Ordinance No. 3,45220826 -10
ORDINANCE NO. 3452
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN
AUTHORIZING CHANGE ORDER NO. I TO THE CONTRACT WITH SKRLA,
INC. FOR THE FOR THE CITY OF BAYTOWN 1982 STREET IMPROVEMENT
PROGRAM.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS:
Section 1: That the City Council does hereby authorize
Change Order No. I to the contract with Skrla, Inc. for
the 1982 Street Improvement Program for the City of Baytown. A
copy of said change order is attached hereto marked "Exhibit A ",
and made a part hereof for all intents and purposes.
Section 2: This ordinance shall take effect from and after
the date of its passage.
INTRODUCED, READ, and PASSED by the affirmative vote of the
City Council of the City of Baytown, on this the 26th day of
August , 1982.
oo
'EMMETT 0. TTO, Mayor
ATTEST:
Z �'6� A —'/4 �
EILEEN P. HALL, City Clerk
APPROVED:
OANDALL•: ,fir
,' "EXHIBIT A" 20526 -10a
CITY OF BAYTOWN
1982 STREET IMRPOVEMENT PROGRAM
CHANGE ORDER No. 1
AUGUST 20, 1982
SKRLA, Inc.
P. 0. Box 12301
Houston, Texas 77017
Gentlemen:
We propose to ADD the following changes to your present contract:
Item
No. quant Unit Description _ Cost Amount
1 100.0 Ton Hot mix asphaltic concrete, $40.00 $ 4,000.00
0 8 W OIL]
10,400.00
440.00
.10 11
724.50
1.5" thick (170 lbs /s.y.),
complete in place (CIP)
3
200.0 Gal Asphaltic material, prime
1.50
coat of tack coat (0.17
gals /s.y.), CIP
5
520.0 Ton Crushed limestone base ma-
20.00
terial (4,000 lbs /c.y.),
CIP
6
176.0 S.F. Concrete sidewalk 4" thick
2.50
w1l" sand bedding including
saw cutting, removal of
existing concrete, hauling,
& excavation, CIP
9
150.0 L.F. Concrete curb, 6 ", includ --
4.00
ing drilling holes, dowels,
steel, saw cutting, removal
of existing concrete, haul-
ing, & excavation, CIP
10
230.0 S.F. Concrete valley gutter 6"
3.15
thick with 4" cement sta-
bilized sand including saw
cutting, removal of exist-
ing concrete, hauling, &
excavation, CIP
0 8 W OIL]
10,400.00
440.00
.10 11
724.50
20826 -10b
Item
No.
Quant
Unit
Description
Cost
Amount
13
460.0
C.Y.
Salvage & reuse existing
$ 3.00
$ 1,380.00
base mat'l in place to the
depth specified on the
plans, CIP
14
325.0
G.Y.
Excavation of mat'l (sub -
5.00
1,625.00
grade) & haul to desig-
nated site, CIP
21
150.0
Ton
Cement stabilized sand (1.5
15.00
2,250.00
sack mix), CIP
TOTAL $21,719.50
ADD 15 work days to the original 110 days allowed for completion of job.
If this change meets with your approval, please sign this document and re-
turn to the Engineering Department. A signed copy will be returned to you.
Sincerely,
Norman Dykes, P.E.
City Engineer /Director of Public Works
APPF,0VED : APPROVED:
City of Baytown SKRLA, Inc.
By:
Date:.
ES /lc
2
By:_
Date: