Ordinance No. 7,273950323 -14
ORDINANCE NO. 7273
• AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 2 WITH PALTON
CONSTRUCTION FOR HOUSING REHABILITATION PROJECT #93 -04 AT
2203 ALABAMA; AUTHORIZING PAYMENT BY THE CITY OF BAYTOWN,
THE SUM OF ONE THOUSAND FOUR HUNDRED SEVENTY -TWO AND
N01100 DOLLARS ($1,472.00) ; MAKING OTHER PROVISIONS
RELATED THERETO; AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize Change
Order No. 2 with Palton Construction for Housing Rehabilitation
Project #93 -04 at 2203 Alabama. A copy of said change order is
attached hereto, marked Exhibit "A," and made a part hereof for all
intents and purposes.
Section 2: That the City Council of the City of Baytown hereby
authorizes payment of the amount of ONE THOUSAND FOUR HUNDRED
SEVENTY -TWO AND N01100 DOLLARS ($1,472.00) to Palton Construction
for Change Order No. 2 for Housing Rehabilitation Project ##93 -04 at
2203 Alabama.
Section 3: That pursuant to the provisions of Texas Local
Government Code Annotated § 252.048, the City Manager is hereby
granted general authority to approve any change order involving a
decrease or an increase in costs of FIVE THOUSAND AND N01100
DOLLARS ($5,000.00) or less, subject to the provision that the
original contract price may not be increased by more than ten
percent (10 °s) or decreased by more than twenty -five percent (2511)
without the consent of the contractor to such decrease.
Section 4: This ordinance shall take effect immediately from
and after its passage by the City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the
City Council of the City of Baytown this the 23rd day of March,
1995.
PETE C. ALFARO, Mayor
ATTEST:
EILEEN P. HALL, City Clerk
•
APPROVED AS TO FORM:
I ACID IREZ, City Attorney
legal / council /march/3- 23- 95chORDrehabALABAMA
•
950323 -14a
• CHANGE ORDER #93 -04 -2
Original Contract Price:$18,275.00
HOMEOWNER: Footsiag
HOMEOWNER
COMMUNITY DEVELOPMENT OFFICER
PROJECT NUMBER: 93 -04
CONTRACTOR
DATE
The following changes will be added to the existing work write -up:
Install approximately 2,112 Square Feet of 1/2" Plywood Decking to
roof. ( Install to Specification 7.05 -7.07 )
$972.00
Install approximately 1,800 Square Feet of R -19 insulation complete
to program specifications.
$500.00
Total Cost = $1,472.00
EXHIBIT A