors, materialmen and/or suppliers of any type or nature whatsoever. The Contractor shall further be
exclusively responsible for ensuring that no claims or liens of any type are filed against any property owned by
the City arising out of or incidental to the performance of any services performed pursuant to this Agreement. In
the event a statutory lien notice is sent to the City or the City's Representative, the Contractor shall, where no
payment bond covers the work, upon written notice from the City or the City's Representative, immediately
obtain bond at the Contractor's sole expense and hold the City harmless from any losses that may result from the
filing or enforcement of any said lien notice. In the event that the Contractor defaults in the provision of the bond,
the City may withhold such funds as are necessary to ensure the payment of such claim until litigation determines
to whom payment shall be made.
21. POSSESSION AND USE OF COMPLETED PORTIONS: The City shall have the right to take possession of
and use any completed or partially completed portions of the work, notwithstanding the time for completing the
entire work or such portions may not have expired, but such taking possession and use shall not be deemed an
acceptance of any work not completed in accordance with the Contract Documents.
22. PERMITS AND CERTIFICATES: The Contractor shall secure and pay for all necessary permits, licenses
and/or certificates issued by the state, municipality or other authorities and submit the same to the City's
Representative. The City may withhold any payments due under this Agreement or that may become due under
this Agreement until the necessary permits, licenses and/or certificates are procured and delivered. The
Contractor will not, however, be required to pay for any permit fees for permits to be issued by the City, which
will be waived in conjunction with this Agreement.
23. FAULTY WORKMANSHIP: Neither the final payment nor any acceptance nor certificate nor any provision of
this Agreement shall relieve the Contractor of any responsibility for faulty workmanship or materials. At the
option of the City, as provided in this Agreement,the Contractor shall remedy any defects thereto and pay for any
damage to other work resulting therefrom,which may appear after final acceptance of the work.
24. WARRANTY: Upon acceptance of the work by the City, the Contractor warrants for a period of ten (10)
calendar years from the date thereof that all materials provided to the City under this Agreement shall be new
unless otherwise approved in writing by the City's Representative and that all materials and work will be of good
quality, free from faults and defects, and in conformance with this Agreement. All work not conforming to these
requirements, including,but not limited to, substitutions not properly approved and authorized,may be considered
10
City of Baytown,Texas
Hydro-Stop Roofing Projects
defective. This warranty is in addition to any rights or warranties expressed or implied by law and consumer
protection claims arising from misrepresentations by the Contractor. Where a longer warranty is specified for
individual products, work or materials, the longer warranty shall govern. This warranty obligation shall be
covered by any performance or payment bonds tendered in compliance with this Agreement.
25. DEFECTIVE WORK DISCOVERED DURING WARRANTY PERIOD: If within ten (10) calendar years
after the date of acceptance by the City of designated equipment or within such longer period of time as may be
prescribed by law or by the terms of any applicable special warranty required by this Agreement, any of the work
is found or determined to be defective, including obvious defects, or otherwise not in accordance with this
Agreement,the Contractor shall correct it PROMPTLY.
a) After receipt of written notice from the City to begin corrective work,the Contractor shall promptly begin the
corrective work. This obligation shall survive the termination of this Agreement. The guarantee shall not
constitute the exclusive remedy of the City,nor shall other remedies be limited to either warranty or guarantee
period.
b) If within seven(7) calendar days after the City has notified the Contractor of a defect, failure or abnormality
in the work, the Contractor has not started to make the necessary corrections or adjustments, the City is
hereby authorized to make the corrections or adjustments, or to order the work to be done by a third party.
The cost of the work shall be paid by the Contractor.
c) The cost of all materials, parts, labor, transportation, supervision, special instruments, and supplies required
for replacement or repair of parts and for correction of defects, shall be paid by the Contractor or by the
surety.
d) The ten (10) calendar years warranty shall cover all work, equipment, and materials that are part of this
project,whether or not a warranty is specified in the individual section prescribing that particular aspect of the
work.
26. LIQUIDATED DAMAGES: It is expressly understood and agreed by the parties that time is of the essence to
this Agreement and that the date set for the final completion of the work described herein is an essential condition
of this Agreement. It is further understood and agreed that the date for final completion of the work is reasonable
dates for the completion of the project, taking into consideration all conditions, including, but not limited to, the
average climatic change and conditions and usual industrial conditions prevailing in this locality. If the
Contractor should neglect, fail, or refuse to complete the work required for final completion within the date
specified in this Agreement, or any proper extension that is granted in writing by the City, then the Contractor
hereby agrees, as a part of the consideration for the awarding of this Agreement, that the City may withhold
permanently from the Contractor's total Payment Amount the sum of FIVE HUNDRED AND NO/100
DOLLARS ($500.00) for each and every calendar day that the Contractor is in default after the date stipulated
for final completion, not as a penalty, but as liquidated damages for the breach of the Agreement. The amount of
liquidated damages for the Contractor's failure to meet the deadline for final completion is fixed and agreed on by
the Contractor because of the impracticability and extreme difficulty in fixing and ascertaining actual damages
that the City would in such an event sustain. The amounts to be charged are agreed to be the damages that the
City would sustain and may, at the option of the City, be retained from final payment or any other payment made
hereunder.
27. WITHHOLD PAYMENT AND CONTRACTOR'S PAYMENT: Regardless of any bond, the City may, on
account of subsequently discovered evidence,withhold payment or nullify the whole or part of any acceptance or
certificate to such extent as may be necessary to protect the City from loss on account of:
a) Defective work or work that is not in strict accordance with the terms of this Agreement, the Specifications,
or the other Contract Documents;
b) Claims filed or reasonable evidence indicating probable filing of claims, as determined at the sole discretion
of the City;
c) Failure of the Contractor to make prompt payments to subcontractors or for material or labor or materialmen;
d) Claims filed or reasonable evidence, as determined at the sole discretion of the City, of damage to another
Contractor or a third party, including adjacent property owners;
11
City of Baytown,Texas
Hydro-Stop Roofing Projects
e) Reasonable doubt, as determined at the sole discretion of the City, that the work can be completed for the
unpaid balance of the contract amount;
f) Reasonable indication, as determined at the sole discretion of the City, that the work will not be completed
within the contract time;
g) Liquidated damages and administrative charges,as determined by the City at its sole discretion;
h) Charges made for repairs to the Contractor's defective work or repairs made by the City to correct damage to
other property;
i) Claims filed or reasonable evidence as determined at the sole discretion of the City indicating unremedied
damage to property owned by the City; or
j) Other amounts authorized under this Agreement.
Whenever the Contractor and/or its surety is required to make a payment under this Agreement, it is expressly
understood and agreed that such payment shall be due within 15 days after receipt of an invoice therefore unless
expressly stated otherwise. Payments required by Contractor and/or its surety, which are not timely made, shall
accrue interest at a rate of one percent per month.
28. CHARGES FOR INJURY OR REPAIRS:
a) REPAIRS. The Contractor shall be liable and responsible for any damages incurred or repairs made
necessary by reason of its work and/or caused by it. Repairs of any kind required by the City or the City's
Representative will be made and charged to the Contractor by the City. The Contractor shall take the
necessary precautions to protect any areas adjacent to its work. The work specified consists of all work,
materials and labor required by the City or the City's Representative to repair any damage to the property of
the City, including,but not limited to, structures, roadways,curbs,parking areas and sidewalks,to an equal or
better condition than before such property was damaged.
b) INJURY. The Contractor shall at all times exercise reasonable precautions for the safety of employees and
others on or near the work and shall comply with all applicable provisions of Federal, State, and Municipal
safety laws and building and construction codes. All machinery and equipment and other physical hazards
shall be guarded in accordance with the "Manual of Accident Prevention in Construction" of the Associated
General Contractors of America except where incompatible with Federal, State, or Municipal laws or
regulations. The Contractor shall provide such machinery guards, safe walkways, ladders, bridges,
gangplanks, and other safety devices. The safety precautions actually taken and their adequacy shall be the
sole responsibility of the Contractor, acting at his discretion as an independent Contractor.
29. PAYMENT OF EMPLOYEES AND FOR MATERIALS: Wage rates paid on this project shall not be less
than specified in the schedule of general prevailing rates of per diem rates attached hereto as Exhibit "A" and
incorporated herein for all intents and purposes. Should the Contractor or any of its subcontractors fail to pay the
general prevailing rate to a worker performing work on the project, the Contractor shall pay to the City SIXTY
AND NO/100 DOLLARS ($60.00) for each worker employed for each calendar day or part of the day that the
worker is paid less than the wage rates stipulated in this Contract. The Contractor and each of the subcontractors
shall pay each of its employees engaged in work on the project under this Agreement in full(less mandatory legal
deductions), in cash or by check readily cashable, without discount, no less than once every two (2)weeks. The
City or City's Representative may, prior to final acceptance of the project, require the Contractor to execute an
affidavit in legal form stating that all bills for labor, materials, and incidentals incurred have been paid in full and
that there are no claims pending of which the Contractor has been notified.
30. INSURANCE REOUIREMENTS:
Contractor shall procure and maintain at its sole cost and expense for the duration of the Agreement, insurance
against claims for injuries to person or damages to property which may arise from or in connection with the
performance of the Work hereunder by Contractor, its agents, representatives, volunteers, employees or
subconsultants.
12
City of Baytown,Texas
Hydro-Stop Roofing Projects
a. Contractor's insurance coverage shall be primary insurance with respect to the City, its officials, employees
and agents. Any insurance or self-insurance maintained by the City, its officials,employees or agents shall be
considered in excess of Contractor's insurance and shall not contribute to it. Further,Contractor shall include
all subconsultants, agents and assigns as additional insured under its policy or shall furnish separate
certificates and endorsements for each such person or entity. All coverage's for subconsultants and assigns
shall be subject to all of the requirements stated herein.
The following is a list of standard insurance policies along with their respective minimum coverage amounts
required in this Agreement:
1. Commercial General Liability
General Aggregate: $2,000,000
Products&Completed Operations Aggregate: $2,000,000
Personal&Advertising Injury: $1,000,000
Per Occurrence: $1,000,000
Fire Damage: $300,000
Coverage shall be at least as broad as ISO CG 00 02 12 07
No coverage shall be deleted from standard policy without notification of individual
exclusions being attached for review and acceptance.
2. Business Automobile Policy
Combined Single Limits: $500,000
Coverage for"Any Auto"
3. Workers' Compensation
Statutory Limits
Employer's Liability: $500,000
Waiver of Subrogation required.
4. Errors and Omissions
Limit: $1,000,000 for this project
For all architects,engineers,and/or design companies
Claims-made form is acceptable.
Coverage will be in force for one(1)year after construction of the Project is completed.
b. The following shall be applicable to all policies of insurance required herein.
1. Insurance carrier must have an A.M. Best Rating of B+:VIII or better.
2. Only insurance carriers licensed and admitted to do business in the State of Texas will be accepted.
3. Liability policies must be on occurrence form.
4. Each insurance policy shall be endorsed to state that coverage shall not be suspended,voided, canceled or
reduced in coverage or in limits except after thirty (30)days' prior written notice by certified mail, return
receipt requested,has been given to the City.
5. The City, its officers, agents and employees are to be added as Additional Insured to all liability policies.
6. Upon request and without cost to the City, a certified copy of all insurance polices and/or certificates of
insurance shall be furnished to the City.
7. Upon request and without cost to the City,loss runs(claims listing)of any and/or all insurance coverage's
shall be furnished to the City.
8. All insurance required herein shall be secured and maintained in a company or companies satisfactory to
the City,and shall be carried in the name of Contractor.
9. The Contractor shall comply with Section 110.110 of Title 28 of the Texas Administrative Code,which is
incorporated herein by this reference for all intents and purposes. However, it is expressly understood
and agreed that in the event of a conflict between the provisions of this section and the provision
13
City of Baytown,Texas
Hydro-Stop Roofing Projects
contained in Section 110.110 of Title 28 of the Texas Administrative Code, the more stringent shall
control
31. BONDING: Both the Contractor and the City agree that the Contractor will execute performance, payment
and maintenance bonds, each in the sum of one hundred percent (100%) of the total contract price, in standard
forms for this purpose, guaranteeing faithful performance of the contract, faithful performance of work during the
warranty period and faithful payment to all persons supplying labor and materials or furnishing any equipment in
the execution of the Agreement. It is agreed that this Contract shall not be in effect until such bonds are furnished
and approved by the City. The cost of the premium for the bonds have been included in the Contractor's quote.
The bonds shall be executed by the Contractor and by a corporate surety, the qualifications of which shall be as
required below. The bond required herein shall remain in effect throughout the term of this Agreement and for a
period of one (1) year after the completion of the work and shall be extended for any warranty work to cover the
warranty period. If at any time during the execution of this Agreement or in the required period thereafter,the bond
becomes invalid or ineffective for any reason,the Contractor shall promptly supply within ten(10)days such other
bond, which bond shall assure payment as required. Such replacement bond(s) shall be issued by a surety
acceptable to the City.
Changes and alterations in the work herein contemplated, or any part thereof, does not affecting the validity of this
Agreement and any accompanying bond.
32. PROJECT UNDER CONTRACTOR'S CONTROL: Any injury or damage caused to the Contractor or the
project prior to and including the date of final completion caused by an act of God, natural cause, a party or entity
not privy to this Agreement,or other force majeure shall be assumed and borne by the Contractor.
33. COMPLIANCE WITH LAWS: Contractor shall comply with all Federal and State laws and City Ordinances
and Codes applicable to the Contractor's operation under this contract. Violations will be corrected at
Contractor's expense. The Contractor will pay for all applicable royalties, permits, and license fees and defend
all suits and claims of infringements of any rights.
34. SAFETY PRECAUTIONS: Safety precautions at the site are a part of the construction techniques and
processes for which the Contractor shall be solely responsible. The Contractor is solely responsible for handling
and use of hazardous materials or waste, and informing employees of any such hazardous materials or waste.
The Contractor has the sole obligation to protect or warn any individual of potential hazards created by the
performance of the work set forth herein. The Contractor shall, at its on expense, take such precautionary
measures for the protection of persons,property and the work as may be necessary. The safety of the public and
convenience of traffic shall be regarded as prime importance during construction.
a) During normal construction, the Contractor shall not hinder or inconvenience travel of streets or intersecting
alleys for more than two blocks at any one time. The Contractor shall use warning signs as necessary to
adequately protect the traffic. If the City or other appropriate entity approves a street closure, the Contractor
shall furnish and maintain at each end of the closed section, at all intersecting streets within the section,and in
all intersecting streets at a distance of one block on each side of the work, properly worded signs and
barricades announcing the closure to the public. The Contractor shall not be allowed to start any operation
that will close a street or streets until the required barricades are in place. Barricades and warning signs shall
meet the specifications as shown in the plans and/or specifications. Warning lights shall be kept burning from
sunset to sunrise. When a street is to be closed, the Contractor must notify the City's Engineering and Public
Works Departments 48 hours in advance of the closure.
b) The Contractor shall remove, as soon as practicable, accumulated rubbish, surplus dirt, etc., from the
construction site, thereby opening each block for public use. Use by the public, however, of any portion of a
street where work has been done, shall not constitute in itself acceptance of the work done therein. The
Contractor shall backfill and shape trenches across street intersections or driveways to permit safe usage at
night. If trenches must be left open for any length of time, the Contractor shall span with wooden mats or
bridges to permit traffic flow and prevent injury to the public. When driveways are cut, the City may direct
14
City of Baytown,Texas
Hydro-Stop Roofing Projects
the immediate placement of mats for ingress and egress of vehicles if, in the City's Representative or City's
opinion,undue hardship to property owners would otherwise result.
c) The Contractor shall not block ditches, inlets, fire hydrants, etc. The Contractor shall provide temporary
drainage where necessary or as directed by the City's Representative or the City.
d) When persons or equipment are working in streets open to moving traffic, or if otherwise ordered by the
City's Representative, the Contractor shall famish flagmen for direction of traffic to protect both the moving
traffic and the Contractor's operations. The flagmen shall wear an orange fluorescent vest over their normal
work clothes.
The Contractor shall be held responsible for all damages to property, personal injuries and/or death due to failure
to use safety devices of any type or nature that may be required to protect or warn any individual of potential
hazards created by the performance of the work; and when any property damage is incurred,the damaged portion
shall immediately be replaced or compensated for by the Contractor at its own cost and expense.
35. RELEASE: By this Agreement, the City does not consent to litigation and expressly revokes any consent to
litigation that it may have granted by the terms of this Agreement, any charter, or applicable state law. The
Contractor assumes full responsibility for the work to be performed and releases, relinquishes, and discharges the
City, its officers,agents and employees from all claims,demands and causes of action of every kind and character
for any injury to, including, but not limited to, death of any person (whether third persons, the Contractor, or
employees of either of the parties). This release includes the cost of defense of any claim and any loss of or
damage to property (whether property of the parties or of third parties) that is caused by or alleged to be caused
by, arising out of, or in connection with the Contractor's work to be performed under this Agreement whether or
not said claims,demands,and causes of action are covered in whole or in part by insurance.
36. INDENMM AGREEMENT:
THE CONTRACTOR HEREBY AGREES TO AND SHALL INDEMNIFY, HOLD
HARMLESS, AND DEFEND THE CITY, ITS OFFICERS, AGENTS AND
EMPLOYEES FROM AND AGAINST ANY AND ALL CLAIMS, LOSSES,
DAMAGES, DEMANDS, CAUSES OF ACTION, SUITS AND LIABILITY OF EVERY
KIND, INCLUDING ALL EXPENSES OF LITIGATION, COURT COSTS AND
ATTORNEYS' FEES, FOR INJURY TO OR DEATH OF ANY PERSON, FOR LOSS
OF USE OR REVENUE, OR FOR DAMAGE TO ANY PROPERTY ARISING OUT
OF OR IN CONNECTION WITH THE ACTUAL OR ALLEGED MALFUNCTION,
DESIGN OR WORKMANSHIP IN THE MANUFACTURE OF EQUIPMENT, THE
FULFILLMENT OF CONTRACT, OR THE BREACH OF ANY EXPRESS OR
IMPLIED WARRANTIES UNDER THIS CONTRACT. SUCH INDEMNITY SHALL
APPLY WHERE THE CLAIMS, LOSSES, DAMAGES, CAUSES OF ACTION, SUITS
OR LIABILITY ARISE IN PART FROM (I) THE JOINT NEGLIGENCE OF THE
CITY AND THE CONTRACTOR, AND/OR THEIR RESPECTIVE OFFICERS,
AGENTS AND/OR EMPLOYEES OR (II) THE SOLE NEGLIGENCE OF THE
CONTRACTOR, ITS OFFICERS, AGENTS AND EMPLOYEES. IT IS THE
EXPRESSED INTENTION OF THE PARTIES HERETO, BOTH CONTRACTOR
AND THE CITY, THAT THE INDEMNITY PROVIDED FOR IN THIS PARAGRAPH
IS INDEMNITY BY CONTRACTOR TO INDEMNIFY AND PROTECT THE CITY
FROM THE CONSEQUENCE OF (I) THE CITY'S OWN NEGLIGENCE WHERE
THAT NEGLIGENCE IS A CONCURRING CAUSE WITH THAT OF THE
CONTRACTOR OF THE INJURY, DEATH OR DAMAGE AND/OR (II) THE
CONTRACTOR'S OWN NEGLIGENCE WHERE THAT NEGLIGENCE IS THE
15
City of Baytown,Texas
Hydro-Stop Roofing Projects
SOLE CAUSE OF THE INJURY, DEATH, OR DAMAGE. FURTHERMORE, THE
INDEMNITY PROVIDED FOR IN THIS PARAGRAPH SHALL HAVE NO
APPLICATION TO ANY CLAIM, LOSS, DAMAGE, CAUSE OF ACTION, SUIT
AND LIABILITY WHERE IN INJURY, DEATH OR DAMAGE RESULTS FROM
THE SOLE NEGLIGENCE OF THE CITY UNMIXED WITH THE FAULT OF ANY
OTHER PERSON OR ENTITY. IN THE EVENT ANY ACTION OR PROCEEDING
IS BROUGHT AGAINST THE CITY BY REASON OF ANY OF THE ABOVE, THE
CONTRACTOR AGREES AND COVENANTS TO DEFEND THE ACTION OR
PROCEEDING BY COUNSEL ACCEPTABLE TO THE CITY. THE INDEMNITY
PROVIDED FOR HEREIN SHALL SURVIVE THE TERMINATION OR
EXPIRATION OF THIS AGREEMENT.
