Ordinance No. 7,352950713 -12
ORDINANCE NO. 7352
AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 93 -06 -01 WITH
PALTON CONSTRUCTION FOR HOUSING REHABILITATION PROJECT
NO. 93 -06 AT 1213 TURNER; AUTHORIZING PAYMENT BY THE CITY
OF BAYTOWN, THE SUM OF FOUR THOUSAND SIX HUNDRED FIVE AND
N01100 DOLLARS ($4,605.00) ; MAKING OTHER PROVISIONS
RELATED THERETO; AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize Change
Order No. 93 -06 -01 with Palton Construction for Housing
Rehabilitation Project No. 93 -06 at 1213 Turner. A copy of said
change order is attached hereto, marked Exhibit "A," and made a
part hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby
authorizes payment in the amount of FOUR THOUSAND SIX HUNDRED FIVE
AND N01100 DOLLARS ($4,605.00) to Palton Construction for Change
Order No. 93 -06 -01 for Housing Rehabilitation Project No. 93 -06 at
1213 Turner.
Section 3: That pursuant to the provisions of Texas Local
Government Code Annotated § 252.048, the City Manager is hereby
granted general authority to approve any change order involving a
decrease or an increase in costs of FIVE THOUSAND AND N01100
DOLLARS ($5,000.00) or less, subject to the provision that the
original contract price may not be increased by more than ten
percent (10%) or decreased by more than twenty -five percent (25 %)
without the consent of the contractor to such decrease.
Section 4: This ordinance shall take effect immediately from
and after its passage by the City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the
City Council of the City of Baytown this the 13th day of July,
1995.
PETE C. ALFARO, Mayor
ATTESTr:;
® EILEEN', P. HALL, City Clerk
•
APPROVED AS TO FORM:
IG ACIO RAMIREZ, S ., City Attorney
legal /cou nci Ilju ly /7- 13 -95chO RD ER palto n
r�
950713 -12a
r�
CHANGE ORDER #93 -06 -01
Original Contract Price: $18,420.00
HOMEOWNER:Alfreda Baskin
ADDRESS: 1213 Turner
HOMEOWNER
CONTRACTOR: Palton Construction
PROJECT NUMBER: 93 -06
CONTRACTOR
COMMUNITY DEVELOPMENT OFFICER DATE
The following additions will be made to the existing work write -up:
1. This structure was scheduled for rehabilitation. After
initial exposure, it was apparent there was extensive termite
damage, dry rot, and other structural problems which rendered
it economically unfeasible to rehabilitate. Therefore,
reconstruction is the only feasible alternative.
Please see the attached scope of work for the
reconstruction of 1213 Turner.
EXHIBIT A
® Original contract price - $18,420.00
Change order amount - $ 4,605.00
TOTAL CHANGE ORDER COST: $23,025.00
0
Bobby Rountree,
City Manager
® SCOPE OF WORK
FOR RECONSTRUCTION OF
1213 TURNER
Foundation:
a. Install new sills and floor joist for entire foundation. Raise and level foundation. Install
additional blocks and beams entire length of structure. Install termite caps.
Roof:
a. Install new framework, decking, felt paper 30 9, drip edge and shingles over entire
structure.
Windows:
a. Install new aluminum frame windows complete with screens
Siding:
a. Install innerseal (osb backing) exterior siding over entire structure.
b. Install necessary trim (corner boards, bird board, door and window facings).
C. Install two attic vents.
Water heater cabinet:
a. Base, walls, roof, vent and locking door with necessary hardware.
b. Install new water heater, supply lines, cut -offs, pop -off, double walled vent pipe, gas line
and valve.
Exterior paint:
a. Paint entire exterior of structure
Electrical:
a. Install new electric service (breaker box, met�:r loop and weather head).
b. Install new wiring throughout entire structure.
C. Install cover plates for all switches and outlets.
Plumbing:
• a. Install new fresh water Imes throughout structure and to water meter.
b. Install two hose bibs.
C. Install pipe insulation on all pipes under structure.
d. Install new waste water lines under structure. Install clean out and wast water line to city
main.
e. Install new gas lines throughout structure and to gas meter.
INTERIOR
Living room:
a. Front entry - install pre -hung metal door complete with security knob, dead bolt lock,
peephole, door stop, interior facing.
b. Front entry - install aluminum storm door complete with screen and hardware.
C. Front entry - install treated wood porch, steps, and handrail.
d. Front entry - install exterior light fixture with interior wall switch.
e. Install new ceiling joists and wall studs.
f. Install sheetrock on walls and ceiling, tape, float and texture.
g. Install carpet pad and carpet.
h. Install baseboard.
i. Paint walls, ceiling and all trim. t
j. Install light fixture with wall switch. `
0 Bedroom #l:
a. Install new ceiling joists, rafters, and wall studs.
b. Install stud walls to form closet.
C. Closet - install supports, hanger rod and shelf.
d. Closet - install passage door, knob, door stop, and facings.
e. Install sheetrock on walls and ceiling, tape, float, and texture.
f. Install carpet pad and carpet.
g. Install baseboard.
h. Paint walls, ceiling and all trim.
i. Install light fixture with wall switch.
j. Install pare -hung door complete with facings, door knob and door stop.
Bedroom #2:
a. Install new ceiling joists, rafters, and wall studs.
b. Install stud walls to form closet.
C. Closet - install supports, hanger rod, and shelf.
-d. Closet - install passage door, knob, door stop, and facings.
e. Install sheetrock on walls ceiling, tape, float, and texture.
F Install carpet .pad and carpet.
g. Install baseboard.
h. Paint walls, ceiling and a:! trim.
i. Install light fixture with >,all switcl
j. Install hollow core door ..: mplete ;1!ith facings, door knob, and door stop
0 Hn11:
a. Install stud walls, ceiling joists, and rafters.
b. Install sheetrock on walls and ceiling, tap e , float , and texture.
C. Install carpet pad and carpet.
d. Install baseboard.
e. Install light fixture with wall switch.
f. Install attic stairway with frame.
g. Install smoke detector.
h. Paint walls, ceiling and all trim.
Bathroom:
a. Install ceiling joists, rafters, and wall studs.
b. Install sheetrock on walls and ceiling, tape, float, and texture.
C. Install vinyl floor covering.
d. Install base and shoe molding.
e. Paint walls, ceiling and all trim.
f. Install hollow core door complete with facing and privacy hardware.
g. Install vanity, vanity top, pop -up, supply lines, cut -offs, faucets, drain line and p -trap, vent
with roof jack.
h. Install toilet, supply line, cut -off, drair. line, vent, wax ring, and seat.
i. Install tub and shower, supply Fries, faucets, shower head, drain line, vent, shower rod. �
j. Install medicine cabinet • -.:-:th mi- � or above vanity.
k. Install light fixture with wall switch.
0
T
A.
Kitchen:
a.
Back entry - install pre -hung metal door complete with security knob, deadbolt lock
peephole, door stop, interior facing.
b.
Back entry - instaIl aluminum storm door complete with screen and hardware.
C.
Back entry - install treated wood steps and handrail.
d.
Back entry - install exterior light fixture with interior wall switch.
e.
Install new ceiling joists, rafters, and wall studs.
f.
Install sheetrock on walls and ceiling, tape, float, and texture.
g.
Install new upper and lower kitchen cabinets, pre -fab counter top, double basin stainless
steel sink, supply sines, cut -offs, drain line, p -trap and vent with roof jack, stain cabinets.
h.
Install gas line and connection for stove.
i.
Install vinyl floor covering.
j,
Install shoe/base molding.
k.
Paint walls, ceiling and ail trim.
1.
Install ductless vent hood.
M.
Install light fixture with wall switch.
n.
Install connections, drain line and p -trap for washer.
o.
Install electrical outlet for dryer.
P.
Install gas jet for dryer.
Attic
insulati -,n: i
a.
Over • hire living area, install R -19 attic insulation.
Hvac:
a. Install centrai heat (complete), including registers, boxes, ductwork, return air and chase,
heater wiring, thermostat