Ordinance No. 1,966trtO
ORDINANCE NO.1966
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OFBAYTOWN,
TEXAS,AUTHORIZING A CHANGE ORDER TO THE CONTRACT WITH
KATY ENGINEERING COMPANY FOR THE ENLARGEMENT OF THE
EAST DISTRICT SEWAGE TREATMENT PLANT,AND PROVIDINGFOR
THE EFFECTIVE DATE HEREOF.
BE IT ORDAINED BYTHECITY COUNCIL OF THE CITY OF
BAYTOWN,TEXAS:
Section 1:That the City Council does hereby authorize
a change order to the contract with Katy Engineering Company
for the enlargement of the East District Sewage Treatment
Plant.A copy of said change order is attached hereto,
marked Exhibit "A,"and made a part hereof for all intents
and purposes.
Section 2:This ordinance shall take effectfrom and
after the date of its passage by the affirmative vote of the
City Council of the City of Baytown.
INTRODUCED,READ and PASSED by the affirmative vote of
a majority of the City Council of the City of Baytown this
11th day of March,1976.
TOM GENTRY,Mayor \/
ATTEST:
EILEEN P.HALL,City Clerk
APPROVED:
NEEL
5504
EXHIBIT "A"
/#*s /«i£505
CHANGE ORDER NO.1
March 5,1976
Mayor and City Council
City of Baytown
P.O.Box 424
Baytown,Texas 77520
Subject:Addition of Sludge Drying Beds and Chlorination Facil-
ities at the East District Sewage Treatment Plant.
Contractor:Katy Engineering Co.
Contract Dated:October 15,1975
Original Contract Amount:$1,633,330.00
Project:Construction of Enlargement of East District Sewage
Treatment Plant,Job No.44B Contract No.1,WPC-Tex-
1048.
Gentlemen:
Pursuant to your authorization of February 12,1976 we have pre
pared this Change Order,for addition of sludge drying beds,
chlorination facilities and revisions to the waste sludgepumps
at the East District Sewage Treatment Plant.The total cost of
these facilities are as listed below,with the attached letters
showing the complete breakdown of each item,in accordance with
current federal regulations.The sludgedryingbeds shall be
constructed within eight weeks after authorization is given to
proceed and the chlorination facilities shall be installed as
soon as the various items of equipment can be obtained (after
submittals have been approved).The attached drawings (Sheets
1 thru 4 of Change Order No.1)show the details of the work
to beaccomplished,as outlined below:
Description Cost
Construction of 8 additional sludge drying
beds,as per the attached drawings,(Sheets
1 and 2),and proposal No.5621-3 of Katy
Engineering Co.,dated March 3,1976 -$84,917.00
2.Construction of additional chlorination
facilities,as per the attached drawing,
(Sheet 3),and proposal No.5621-4 ofKaty
Engineering Co.dated March 3,1976 -$13,370.00
506
Mayor and City Council -2-March 5,1976
Item
No.
3.
Description
Revisions to waste sludge pumps,as per
the attached drawing,(Sheet 4),and pro
posed No.5621-1 of Katy Engineering Co.,
dated March 3,1976 -
Cost
850.00
TOTAL COST CHANGE ORDER NO.1 $99,137.00
This represents an increase of (+)6.07%in the original contract
amount.This work will require an extension in contract time of
90 calendar days,which will make the revised completion date
January 25,1977,in lieu of the original completion date of
October 27,1976.
RECOMMENDED FOR APPROVAL:
LANGFORD ENGINEERING,INC.
ACCEPTED:
KATY ENGINEERING CO.
Robert W.McDaniel,P.E.
Vice President
APPROVED:
CITY OF BAYTOWN
Date =_^C/'J
By:
Fritz Lanham,City Manager
Date: