Ordinance No. 9,321ORDINANCE NO. 9321 AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS, AUTHORIZING CHANGE ORDER NO. 1 WITH EXCALIBUR CONSTRUCTION, LTD., TO ADJUST THE FINAL UNIT BID QUANTITIES FOR THE ROLLINGBROOK EMERGENCY STORM SEWER REPAIR PROJECT; AUTHORIZING FINAL PAYMENT OF THE SUM OF FOUR THOUSAND SIX HUNDRED EIGHTY -NINE AND 74/100 DOLLARS ($4,689.74) TO EXCALIBUR CONSTRUCTION, LTD., FOR SAID PROJECT; AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. WHEREAS, the City of Baytown contracted with Excalibur Construction, Ltd., for the Rollingbrook Emergency Storm Sewer Repair project (the "Project "); and WHEREAS, a change order in the amount of SEVENTY -TWO AND 40/100 DOLLARS ($72.40) to adjust the final unit bid quantities is necessary to reflect the actual quantities used in the Project; and WHEREAS, all of the said improvements, as provided in the plans and specifications heretofore prepared by the City Engineer and as approved and adopted by the City Council have been performed and completed in full accordance with all of the terms and conditions of the aforesaid contract; and WHEREAS, the City Engineer in the manner provided by the terms of the said contract and the plans and specifications thereof, has approved and accepted the Rollingbrook Emergency Storm Sewer Repair project and improvements and has heretofore issued his Certificate of Final Acceptance and has certified same to the City Council and recommended that it accept and receive said work and improvements as constructed and completed by Contractor; and WHEREAS, there remains due and owing to Excalibur Construction, Ltd., the sum of FOUR THOUSAND SIX HUNDRED EIGHTY -NINE AND 74/100 DOLLARS ($4,689.74); NOW THEREFORE BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS: Section 1: That the City Council does hereby authorize Change Order No. 1 with Excalibur Construction, Ltd., to adjust the final unit bid quantities for the Rollingbrook Emergency Storm Sewer Repair project. A copy of said change order is attached hereto, marked Exhibit "A," and made a part hereof for all intents and purposes. Section 2: . That the City Council hereby accepts and approves the above - described work and improvements, and finds and determines that all of said improvements have been completed as • provided in the plans and specifications thereof, and in full accordance with all of the terms and provisions of the aforesaid contract. Section 3: That the Certificate of Final Acceptance heretofore issued by the City Engineer and certified to the City Council is hereby accepted and received. Section 4: That final payment to Excalibur Construction, Ltd., in the amount of FOUR THOUSAND SIX HUNDRED EIGHTY -NINE AND 74/100 DOLLARS ($4,689.74) is hereby authorized. Section 5: This ordinance shall take effect immediately from and after its passage bythe City Council of the City of Baytown. INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the City of Baytown this the 14th day of February, 2002. PETE C. ALFARO, Mayor ATTEST: GZR W W. ITH, City Clerk APPROVED AS TO FORM: /C G ACIO RAMIREZ, SW., City Attorney F:\Jeanene\My Doc uments \Council \01 -02 \February\ChOrder IF ina] Pay4RoII ingbrookEmergeneyStormSewerRepair .doc • • CITY OF BAYTOWN ROLLINGBROOK EMERGENCY STORM SEWER REPAIRS CHANGE ORDER #1 February 7, 2001 This change order is requested to balance the difference of the originally estimated quantities and actual quantities used to complete the project. The project consisted of emergency repairs to an existing 48" storm sewer line on Rollingbrook Drive at Goose Creek that had failed and caused erosion under the roadway. Additional contract days are required due to rain and excessively wet conditions underneath the Goose Creek bridge. The contractor requested an additional 32 days but only 28 days were needed in order to complete the project. Item Description Unit Orig. Quant. Final Quant. Diff. Price Cost Difference 1 Roadway excavation CY 150 120 -30 $ 20.00 $ (600.00) 2 Borrow CY 257 252 -5 $ 25.00 $ (125.00) 3 Trench safe (10' -15') depth LF 35 0 -35 $ 5.00 $ (175.00) 4 Trench safe (15' -20') depth LF 80 72 -8 $ 10.00 $ (80.00) 5 48" RCP LF 115 72 -43 $ 140.00 $ (6,020.00) 6 Cement stabilized sand TON 85 412.58 327.58 $ 30.00 $ 9,827.40 7 Remove exist CMP LF 115 72 -43 $ 35.00 $ (1,505.00) 8 5" reinforced concrete slope paving SY 70 60 -10 $ 125.00 1 $ (1,250.00) 9 ITraffic control I MO 1 1 1 1 1 01$ 5,000.00 1 $ - Total Change Order #1 Change Order Summary: Final Construction Cost $ 46,897.40 Initial Estimate $ 46,825.00 Change Order #1 $ 72.40 Excalibur Construction, Ltd. Date Finance Date 72.40 Original contract time 30 calendar days Change order No. 1 - add 28 calendar days Amended contract time 58 calendar days Director of Engineering Date City Manager EXHIBIT A Date s CITY OF BAYTOWN Project: Rollingbrook Emergency Storm Sewer Repair Excalibur Construction, Inc. P.O. Box 783 Spring, Texas 77383 -0788 Pay Estimate No. 2 (Final) Pay Estimate Cut -off Date: January 30, 2002 Total Time Allowed: 30 calander days Total Time Used: 58 calander days Item Description Unit Estimated oty Qty this Estimate Unit Price Total this Estimate 1 Roadway excavation CY 150 120 $20.00 $2,400.00 2 Borrow CY 257 252 $25.00 $6,300.00 3 Trench safety 10' -15' depth LF 35 0 $5.00 $0.00 4 Trench safety 15' -20' depth LF 80 72 $10.00 $720.00 5 48" RCP LF 115 72 $140.00 $10,080.00 6 Cement stabilized sand TON 85 412.58 $30.00 $12,377,40 7 Remove exist CMP LF 115 72 $35.00 $2,520.00 8 5" reinforced concrete slope paving SY 70 60 $125.00 $7,500.00 9 Traffic control MO 1 1 $5,000.00 $5,000.00 Subtotal $46,897.40 Deduct previous payments ($42,207.66) Payment Due $4,689.74 Excalibur Construction, Inc. Date Contract Summary: Asst. Director of Engineering Date Original Contract Amount: $46,825.00 Change Order No. 1 , Add: $72.40 Change Order, Deduct: $0.00 Current Contract Amount: $46,897.40 Work Performed to Date: $46,897.40 Less 10% Retains e: $0.00 Net Amount Earned to Date: $46,897.40 Less Previous Payments: $42,207.66 * ** *AMOUNT DUE THIS ESTIMATE * * *` $4,689.74