Ordinance No. 1,955ORDINANCE NO.1955
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS APPROVING AND ACCEPTING THE CONSTRUCTION OF
ROLLINGBROOK DRIVE BRIDGES BY HANNA CONSTRUCTION COMPANY
FINDING THAT THE WORK HAS BEEN PERFORMED IN ACCORDANCE
WITHTHE TERMS OF THE CONTRACT;ACCEPTING THE CITY'S
CONSULTING ENGINEERS'CERTIFICATE OF FINAL ACCEPTANCE;
AUTHORIZING THE FINAL PAYMENT TO THE SAID HANNA CON
STRUCTION COMPANY AND PROVIDING FOR THE EFFECTIVE DATE
HEREOF.
WHEREAS,the City of Baytown contracted with Hanna
Construction Company for the construction of Rollingbrook
Drive Bridges;and
WHEREAS,all of the said work,as provided for in the
plans and specifications heretofore prepared by the Consulting
Engineers,Busch,Hutchison &Associates,Inc.,and as
approved and adopted by the City Council,has been performed
and completed in full accordance with all of the terms and
provisions of the aforesaid contract;and
WHEREAS,the City's Consulting Engineers in the manner
provided by the terms of the said contract andthe plans and
specifications thereof,have approved and accepted said work
and have heretofore issued their Certificate of Final Accep
tance,and have certified same to the City Council and
recommended that it accept and receive said work as constructed
and completed by the said Hanna Construction Company;and
WHEREAS,there remains and owing to said contractor the
sum of Fourteen Thousand Six Hundred Seventy-Three and
98/100 ($14,673.98)Dollars,thesum of One Hundred Twenty-
Seven Thousand Three Hundred Twelve and 2/100 ($127,312.02)
Dollars heretofore advanced to Contractor in partial payments
under the provisions of the said contract;NOW THEREFORE,
BE IT ORDAINED BYTHE CITY COUNCIL OF THE CITYOF
BAYTOWN,TEXAS:
Section 1:That the City Council hereby approves and
accepts said work,and finds and determines that all of said
work has been completed as provided in the plans and speci
fications therefore,and in full accordance with all of the
terms and provisions of the aforesaid contract.
Section 2:Thatthe Certificate of Final Acceptance
heretofore issued by the Consulting Engineers and certified
to the City Council is hereby accepted andreceived.
Section 3:That finalpayment to thesaid Hanna
Construction Company in the amount of Fourteen Thousand Six
Hundred Seventy-Three and 98/100 ($14,673.98)Dollars is
hereby authorized and directed.
Section 4:This ordinance shall take effect from and
after its passage by the City Council of the City of Baytown,
Texas.
INTRODUCED,READ and PASSED by the affirmative vote of
the City Council of the City of Baytown this26th day of
February,1976.
TOM GENTRY,Mayor \/
ATTEST:
EILEEN P.HALL,City Clerk
APPROVED:
NEEC RICHARDSON,City Attorney
-2-