37. ABANDONMENT: In case the Contractor should abandon, fail or refuse to resume work within ten (10) days
after written notification from the City or the City's Representative, or if the Contractor fails to comply with the
orders of the City or the City's Representative, when such orders are consistent with the Contract Documents,
then,and in that case,where performance and payment bonds exist,the sureties on these bonds shall be notified in
writing and directed to complete the work, and a copy of said notice shall be delivered to the Contractor. After
receiving said notice of abandonment, the Contractor shall not remove from the work any machinery, equipment,
tools, materials, or supplies then on the job, but the same, together with any materials and equipment under
contract for the work, may be held for use on the work by the City or the surety on the performance bond, or
another Contractor in completion of the work; and the Contractor shall not receive any rental or credit therefor, it
being understood that the use of such equipment and materials will ultimately reduce the cost to complete the
work and be reflected in the final settlement.
38. BREACH OF CONTRACT: The City shall have the right to declare the Contractor in breach of this Agreement
for cause when the City determines that this Agreement is not being performed according to its understanding of
the intent and meaning of this Agreement. Such breach shall not in any way invalidate, abrogate or terminate the
Contractor's obligation under this Agreement.
39. TERMINATION: If this Agreement is terminated for cause, the City shall have the right but shall not be
obligated to complete the work either itself or by others; and to this end, the City shall be entitled to take
possession of and use such equipment and materials as may be on the job site and to exercise all rights, options
and privileges of the Contractor under its subcontracts, purchase orders or otherwise; and the Contractor shall
promptly assign such rights,options,and privileges to the City. If the City elects to complete the work itself or by
others, pursuant to the foregoing, then the Contractor will reimburse the City for all costs incurred by the City's
Representative, (including, without limitation, applicable, general and administrative expenses, and field
overhead, and the cost of necessary equipment, materials and field labor) in correcting work by the Contractor
that fails to meet the requirements of the Contact Documents.
After receipt of a notice of termination, whether with or without cause, the Contractor shall, in good faith and to
the best of its ability, do all things necessary in light of such notice to assure the efficient and proper close-out of
the terminated work(including, but not limited to, the protection of the City's property). Among other things the
Contractor shall,except as otherwise directed or approved by the City,do the following:
a) Stop the work on the date and to the extent specified in the notice of termination;
b) Place no further orders or subcontracts for services, equipment, or material, except as may be necessary for
completion of such portion of the work as is not terminated;
c) Immediately terminate all orders and subcontracts to the extent that they relate to the performance of the work
terminated by the notice of termination;
d) Assign to the City, in the manner and to the extent directed by it, all of the right, title and interest of the
Contractor under the orders or subcontracts so terminated in which case, the City shall have the right to settle
or pay any or all claims arising out of the termination of such orders and subcontracts;
16
City of Baytown,Texas
Hydro-Stop Roofing Projects
e) With the approval of the City, settle all outstanding liabilities and all claims arising out of such termination,
orders and subcontracts;
f) Deliver to the City, when directed by the City, all documents and all property, which if the work had been
completed, the Contractor would have been required to account for or deliver to the City, and transfer title to
such property to the City to the extent not already transferred; and/or
g) Take actions necessary or as otherwise directed by the City's Representative or the City for the protection and
preservation of the work.
In the event of such termination, there shall be an equitable reduction of the Payment Amount to reflect the
reduction in the work. Costs incurred after the effective date of the notice of termination shall not be treated as
reimbursable costs unless they relate to carrying out the unterminated portion or taking close-out measures.
40. TERNIINATION FOR CAUSE: Without prejudice to any other legal or equitable right or remedy that the City
would otherwise possess hereunder or as a matter of law,the City, upon giving the Contractor five(5)days' prior
written notice, shall be entitled to terminate this Agreement in its entirety at any time for the following:
a) If the Contractor becomes insolvent, commits any act of bankruptcy, makes a general assignment for the
benefit of creditors, or becomes the subject of any proceeding commenced under any statute or law for the
relief of debtors;
b) If a receiver,trustee or liquidator of any of the property or income of the Contractor shall be appointed;
c) If the Contractor shall fail to prosecute the work or any part thereof with diligence necessary to ensure its
progress and completion as prescribed by the time schedules;
d) If within five (5) calendar days after written notice thereof from the City or the City's Representative, the
Contractor shall fail to remedy any defective work or work that does not conform to the requirements of this
Agreement, specifications, and other Contract Documents, or any other default under any of the terms,
provisions, conditions, or covenants contained in this Agreement or any other current agreement between the
Contractor and another City for similar construction work on other property; or
e) If the Contractor shall fail for any reason other than the failure by the City to make payment called upon when
due.
In the event of such termination for cause, the Contractor shall only be paid its reimbursable costs incurred prior
to the effective date of the termination and shall not be entitled to receive any further payment hereunder and shall
be further subject to any claim that the City's Representative or the City may have against the Contractor under
the provisions of this Agreement or as a matter of law, including the refund of any overpayments of reimbursable
costs or other payments.
41. TERMINATION FOR CONVENIENCE: The performance of the work may be terminated at any time in
whole or in part, by the City's Representative for its convenience. Any such termination shall be effected by
delivery to the Contractor of a written notice (notice of termination) specifying the extent to which performance
of the work is terminated and the date upon which termination becomes effective. If, for whatever reason, this
contract is terminated for cause, which is later determined not to exist, the parties agree that the contract will be
deemed to be terminated for convenience. In the event of termination for convenience, the Contractor shall only
be paid its reimbursable costs incurred prior to the effective date of the termination notice and shall not be entitled
to receive any further payment hereunder and shall be further subject to any claim the City may have against the
Contractor under other provisions of this Agreement or as a matter of law, including the refund of any
overpayment of reimbursable costs and/or other payment.
42. COMPLETION AFTER ABANDONMENT OR TERMINATION: In the event that the Contractor has
abandoned the project or the City has terminated the contract for cause and where there is no performance bond
provided or where there is a surety but such surety, within seven (7) calendar days after the notice demanding
completion is sent,fails to commence the completion and diligent prosecution of the work in compliance with this
Agreement, then the City may AT ITS OPTION provide for completion of the work in either of the following
elective manners:
a) The City may employ such force of men and use such machinery, equipment,tools, materials, and supplies as
said City may deem necessary to complete the work and charge the expense of such labor, machinery,
equipment, tools, materials, and supplies to said Contractor, and expense so charged shall be deducted and
17
City of Baytown,Texas
Hydro-Stop Roofing Projects
paid by the City out of such monies as may be due, or that may thereafter at any time become due to the
Contractor under and by virtue of this Agreement. In case such expense is less than the sum which would
have been payable under this contract, if the same had been completed by the Contractor,then said Contractor
and/or its surety hereby waives any and all privileges, rights, and claims to receive the difference. In case
such expense is greater than the sum which would have been payable under this contract, if the same had been
completed by said Contractor, then the Contractor and/or its surety shall, within seven(7)calendar days, pay
the amount of such excess to the City.
b) The City, under sealed bids, after notice published as required by law at least twice in a newspaper having
general circulation in the city, may let the contract for the completion of the work under substantially the
same terms and conditions which are provided in this contract. In case any increase in cost to the City under
the new contract as compared to what would have been the cost under this contract, such increase shall be
charged to the Contractor and the surety shall be and remain bound therefor. However, should the cost to
complete any such new contract prove to be less than what would have been the cost to complete under this
contract, the Contractor and/or its surety hereby waives any and all privileges, rights and claims to such
excess.
In the event of abandonment by the Contractor, the Contractor shall assign to the City, in the manner and to the
extent directed by the City, all of the right, title, and interest of the Contractor in and to any and all materials
located on the property and any subcontracts for work to be performed on the property; in which case the City
shall have the right to settle or pay all claims arising out of the termination of such orders and subcontracts.
43. DAMAGES: Without prejudice to any other legal or equitable right or remedy that the City would otherwise
possess hereunder or as a matter of law, the City upon giving the Contractor five (5) days' prior written notice
shall be entitled to damages for breach of contract,upon but not limited to the following occurrences:
a) If the Contractor shall fail to remedy any default after written notice thereof from the City or the City's
Representative;or
b) If the Contractor shall fail for any reason other than the failure by the City to make payments called upon
when due;or
c) If the Contractor commits a substantial default under any of the terms, provisions, conditions or covenants
contained in this Agreement.
44. INVALIDITY: If any provision of this Agreement shall be held to be invalid, illegal or unenforceable by a court
or other tribunal of competent jurisdiction, the validity, legality and enforceability of the remaining provisions
shall not in any way be affected or impaired thereby. The parties shall use their best efforts to replace the
respective provisions or provisions of this Agreement with the legal terms and conditions approximating the
original intent of the parties.
45. ENTIRE AGREEMENT: It is understood that this Agreement contains the entire agreement between the parties
and supersedes any and all prior agreements, arrangements or understandings between the parties relating to the
subject matter. There are no oral understandings, statements, promises or inducements contrary to the terms of
this Agreement. This Agreement cannot be changed or terminated orally. No verbal agreement or conversation
with any officer, agent, representative or employee of the City, either before or after the execution of this
Agreement, shall affect or modify any of the terms or obligations hereunder.
46. AMENDMENT: No amendments to this Agreement shall be effective and binding until they are reduced to
writing and signed by duly authorized representatives of both parties.
47. TEXAS LAW: This Agreement has been made under and shall be governed by the laws of the State of Texas.
48. PLACE OF PERFORMANCE: The place of making and the place of performance for all purposes shall be
Baytown,Harris County, Texas.
49. NON-WAIVER: Failure of any party, at any time, to enforce a provision of this Agreement shall in no way
constitute a waiver of that provision, nor in any way affect the validity of this Agreement or part hereof or the
18
City of Baytown,Texas
Hydro-Stop Roofing Projects
right of the City or the City's Representative thereafter to enforce each and every provision hereof. No term of
this Agreement shall be deemed waived or breach excused unless the waiver shall be in writing and signed by the
party claimed to have waived the same. Furthermore, any consent to or waiver of a breach will not constitute
consent to or waiver of or excuse of any other different or subsequent breach. Nothing contained in this
Agreement or any of the Contract Documents shall be deemed to limit or waive the sovereign immunity of the
City
50. HEADINGS: The article headings are used in this Agreement for convenience and reference purposes only and
are not intended to define, limit or describe the scope or intent of any provision of this Agreement and shall have
no meaning or effect upon its interpretation.
