Ordinance No. 5,184890112 -15
ORDINANCE 5184
AN ORDINANCE AUTHORIZING CHANGE ORDER NO. 1 WITH
SUGAR LAND REHAB, INC. FOR THE 1988 SANITARY SEWER
SLIPLINING PROJECT; AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize
Change Order No. 1 with Sugar Land Rehab, Inc. for the 1988
Sanitary Sewer Sliplining Project. A copy of said change order
is attached hereto, marked Exhibit "A," and made a part hereof
for all intents and purposes.
Section 2: That the City Council of the City of Baytown
hereby authorizes the payment of FOURTEEN THOUSAND TWO HUNDRED
TWENTY AND N01100 ($14,220.00) DOLLARS to Sugar Land Rehab, Inc.
for Change Order No. 1 of the 1988 Sanitary Sewer Sliplining
Project.
Section 3: This ordinance shall take effect immediately
from and after its passage by the City Council of the City of
Baytown.
INTRODUCED, READ
City Council of the
January, 1989.
and PASSED by the affirmative vote of the
City of Baytown, this the 12th day of
EMMETT 0. HUTTO, Mayor
ATTEST:
EILEEN P. HALL, City Clerk
RANDALL B. STRONG, City orney
C:1:23:16
1988 Sanitary Sewer Sliplining Project
Job No. 8811 -10
Change Order No. 1
January 9, 1989
Sugar Land Rehab. Inc.
P.O. Box 1504
Sugar Land, Texas 77478
Dear Mr. Geary:
The City of Baytown proposes to add the following quantities to the
1988 Sanitary Sewer Sliplining Project:
Item Approx. Unit of Description Unit Extension
No. Ouant. Measure Price
3 1580 l.f. Sliplining 7.125% O.D. 9.00 $ 14,220.00
polyethylene pipe liner in
existing 8" sewer, including
manhole tie -ins, CIP
13 0 each Point repairs where 200.00 0.00
sliplining is impossible due
to short sections of
undersized pipe installed by
City maintenance crews, for
lines added under this change
order only, if necessary, CIP
The additional work noted above is to be performed in two locations.
They are as follows:
a. Felton Street from the easement between James and Murrill to the
easement between Murrill and Sterling. The majority of this line is
under Felton Street. Approx. length = 350 ft. No taps.
b. Ward Road beginning approx. 200 ft. west of Fifth St. to Hwy 146.
Approx. length = 1230 ft. No taps.
If this Change Order meets with your approval, please sign below and
return this document to the Engineering Department. A signed copy will be
sent to you.
Original Contract Amount $ 105,710.00 Sincerely,
Change Order No. 1 _4,220.00
Ammended Contract Amount 119,930.00
APPROVED
City of Baytown
By: By:
Title:
Norman Dykes, P.E.
City Engineer /Dir. of Public Works
APPROVED
Sugar Land Rehab, Inc.
Title:
Date: Date: