Ordinance No. 14,107ORDINANCE NO. 14,107
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
APPROVING CHANGE ORDER NO. 6 TO THE BAYTOWN AREA WATER AUTHORITY 6
MGD SURFACE WATER TREATMENT PLANT PROJECT BETWEEN THE BAYTOWN AREA
WATER AUTHORITY AND PEPPER LAWSON WATERWORKS, LLC; AND PROVIDING FOR
THE EFFECTIVE DATE THEREOF.
****************************************************************************************************
WHEREAS, the Baytown Area Water Authority's enabling legislation requires that the City Council approve
certain agreements before Baytown Area Water Authority ("BAWA") enters into the same; and
WHEREAS, on June 20, 2019, the Board of Directors of BAWA approved Change Order No. 6 to the Baytown
Area Water Authority 6 MGD Surface Water Treatment Plant Project between the Baytown Area Water Authority and
Pepper Lawson Waterworks, LLC; and
WHEREAS, the City of Baytown desires to approve such change order; NOW THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the recitals set forth hereinabove are hereby found to be true and correct and are hereby
adopted.
Section 2: That the City Council of the City of Baytown, Texas, hereby approves Change Order No. 6 for
the Baytown Area Water Authority 6 MGD Surface Water Treatment Plant Project between the Baytown Area Water
Authority and Pepper Lawson Waterworks, LLC, which change order is attached hereto as Exhibit "A" and incorporated
herein for all intents and purposes.
Section 3: This ordinance shall take effect immediately from and after its passage by the City Council of
the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the Cit of Baytown this the
27"' day of June, 2019.
RANDON CAPETILLO, Ma or
ATTAST:
LETICIA BRYSCH, City -Clerk
APPROVED AS TO FORM: p°°o
°•°,,ro
Y .
ACIO RAMIREZ, SR., ty ttorney �4i`� jtl0 �O®
R."KarenTiles'City Counc&Ordinances•2019 June 27WpprovingBAWAChangeOrderNo6.doc
Exhibit "A"
3AYTOWN AREA WATER AUTHORITY
Change Order No. 6
IGD SURFACE WATER TREATMENT PLANT
"in 1 V 11 i 1 PO: 1806021
Date: 20-May-19
Brie escri on of Changes:
Per the request from the City and the attached R.FP 003, PLW is proposing to furnish and install the specified
Endress+[causer radar type level transmitters and local readout, in order to match the City of Baytown's
Instrumentation. The radar type level transmitters will replace the originally designed ultrasonic level transmitters
and transducers per the request. The equipment identifiers will remain the same as originally designed. Please see the
attached back-up documentation.
Additionally, per the request front the City, PLW is proposing to develop install and configure a complete and
functional SCADA System per the Contract Documents, as outlined by the EOR/City.
Add or Delete Items:
Item UescriRttion Unit DuLntity
CO 6.1 Radar Type Level Instruments LS 1
CO 6.2 SCADA Programming and Coordination LS 1
1 Original Contract Price
2 Owner Contingency
Previous Change Orders
This Change Order
Remaining Contingency
3 IChange Orders _
Previous Change Orders
This change order
4 Revised Contract Price
Unit Price
4,340.10 $
546,559.20 $
Total
4,340.1
546,559.
$ 550,899.30
Original Revised
r� f $ 52,186,000.00
Original Contract Duration
1095
Previous Extensions
0
This Change Ord
0
Revised Durat' Calendar Days
1095
$ (4,166,532.1
$ 550,899
$ 52,186,000.00 $ 48,570,367
r-I/ May 21, 2019
Contractor: PLW terworks, LLC Date Engineering Director Date
Emilio Lopez P t
tti, Executive Vice President
Consultant: Jones) -arter, Inc. Da tCity Manager Date
5/2.8/2a 19