51. GENDER AND NUMBER: Words of any gender used in this Agreement shall be held and construed to include
any other gender, and words in the singular number shall be held to include the plural, and vice versa, unless
context requires otherwise.
52. CONSTRUCTION OF AGREEMENT: The parties agree that this Agreement shall not be construed in favor
of or against any party on the basis that the party did or did not author this Agreement.
53. AUTHORITY TO ENTER CONTRACT: Each party has the full power and authority to enter into and
perform this Agreement, and the person signing this Agreement on behalf of each party has been properly
authorized and empowered to enter into this Agreement. The persons executing this Agreement hereby represent
that they have authorization to sign on behalf of their respective corporations and/or business entities.
54. AGREEMENT READ: The parties acknowledge that they have read,understand and intend to be bound by the
terms and conditions of this Agreement.
55. ASSIGNMENT: Contractor may not assign or otherwise transfer this Agreement or any rights or obligations
hereunder without the prior written consent of the City.
56. SUCCESSORS AND ASSIGNS: This Agreement shall inure to the benefit of and be binding upon the
Contractor and its successors and assigns.
57. MULTIPLE ORIGINALS: It is understood and agreed that this Agreement may be executed in a number of
identical counterparts each of which shall be deemed an original for all purposes.
58. SEVERABILITY: If any section, subsection,paragraph, sentence,clause,phrase or word of these requirements
or specifications shall be held invalid, such holding shall not affect the remaining portions of these requirements
and the specifications and it is hereby declared that such remaining portions would have been included in these
requirements and the specifications as though the invalid portion had been omitted
IN WITNESS WHEREOF, the parties hereto have executed this Agreement in multiple copies, each o hich
shall be deemed to be an original, but all of which shall constitute but one and the same Agreement on thi y ofJanuary2013,the date of execution by the City Manager of the City of Baytown.
GENERAL CONTRACTOR S RVICES,INC.
Signature)
Pamela Teltschick
Printed Name)
President
Title)
19
City of Baytown
Hydro-Stop Roofing Projects
CITY OF BAYTOWN
A T•
S OBERT D.LEIPER,City Man er
j' e
Le
LETIC &YS SCH; ity erk
APPROVED AS TO FORM:
ACID RAMIREZ, SR.,Ci orney
STATE OF Texas
COUNTY OF Harris
Before me on this day personally appeared Pamela Teltschick in his/her capacity asPresidentofGeneralContractorServices,Inc.,on behalf of such corporation,
known to me;
proved to me on the oath of or
proved to me through his/her current description of
identification card or other document issued by the federal government or any state government that
contains the photograph and signature of the acknowledging person}
check one)
to be the person whose name is subscribed to the foregoing instrument,and acknowledged to me that he/she executed that
instrument for the purposes and consideration therein expressed.
Given under my hand and seal of office this7th day of January 2013.
oder oi:MARYANN TIIISON f J
Notary Public,State of Texas Notary Pub c in and for the State of Texas
E,,
My Commission Expires
February 15, 2015
My co sion expires: February 15, 2015
20
Bond No. 70083600
PAYMENT BOND
STATE OF TEXAS
COUNTY OF
KNOW ALL MEN BY THESE PRESENTS: That General Contractor Services, Inc.
of the City of Houston County of
Harris and State of Texas as principal, and
The Guarantee Company of North America USA authorized under the laws of the State
of Texas to act as surety on bonds For principals, are held and firmly bound unto
City of Baytown Owner),in the penal sum of
ls'i.ght: :Hundred Forty Pi.ve Thousand
Thre- Nin ry and 00i1.00 Dollars ($845,390.00 ) for the payment whereof, the said Principal
and Surety bind themselves, and their heirs, administrators, executors, successors and assigns,jointly and severally, by
these presents:
WHEREAS, rincipal has entered into a certain written contract with the Owner,dated the
day of 20 to which contract is hereby referred to and made a part hereof
as fully and to th same exten if copied at length herein.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall pay ail
claimants supplying labor and material to it or a subcontractor in the prosecution of the work provided for in said contract,
then,this obligation shall be void;otherwise to remain in full force and effect,
PROVIDED, HOWEVER,that this bond is executed pursuant to the provisions of Chapter 2253 of Texas Government
Code as amended and all liabilities on this bond shall be determined in accordance with the provisions of said Chapter to
the same extent as if it were copied at length herein.
Surety,for value received,stipulates and agrees that no change, extension of time, alteration or addition to the terms of
the contract, or to the work performed thereunder, or the plans, specifications or drawings accompanying the same, shall
in anywise affect its obligation on this bond, and it does hereby waive notice of any such change, extension of time,
alteration or addition to the terns of the contract,or to the work to be performed thereunder.
