Ordinance No. 11,099ORDINANCE NO. 11,099
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
AUTHORIZING CHANGE ORDER NO_ 1 WITH HASSELL CONSTRUCTION
COMPANY, INC., FOR THE WAYNE GRAY FAMILY AQUATICS CENTER PROJECT_
AUTHORIZING PAYMENT BY TI IE CITY OF BAYTOWN, THE SUM OF THIRTY -
FOUR THOUSAND FIVE HUNDRED AND NO /100 DOLLARS (S34.500.00): MAKING
OTHER PROVISIONS RELATED THERETO: AND PROVIDING FOR THE EFFECTIVE
DATE THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BA- VTOWN, TEXAS:
Section 1: That the City Council does hereby authorize Change Order No_ 1 with Hassell
Construction Company, Inc., for the Wayne Gray Family Aquatics Center Project. A copy of said change
order is attached hereto, marked Exhibit "A" and made a part hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby authorizes the payment of
THIRTY -FOUR THOUSAND FIVE HUNDRED AND NO /100 DOLLARS (534,500.00) to Hassell
Construction Company. Inc_. for Change Order No_ 1 for the Wayne Gray Family Aquatics Center Project_
Section 3: That pursuant to the provisions of Texas Local Government Code Annotated
§252.048, the City Manager is hereby granted general authority to approve any change order involving a
decrease or an increase in costs ofTWENTY -FIVE THOUSAND AND NO /100 DOLLARS (525,000.00) or
less, subject to the provision that the original contract price may not be increased by more than twenty -five
percent (25 9/6) or decreased by more than twenty -five percent (25 ° /u) without the consent of the contractor to
such decrease_
Section 4: This ordinance shall take effect immediately from and after its passage by the City
Council of the City of Baytown_
INTRODUCED, READ and PASSED by the affirmative vote of the Cit Council of the City of
Baytown this the 7th day of April, 2009_
a �,Y T O '✓r,
off_.- • ,' �. ST 1JEN 11. DONCARLOS, Mayor
FCAVT DARNELL. City Clerk
APP OVED AS TO FORM:
ACID R1- 1MIREZ. SR., City r torney
%%..b— I Couneil\ordi ... c X3009 ,April 7Chan ge Onlrr1 \VayneGravAquaticsCenierP"j t.duc
Brief Description of Changes:
CITY OF BAYTOWN
Change Order No. 1
City of Baytown Aquatics center
3/17/2009
Add to revise Roof at Administration & Mechanical Building from Asphalt Shingle to Standing Seam Metal
Roofing to match existing color at park pavilion. Standing Seam Roofing to be manufatured by Berrage.
Add or Delete Items:
Item
Description
Unit
Quantity
Unit Price
Total
1
Add Standing Seam Metal Roofing
1
LS
$58,500.00
$ 58,500.00
2
Delete Asphalt Shingles
1
LS
$24,000.00
($24,000.00)
$
$
Total
$ 34,500.00
Contract Summary:
Original Contract Price
$ 10,240,900.00
Previous Change Orders
$ -
This Change Order
4,
Revised Contract Price
$ 10,275,400.00
Original Contract Duration - Calendar Days 425
Previous Time Extensions 0
This Change Order
Revised Contract Duration - Calendar Days 425
Hassell Construction Company, Inc. Date
Director of Finance Date
Kimley -Horn & Associates, Inc. Date
Director of Engineering Date
City Manager Date