Ordinance No. 14,105ORDINANCE NO. 14,105
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
ACCEPTING THE SAN JACINTO LIFT STATION PROJECT; AUTHORIZING FINAL
PAYMENT OF THE SUM OF FORTY-FOUR THOUSAND NINE HUNDRED THIRTY-
SEVEN AND 761100 DOLLARS ($44,937.76) TO PELTIER BROTHERS CONSTRUCTION,
LTD, FOR SAID PROJECT; AND PROVIDING FOR THE EFFECTIVE DATE THEREOF.
********************************************************************************************
WHEREAS, the City of Baytown contracted with Peltier Brothers Construction, Ltd, for the San Jacinto
Lift Station Project (the "Project"); and
WHEREAS, all of the said improvements, as provided in the plans and specifications heretofore prepared
by the City's engineer and as approved and adopted by the City Council, have been performed and completed in full
accordance with all of the terms and conditions of the aforesaid contract; and
WHEREAS, the City's engineer, in the manner provided by the terms of the said contract and the plans and
specifications thereof, has approved the San Jacinto Lift Station Project, has heretofore issued his Certificate of
Final Acceptance, has certified same to the City Council, and has recommended that it accept and receive said work
and improvements as constructed and completed by the contractor; and
WHEREAS, there remains due and owing to Peltier Brothers Construction, Ltd, the sum of FORTY-FOUR
THOUSAND NINE HUNDRED THIRTY-SEVEN AND 76: 100 DOLLARS ($44,937.76); NOW THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the City Council of the City of Baytown hereby accepts and approves the above -
described work and improvements, and finds and determines that all of said improvements have been completed as
provided in the plans and specifications thereof, and in full accordance with all of the terms and provisions of the
aforesaid contract.
Section 2: That the Certificate of Final Acceptance heretofore issued by the City's engineer and
certified to the City Council is hereby accepted and received.
Section 3: That final payment to Peltier Brothers Construction, Ltd, in the amount of FORTY-FOUR
THOUSAND NINE HUNDRED THIRTY-SEVEN AND 76 100 DOLLARS ($44,937.76) is hereby authorized.
Section 4: This ordinance shall take effect immediately from and after its passage by the City Council
of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the City of Baytown
this the 271h day of June, 2019. '
��^QC�
BRANDON CAPETILLO, Ayor
ATT
LE ICIA BRYSCH, City erk ��s•..•;.os�,
%
0,
►- 4 /l t U.
APPROVED AS TO FORM:
r ° .
NACIO RAMIltEZ, SR., C' Attorney
R:`.Karen Files',City Council Ordinances\2019Vune 27\FinalPay4SanJacintoLiftStationProject.doc