Ordinance No. 6,176920227 -13
ORDINANCE NO. 6176
• AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 1 WITH
BUSCH, HUTCHISON AND ASSOCIATES, INC. FOR ENGINEERING
AND ARCHITECTURAL SERVICES ON THE GOOSE CREEK STREAM
GREENBELT PROJECT; AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
•
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize
Change Order No. 1 with Busch, Hutchison and Associates, Inc.
for engineering and architectural services on the Goose Creek
Stream Greenbelt project. A copy of said change order is
attached hereto, marked Exhibit "A," and made a part hereof for
all intents and purposes.
Section 2: That the City Council of the City of Baytown
hereby authorizes the payment of TWELVE THOUSAND AND N01100
($12,000.00) DOLLARS to Busch, Hutchison and Associates, Inc.
for Change Order No. 1 for engineering and architectural services
on the Goose Creek Stream Greenbelt project.
Section 3: This ordinance shall take effect immediately
from and after its passage by the City Council of the City of
Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the
City Council of the City of Baytown, this the 27th day of
February, 1992.
ATTEST: "
i
EILEEN� 'P'. LL, City Clerk
dmw�2� a4/
ACIO RAMIREZ, ., City Attorney
C:1:85:13
' r
.ENJBUSCH, HUTCHISON & ASSOCIATES, INC. ARCHITECTS- ENGINEERS
1107 FLEETWOOD • BAYTOWN, TEXAS 77520 • (713) 422 -8213
February 10, 1992
Goose Creek Stream Committee
City of Baytown
307 S. Main
Baytown, Texas 77520
Attention: Mrs. Jo Roosa
Project Staff Coordinator
CHANGE ORDER NO. 1
RE: PROFESSIONAL SERVICES COST OVERRUN & REQUEST FOR CHANGE
ORDER
Dear Jo:
While the original scope of surveying on this project was defined to be from Texas
Avenue to Spur 201, it became necessary to do work south of Texas Ave. to Market
Street as well as locate the boundaries of Busch Terrace Park. These requirements also
caused us to need abstract information we had not expected.
Additionally we were subsequently requested to delineate on the ground the 100 year
flood plain elevation across several tracts. The work done south of Texas Avenue will all
be useful for Phase 11 of the project and the surveying costs will be proportionally less
when needed.
At this time we have total billing in the amount of $34,639.13 which includes both
Architectural /Engineering costs as well as surveying. Thera is an outstanding invoice for
A/E fees in the amount of $3,189.38. We have some final additional surveying work from
Park Street to Spur 201 we estimate will cost $3,000 - $4,000. We respectfully request
a change order for an additional $12,000.00. The final cost will then be "not to exceed
$42,000 ".
Sincerely yours,
Ja s P. Hutchison, P.E.
JPH /ma
U
EXHIBIT A