Ordinance No. 3,55430127_4
ORDINANCE NO. 3554
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY
OF BAYTOWN AUTHORIZING CHANGE ORDER NO. 15 TO
THE CONTRACT WITH NUNN & SHUMWAY CONSTRUCTION
COMPANY FOR THE WEST DISTRICT WASTEWATER
TREATMENT PLANT & LAKEWOOD LIFT STATION.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
Section 1: That the City Council does hereby authorize Change Order No. 15
to the contract with Nunn & Shumway for the West District Wastewater Treatment
Plant and Lakewood Lift Station for the City of Baytown. A copy of said change
order is attached hereto marked "Exhibit A ", and made a part hereof for all intents
and purposes.
Section 2: This Ordinance shall take effect from and after the date of its
passage.
INTRODUCED, READ, and PASSED by the affirmative vote of the City
Council of the City of Baytown, on this the 27th day of January , 1983.
EMMETT O. HUTTO, Mayor
ATTEST:
C,Jc.�e_;yC� zed
EILEEN P. HALL, City Clerk
CHANGE ORDER NO. 15 30127 -4a
January 6, 1983
Mr. Fritz Lanham, City Manager
City of Baytown
P.O. Box 424
Baytown, Texas 77520
SUBJECT:Request For Approval of Rates on Labor and /or Materials and /or
Equipment.
CONTRACTOR: Nunn & Shumway Construction Co., Inc.
PROJECT: Construction of West District Wastewater Treatment Plant
ORIGINAL CONTRACT AMOUNT: $3,447,036.25 (Eligible Amount)
$ 18,400.00 (Non - eligible Amount)
$3,465,436.25 (Total Amount)
ORIGINAL COMPLETION DATE: November 29, 1982
Dear Mr. Lanham:
Your approval is requested on the following items which reflect project
(underruns) and /or (overruns). These added costs or de- ductions will be
applied to the contract.
Approved
Description
Cost
Time Extension
1)
Underrun quantities of
Supplementary Bid Items
No. 31A, 31B, 31C, 31D,
31E, 31F, 31G, 31H, &
31I. (per attached Job
Cost summary sheet.)
Deduct
- $6,736.25
Total Additional Cost: Change Order No. 15
- $6,736.25
-0-
2)
Change Order No. 1
-0-
( +)3 Days
3)
Change Order No. 2
- $3,252.54
-0-
4)
Change Order No. 3
-0-
{ +)2 Days
5)
Change Order No. 4
-0-
( +)2 Days
6)
Change Order No. 5
-0-
-0-
7)
Change Order No. 6
-0-
( +)3 Days
8)
Change Order No. 7
-0-
( +)6 Days
9)
Change Order No. 8
-0-
( +)5 Days
`i A
Change Order No. 15
30127 -4b
January 6, 1983
Page 2
This represents an increase of 0.0089% in the Original Contract
Amount.
Approved Time Extensions: 41 Calendar Days
Revised Completion Dater January 10, 1983
Actual Completion Date: January 6, 1983
RECOMMENDED FOR APPROVAL: ACCEPTED:
LANGFORD ENGINEERING, INC. NUNN & SHUMWAY CONST. CO., INC.
J ck Nash
pager of Field Services
6
APPROVED:
CITY OF BAYTOWN, TEXAS
By:
Fritz Lanham, City Manager
Date:
JN:sb
By:
Date: j_ :r
Approved
Description
Cost Time Extension
10) Change
Order
No.
9
-0-
( +)4 Days
11) Change
Order
No.
10
-0-
( +)8 Days
12) Change
Order
No.
11
(add) ( +)$4,300.00
-0-
13) Change
Order
No.
12
(add) ( +)$4,471.00
-0-
14) Change
Order
No.
13
(add) ( +)$1,526.00
-0-
15) Change
Order
No.
14
-0-
( +)8 Days
Final Contract
Amount:
$ 3,465,744.46
(Eligible
Amount:)
3,437,332.00 (NonEligible
Amount)$28,412.46
This represents an increase of 0.0089% in the Original Contract
Amount.
Approved Time Extensions: 41 Calendar Days
Revised Completion Dater January 10, 1983
Actual Completion Date: January 6, 1983
RECOMMENDED FOR APPROVAL: ACCEPTED:
LANGFORD ENGINEERING, INC. NUNN & SHUMWAY CONST. CO., INC.
J ck Nash
pager of Field Services
6
APPROVED:
CITY OF BAYTOWN, TEXAS
By:
Fritz Lanham, City Manager
Date:
JN:sb
By:
Date: j_ :r