Ordinance No. 8,248980409 -3 ORDINANCE NO. 8248 ® AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 2 WITH WHITELAK, INC., TO ADJUST THE FINAL UNIT BID QUANTITIES FOR THE REROUTING OF 21" SANITARY SEWER ON GARTH ROAD PROJECT; AUTHORIZING FINAL PAYMENT OF THE SUM OF FIFTY -FOUR THOUSAND FOUR HUNDRED SIXTY -NINE AND 54/100 DOLLARS ($54,469.54) TO WHITELAK, INC., FOR SAID PROJECT; AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. WHEREAS, the City of Baytown contracted with Whitelak, Inc., for the Rerouting of 21" Sanitary Sewer on Garth Road project (the "Project "); and WHEREAS, a change order in the amount of ELEVEN THOUSAND ONE HUNDRED FORTY -NINE AND 96 /100 DOLLARS ($11,149.96) to adjust the final unit bid quantities is necessary to reflect the actual quantities used in the Project as well as the amount remaining due to Whitelak, Inc.; and WHEREAS, all of the said improvements, as provided in the plans and specifications heretofore prepared by the City's Engineer and as approved and adopted by the City Council have been performed and completed in full accordance with all of the terms and conditions of the aforesaid contract; and WHEREAS, the City's Engineer in the manner provided by the terms of the said contract and the plans and specifications thereof, has approved and accepted the work and improvements and has heretofore issued his Certificate of Final Acceptance and has certified same to the City Council and recommended that it accept and receive said work and improvements as constructed and completed by Contractor; and WHEREAS, there remains due and owing to Whitelak, Inc., the sum FIFTY -FOUR THOUSAND FOUR HUNDRED SIXTY -NINE AND 54/100 DOLLARS ($54,469.54); NOW THEREFORE, BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS: Section 1: That the City Council does hereby authorize Change Order No. 2 with Whitelak, Inc., to adjust the final unit bid quantities for the Rerouting of 21" Sanitary Sewer on Garth Road project. A copy of said change order is attached hereto, marked Exhibit "A" and made a part hereof for all intents and purposes. Section 2: That the City Council hereby accepts and approves the above - described work and improvements, and finds and determines that all of said improvements have been completed as L� 980409 -3a ® provided in the plans and specifications thereof, and in full accordance with all of the terms and provisions of the aforesaid contract. Section 4: That the Certificate of Final Acceptance heretofore issued by the City's Engineer and certified to the City Council is hereby accepted and received. Section 5: That final payment to Whitelak, Inc., in the amount of FIFTY -FOUR THOUSAND FOUR HUNDRED SIXTY -NINE AND 54 /100 DOLLARRS ($54,469.54) is hereby authorized. Section 6: This ordinance shall take effect immediately from and after its passage by the City Council of the City of Baytown. INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the City of Baytown this the 9`h day of April, 1998. ,0 v _ C• e PETE C. ALFARO, Mayor ATTEST: /z� EILEEN P. HA; ;L, City Clerk APPROVED AS TO FORM: ACID RAMIREZ, W., City Attorney cA MyDocumentsl Counci Wee tingsl ApriKhangeOrder2 Final PayGarth San itarySewer9.doe 0 2 • CHANGE ORDER NO. 2 & FINAL April 1, 1998 Honorable Pete C. Alfaro, Mayor and City Council City of Baytown P. O. Box 424 Baytown, Texas 77522 Subject: Request for approval of rates on labor and /or materials and /or equipment. Contractor: Whitelak, Inc. Project: Construction of Rerouting of 21" Sanitary Sewer on Garth Road, Job No. 044 52, Contract No, 1 Original Contract Amount As Executed: $252,176.00 Dear Mayor and City Council: Your approval is requested for an additional pay item necessary due to emergency repairs to collapsed manhole behind the Hospital on Garth Road and your approval to requested on the following adjustments of unit bid price quantities, in order to determine the adjusted Final Contract Amount. Description Qty— Unit Each Cost 1. Emergency Repair 1 L.S. $25,289.96 $ 25,289.96 Subtotal $ 25,289.96 1. Overruns Item No. 6 (f) $ 300.00 ® 2. Underrun Item Nos. 4, 9, 10, 11, 12, 13, & a ( -) $ 14,440.00 EACuncnl Pr6INChinge 0rder% %044.51 r Change Order No. 1 d FINAL EXHIBIT A • � 0 Change Order No. 2 & FINAL April 1, 1998 044 -52, Contract No. 1 Page 2 Total (Change Order No. 2 & FINAL) ( +) $ 11,149.96 Change Order No. 1 $ 42,239.76 Original Contract Amount $252,176.00 Final Contract Amount $305,565.72 Original Contract Time 60 Calendar Days Extension of Time Change Order No. 1 7 Calendar Days Extension of Time Change Order No. 2 5 Calendar Days Total Time with Extensions 72 Calendar Days ® Change Order No. 2 & FINAL April 1, 1998 044 -52, Contract No. 1 Page 3 Change Order No. 1 and No. 2 & FINAL represents an increase of 21.17% to the Original Contract Amount. Except as setforth hereinbefore, no conditions or covenants of the Contract are changed and/or waived hereby. SUBMITTED FOR APPROVAL: LANGFORD ENGINEERING, INC ACCEPTED: WHITELAK, INC. YP4 B y:E. C. M. Whitehead, II President Date: Afz.zz . Z!Z& Date: N OW03 CITY OF BAYTOWN By: Date: • Mr. Pete C. Alfaro Mayor Date: