Ordinance No. 6,845931028 -6
ORDINANCE NO. 6845
• AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 1 WITH
NOLASCO "S CARPENTRY FOR HOUSING REHABILITATION PROJECT
#92 -06 AT 309 MORRELL STREET; AUTHORIZING PAYMENT BY THE
CITY OF BAYTOWN, UP TO THE SUM OF TWO THOUSAND NINE
HUNDRED FORTY AND N01100 DOLLARS ($2,940.00); MAKING
OTHER PROVISIONS RELATED THERETO; AND PROVIDING FOR THE
EFFECTIVE DATE THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize Change
Order No. 1 with Nolasco's Carpentry for Housing Rehabilitation
Project 092 -06 at 309 Morrell Street. A copy of said change order
is attached hereto, marked Exhibit "A," and made a part hereof for
all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby
authorizes payment up to the amount of TWO THOUSAND NINE HUNDRED
FORTY AND N01100 DOLLARS ($2,940.00) to Nolasco's Carpentry for
Change Order No. 1 for Housing Rehabilitation Project 192 -06 at 309
Morrell Street.
Section 3: That pursuant to the provisions of Texas Local
Government Code Annotated S 252.048, the City Manager is hereby
granted general authority to approve any change order involving a
decrease or an increase in costs of FIFTEEN THOUSAND AND N01100
DOLLARS ($15,000.00) or less, subject to the provision that the
original contract price may not be increased by more than
twenty -five (25 %) or decreased by more than twenty -five (25 %)
percent without the consent of the contractor to such decrease.
Section 4: This ordinance shall take effect immediately from
and after its passage by the City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the
City Council of the City of Baytown this the 28th day of October,
1993.
AA C �
PETE C. AL FARO, Mayor
ATTEST:
EILEEN P. HALL, City Clerk
'W
ACIO RAMIREZ, ISA,,. , City Attorney
Iopvca W10-2&93eb0RDMtrensb
•
•
Community Development Program
Housing Rehabilitation Project
Change Order
Project# 92 -06 Date October 19, 1993
Homeowner Myrtis Ballard
Contractor Nolasco's Carpentry
Address 309 Morrell
The following changes to the contract for this project are needed:
1. Remove existing a/c supply ducts and ceiling vents throughout
structure, plenum, return air duct and grill. Remove closet
door and frame, frame in to enclose a/c supply and air ducts
(inside of closet) , reinstall closet rod and shelf, door frame,
door and facings.
$ 500.00
2. Install new sheet metal duct for return air, plenum, flex duct,
adjustable ceiling vents, grill and filter. Sub - contracted out
to a licensed a/c contractor.
$ 1.220.00
3. Install 4 telephone jacks. Necessary to support Life Line
(emergency call button).
$ 60.00
4. Install new prefab kitchen countertop. $ 70.00
5. Install concrete to repair and level existing bathroom floor.
$ 75.00
6. Install double 2" X 12" beam to remove, sag from livingroom
ceiling.
$ 150.00
7. Install new fresh water line from house to meter(approximately
50" of trenching and new water line).
$ 275.00
8. Install light fixture and switch in dining area of livingroom
to be separate from ceiling fan /light fixture.
$ 65.00
TOTAL $ 2,415.00
EXHIBIT A
UA
Community Development Program
Housing Rehabilitation Project
Change Order
Project # 92 -06 Date October 19, 1993
Homeowner Mortis Ballard Address 309 Morrell
Contractor Nolasco's Carpentry
The following items will be deleted from the work write -up:
None
1
Original Contract Price
$
19,600.00
Cost of Change Order
$
2,415.00
New Contract Price
$
21,715.00
Approved by:
Community Development Coordinator
Director Planning & Community Development