Ordinance No. 7,124941013 -2
ORDINANCE NO. 7124
• AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 3 WITH
BELLINGHAM MARINE FOR THE BAYLAND PARK MARINA FLOATING
DOCK SYSTEM; AUTHORIZING PAYMENT BY THE CITY OF BAYTOWN,
THE SUM OF FORTY -SEVEN THOUSAND NINE HUNDRED NINETY -THREE
AND NO /100 DOLLARS ($47,993.00); MAKING OTHER PROVISIONS
RELATED THERETO; AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize Change
Order No. 3 with Bellingham Marine for the Bayland Park Marina
Floating Dock System. A copy of said change order is attached
hereto, marked Exhibit "A," and made a part hereof for all intents
and purposes.
Section 2: That the City Council of the City of Baytown hereby
authorizes the payment of FORTY -SEVEN THOUSAND NINE HUNDRED
NINETY -THREE AND N01100 DOLLARS ($47,993.00) to Bellingham Marine
for Change Order No. 3 for the Bayland Park Marina Floating Dock
System.
Section 3: That pursuant to the provisions of Texas Local
Government Code Annotated S 252.048, the City Manager is hereby
granted general authority to approve any change order involving a
decrease or an increase in costs of FIFTEEN THOUSAND AND N01100
DOLLARS ($15,000.00) or less, subject to the provision that the
original contract price may not be increased by more than
twenty -five (25 %) or decreased by more than twenty -five (25 %)
percent without the consent of the contractor to such decrease.
Section 4: This ordinance shall take effect immediately from
and after its passage by the City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the
City Council of the City of Baytown this the 13th day of October,
1994.
P4 C. ��
PETE C. AL O, Mayor
ATTEST:
i
• EILEEN P. 'HALL, City Clerk
Cl
•
•
CITY OF BAYTOWN
2401 MARKET P.O. BOX 424 BAYTOWN, TX 77522 -0424 (713) 422 -8281 FAX (713) 420 -6586
CITY OF BAYTOWN
BAYLAND PARK MARINA
FLOATING DOCK SYSTEM
Change Order No. 3
October 4, 1994
The following changes are added to the Bayland Park Marina
Floating Dock System contract:
1. The main TV cable trunkline will terminate at a PVC riser
at the bulkhead. This will eventually be connected up to
a main terminal box by TCI Cable.
2. The trunkline will run through the center chase on the
main walk. The tributary lines (at each pier) will run
under the walers and come up to subterminal boxes to be
supplied and installed by TCI Cable. These boxes will
have a capacity of from four to eight services. The
individual lines will then be pulled from these boxes and
hooked up to each slip and labeled accordingly.
3. The 100 pair phone line will terminate at a PVC riser at
the bulkhead. GTE will eventually connect this main line
to its terminal.
4. The phone lines will run through conduit installed in the
center 4" chaseway on the main walk floats.
5. Existing electrical pull boxes will be utilized by
properly shielding the low voltage wire. One 2 -pair
cable will be connected to each outlet for service to the
slip. All proper labeling is included.
TOTAL CHANGE: $47,993.00
Contract Summary:
Original Contract Amount: $1,079,000.00
Change Order No. 1: 0.00
Change Order No. 2: 11,797.00
Change Order No. 3: 47,993.00
Amended Contract Amount: $1,138,790.00
EXHIBIT A