I
IN WITNESS WHEREOF, they( said Principal and Surety have signed and scaled this instrument this
day of / z'b-Z ►20 /-),
The Guarantee Company of
General Contractor Services, Inc. North America USA
Principal Surety
IrzByByZL
Kevin Quain
Title / 1/Y,l2ll Title Attorney-in-Fact
Address 8400 LaPorte Road Address 12600 Northborough, Suite 190
Houston, TX 77012 Houston, TX 77067
The name,address,and telephone number of the Resident Agent of Surety is:
Ag States Agency, LLC dba CHS Surety
200 Valleywood Dr. , Ste. 3100, The Woodlands, TX 77380
2
Bond No. 70083600
PERFORMANCE BOND
STATE OF TEXAS
COUNTY OF
KNOW ALL MEN BY THESE PRESENTS; That general Contractor services, Inc. of the City of
Houston
County of Harris
and State of
Texas he Guarantee Company of North
as principal, and America USA authorized under
the laws of the State of Texas to act as surety on bonds for principals, are held and firmly bound unto the City of
E yhL iiundred Party Five Thousand
Baytown,Texas (Owner), in the penal sum of Three Hundred Ninety and 00/100 Dollars (S845,390.00
for the payment whereof, the said Principal and Surety bind themselves, and their heirs, administrators, executors,
successors and assigns,jointly and severally,by these presents:
WHE AS, the Principal/ heentered into a certain written contract with the Owner, dated the
day of Q! 20"` to which contract is hereby referred to
and made a part hereof as fully and to the same exterikjah if copied at length herein.
NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said Principal shall
faithfully perform said Contract and shall in all respects duly and faithfully observe and perform all and singular the
covenants,conditions and agreements in and by said contract agreed and covenanted by the Principal to be observed and
performed,and according to the true intent and meaning of said Contract and the Plans and Specifications hereto annexed,
then this obligation shall be void;otherwise to remain in full force and effect;
PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Chapter 2253 of Texas
Government Code as amended and all liabilities on this bond shall be determined in accordance with the provisions of
said Chapter to the same extent as if it were copied at length herein.
Surety, for value received, stipulates and agrees that no change, extension of time, alteration or addition to the
terms of the contract, or to the work performed thereunder, or the plans, specifications, or drawings accompanying the
same, shall in anyway affect its obligation on this bond, and it does hereby waive notice of any such change, extension of
time,alteration or addition to the terms of the contract,or to the work to be performed thereunder.
Project: Hydro-Stop Roofing Projects for Baytown Municipal Service Center
City Hall. Annex and Museum and Sterling Municipal Library and Utility
Billing Building
I
IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this instrument this
P 14 day of 1 t'c&r2Z2Z4 20/ _,
General Contractor Services, Inc. The Guaran p y of North America USA
PRINCIPAL SURET
B : r2.0 B :
Kevi McQuain
Title: /SpUJG h / Title: Attorney-in-Fact
Address: 8400 LaPorte Road
Address:
12600 Northborough, Suite 190
Houston, TX 77012 Houston, TX 77067
The name and address of the Resident Agent of Surety is:
Ag States Agency, LLC dba CHS Surety
200 Valleywood Dr. , Ste. B100, The Woodlands, TX 77380
2
Bond No. 70083600
MAINTENANCE BOND
STATE OF TEXAS
COUNTY OF A
KNOW ALL MEN BY THESE PRESENTS: That we, General. Contractor Services, Inc.
as Principal, hereinafter called "Conti-actor" and the other subscriber hereto
he Guaz'arri:ee Comparty cd North America USA
as Surety, do hereby acknowledge ourselves to be held and
firmly bound to the City of Baytown, a municipal corporation, in the sum of
Eight Hundred Forty Five Thousand
Three Hundred Ninety and 00/100 DOLLARS (S 645,390.00 ) for the payment of which
sum well and truly to be made to the City of Baytown and its successors,the said Contractor and Surety do bind
themselves,their heirs,executors,administrators,successors and assigns jointly and severally.
THE CONDITIONS OF THIS OBLIGATION ARE SUCH THAT:
WHEREAS, the Contractor has on or about this day executed a Contract in writing with the City of
Baytown for the Hydro-Stop Roofing Projects and all of such work to be done as set out in full in said Contract
Documents therein referred to and adopted by the City Council, all of which are made a part of this instrument
as fully and completely as if set out in full herein.
NOW THEREFORE, if the said Contractor shall comply with the provisions of the Contract
Documents as defined in the Agreement, and correct Work not in accordance with the Contract Documents
discovered within the established warranty period, then this obligation shall become null and void, and shall be
of no further force and effect;otherwise,the same is to remain in full force and effect.
Surety,for value received,stipulates and agrees that no change,extension of time, alteration or addition
to the terms of the contract, or to the work performed thereunder, or the plans, specifications, or drawings
accompanying the same,shall in anyway affect its obligation on this bond, and it does hereby waive notice of
any such change, extension of time, alteration or addition to the terms of the contract, or to the work to be
performed thereunder.
1
IN NVITNESS WHEREOF, the said Principal and Surety have signed and scaled this instrument this
L day or
The Guarantee Company of
General Contractor Services, Inc.
North America USA
Principal S ery
By 21"'J r B
Kevin Mc vain
Title /p Q1Ll.LC Title Attorney-in-Fact
Address
8400 LaPorte Road
Address
12600 Northborough, Suite 190
Houston, TX 77012 Houston, TX 77067
The natne and address of the Resident Agcnt of Surety is:
Ag States Agency, LLC dba CHS Surety
200 Valleywood Dr. , Ste. B100
The Woodlands, TX 77380
2