Ordinance No. 10,211is
ORDINANCE NO. 10,211
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS, AUTHORIZING CHANGE ORDER NO. 4 WITH LEM
CONSTRUCTION CO., INC., FOR THE EAST DISTRICT WASTEWATER
TREATMENT PLANT RENOVATIONS PROJECT; MAKING OTHER
PROVISIONS RELATED THERETO; AND PROVIDING FOR THE
EFFECTIVE DATE THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize Change Order No. 4 with
LEM Construction Co., Inc., for the East District Wastewater Treatment Plant Renovations
Project. A copy of said change order is attached hereto, marked Exhibit "A," and made a part
hereof for all intents and purposes.
Section 2: That pursuant to the provisions of Texas Local Government Code
Annotated § 252.048, the City Manager is hereby granted general authority to approve any
change order involving a decrease or an increase in costs of TWENTY -FIVE THOUSAND
AND NO 1100 DOLLARS ($25,000.00) or less, subject to the provision that the original contract
price may not be increased by more than twenty -Eve percent (25 %) or decreased by more than
twenty-five percent (25 %) without the consent of the contractor to such decrease.
Section 3: This ordinance shall take effect immediately from and after its passage by
the City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the
City of Baytown this the 22 "d day of November, 2005.
APPROVED AS TO FORM:
ACIO RAMIREZ, SR. 40ty Attorney
RAKarenTiles\City Council\Ordinances12005 \November 22\Changc0rderNo.4f6r1_FN1.doc
CALVIN MUNDINGER, Ma
C
r
Brief Description of Changes:
CITY OF BAYTOWN
Change Order No. 4
East District WWTP Rehabilitation of Influent Lift
Station No. 1, Treatment Train No.1, and
Miscellaneous Facilities
November 7, 2005
Item No. 1
The purpose of this change order is to delete a portion of the work from the contract. The work being deleted is all
work related to the installation of a 14 -inch Return Activated Sludge line and air lift pumping equipment serving
treatment train number three. The reason this work is being deleted is that trash and waste material was discovered
in the proposed location of the new 14 -inch line. Due to this unforeseen condition, the cost associated with
installing the line has become excessive, so the decision was made to delete this portion of the work from the
contract. Attached is the credit proposal from the contractor.
Add or Delete Items:
Item
Description
I Unit
Quantity
Unit Price
Total
1
Deletion of 14 -inch RAS Line
LS
1
(28,005.00)
$ (28,005.00)
i otal
Contract Summary:
$ (28,005.00)
Original Contract Price
$ 1,870,300.00
Previous Change Orders
67,338.99
This Change Order
Revised Contract Price
$ 1,909,633.99
Original Contract Duration - Calendar Days 385
Previous Time Extensions 170
This Change Order
Revised Contract Duration - Calendar Days ann
U47T9
Owner's
W-ekel' lelb-5
Contractor bate
lik /
Director of Finance Date
X1'1 +11.
"Director of Engineering ate
City Manager Date