Ordinance No. 5,226ORDINANCE NO. 5226
AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 4 WITH SUGAR
LAND REHABILITATION, INC. FOR THE 1988 SANITARY SEWER
SLIPLINING PROJECT; AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize
Change Order No. 4 with Sugar Land Rehabilitation, Inc. for the
1988 Sanitary Sewer Sliplining Project. A copy of said change
order is attached hereto, marked Exhibit "A," and made a part
hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown
hereby authorizes the payment of FIFTEEN THOUSAND EIGHT HUNDRED
NINETY AND NO /100 ($15,890.00) DOLLARS to Sugar Land
Rehabilitation, Inc. for Change Order No. 4 of the 1988 Sanitary
Sewer Sliplining Project.
Section 3: This ordinance shall take effect immediately
from and after its passage by the City Council of the City of
Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the
City Council of the City of Baytown, this the 9th day of March,
1989.
,zg,-D -- -
E TT 0. HUTTO, Mayor
ATTEST:
EILEEN P. ffALLF" City Clerk
RANDALL B. STRONG, City torney
C:1:6 :10
A
M 1988 Sanitary Sewer Sliplining Project
Job No. 8811 -10
Change Order No. 4
February 28, 1989
Sugar Land Rehab. Inc.
P.O. Box 1504
Sugar Land, Texas 77478
Dear Mr. Geary:
The City of Baytown proposes to add the following quantities to the
1988 Sanitary Sewer Sliplining Project:
Item Approx. Unit of Description unit Extension
No. Ouant. Measure Price
3 1130 l.f. Sliplining 7.125" O.D. 9.00 $ 10,170.00
polyethylene pipe liner in
existing 8" sewer, including
manhole tie -ins, CIP
4 22 each Service connections to 8" 260.00 5,720.00
sewer line and liner, as per
specifications, CIP
TOTAL ADDITIONS $ 15,890.00
The additional work noted above is to be performed in the easement
parallel to St. Andrews and Country Club View between Quail Hollow and
County Club. If this change order meets with your approval, please sign in
the space provided below and return this document to the Engineering
Department. A signed copy will be sent to you.
Original Contract Amount $ 105,710.00
Change Order No. 1 14,220.00
Change Order No. 2 6,780.00
Change Order No. 3 6,600.00
Change Order No. 4 15,890.00
Ammended Contract Amount $ 149,200.00 (41.1% increase over original contract)
APPROVED
City of Baytown
By:
Title:
Sincerely,
3 ZA1
�6'Nrc ovU
Norman Dykes, P.E.
City Engineer /Dir. of Public Works