Ordinance No. 8,556990408 -8 ORDINANCE NO. 8556 ® AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 1 WITH WILLIAM H. GRAY CONSTRUCTION COMPANY FOR THE 1 -10 SANITARY SEWER EXTENSION PROJECT; AUTHORIZING PAYMENT BY THE CITY OF BAYTOWN, THE SUM OF TWENTY -ONE THOUSAND FIVE HUNDRED SEVENTY -NINE AND NO 1100 DOLLARS ($21,579.00); MAKING OTHER PROVISIONS RELATED THERETO; AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS: Section 1: That the City Council does hereby authorize Change Order No. 1 with William H. Gray Construction Company for the I -10 Sanitary Sewer Extension Project. A copy of said change order is attached hereto, marked Exhibit "A," and made a part hereof for all intents and purposes. Section 2: That the City Council of the City of Baytown hereby authorizes the payment of TWENTY -ONE THOUSAND FIVE HUNDRED SEVENTY -NINE AND NO /100 DOLLARS ($21,579.00) to William H. Gray Construction Company for Change Order No. 1 for the I -10 Sanitary Sewer Extension Project. Section 3: That pursuant to the provisions of Texas Local Government Code Annotated § 252.048, the City Manager is hereby granted general authority to approve any change order involving a decrease or an increase in costs of FIFTEEN THOUSAND AND NO /100 DOLLARS ($15,000.00) or less, subject to the provision that the original contract price may not be increased by more than twenty -five percent (25 %) or decreased by more than twenty -five percent (25 %) without the consent of the contractor to such decrease. Section 4: This ordinance shall take effect immediately from and after its passage by the City Council of the City of Baytown. INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the City of Baytown this the 8`h day of April, 1999. PETE C. ALFARO, Mayor ATTEST: EILEEN P. HALL, City Clerk ® APPROVED AS TO FORM: CK ACIO RAM REZ, S ., ty Attorney c:\MyDocuments\ Council \Meetings\Apri[\ChangeOrderI Forl- I OSanitarySewerExtension.doc City of Baytown IH -10 Sanitary Sewer Extension CHANGE ORDER 41 CHANGE ORDER Page 1 of 2 Contract Number: N/A Change Order Number: n 1 Original Contract Price: $2.395.110 00 cr a se(Qecoas; in Contract Pric (this change order) Tgtgl AdJusted C.Qn1jact (including this change order) $2 579.00 $2.416.689.00 This change order increases /decreases the tune to complete the work by 0 Calendar days. The extended completion date is N/A This change order checked by Erik Miller P.E.. Camp Dresser & McKee. Inc.. DesignEngrineer This change order is requested by Wm- H. Grav Construction Co.. lnc. This chauge order is recommended bv: Erik tililler. P.E. 4,71057, April 5. 1999 Design Engineer P.E. R Date The undersigned agree to „the terms of e change order. tor, Date Owner, Date- Design Engineer, Date r EXHIBIT A Page 2 of 2 417;99 drh 01035 -1 H0263 0 City of Baytown IH -10 Sanitary Sewer Extension CHAINGE ORDER 91 Name of City EPA/SWCB Number Contract Number Contract Title Change Order Number Owner's Name: Owner's Address: Contractor's Name: Contractor's Address: Description of Change: City of Bazgnm NIA IIIJ40 Sanita_rry Sewer Extension �1 City of Baytown 2401 Market Ba4own. Texas 77522 Wm H Gray Construction Co., Inc. 10700 Tower Oaks Blvd.. Houston. Texas 77070 Item ',,I - Remove and replace an 8 -inch transite water line tub -out which is in conflict with the tunnel receivine nit on the north side of 1H -10 at Wade Road The Contractor will remove the em'sting transite stub -out and replace/relocate with PVC pipe of the same diameter and length. The Contractor will also install a Rate valve and blocking on th_ - t th n o f Yi t Qa vale i cc a 1 i will r in 1 I e w gate valve will be installed Item =2 The Contractor shall reconstruct the existing sar itary sewer system on Thompson Road. immediately south of(H l0 The Contractor shall remove and rrplac° an existing manhole (tiIHT 11_�g and grout an eYistin; 15-inch sewer, bout and abandon one manhole and construct a new a 24 -inch gravity sewer from 'MHT 1 to the existing manhole on the large 42 -inch trunk sewer (SW comer of Thompson and fH -10).. Reason for Change: Item a 1- This work is rQQuired to allow for the installation of the tune l receiving pit on then rthea t comer f - 10 and Wade Road, Thc mceivins pit i5 rgquirrd [Qr the avi ty sexygi gossing Qf IH -10 and i5 IQqated ad.j acent to the, stub -out. The pit cannot be constructed without causin} damage to the transite Ripe (brittle) The wa rlin stub -0ut is owned by the Harris County Eresh Water Supply District 91 A. This work will prevent downtime for the contractor's tunneling crew and solutions had been propgsed_ however. will maintain both Qptions th roiect were at considerably schedule (cost = $4,214,00). Two alternative hider cost 15 400 and S4Q.4L35)_pj w_ r less desirable on a t clinical ba�i5 The proposal from Wm. H. Grav Construction outlining the three alternatives is attached Item 92 The reconstruction of the sewer system on Thompson Road south of iH- 10 is required to eliminate a bottleneck in the system. replace a deteriorating_ manhole. and to prevent future problems (cnst = S 17.365,00) The proposal from Wm. H. Grav Construction for this work is attached 4/7!99 drh H0263 End of Change Order 41 01035 -2