Ordinance No. 13,655ORDINANCE NO. 13655
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
APPROVING THE CONSTRUCTION CONTRACT BETWEEN BAYTOWN AREA WATER
AUTHORITY AND PEPPER LAWSON WATERWORKS, LLC, FOR THE BAWA 6 MGD
SURFACE WATER TREATMENT PLANT PROJECT AND APPROVING CHANGE ORDER
NO. 1 FOR SUCH PROJECT; AND PROVIDING FOR THE EFFECTIVE DATE THEREOF.
****************************************************************************************************
WHEREAS, the Baytown Area Water Authority's enabling legislation requires that the City Council approve the
agreement before Baytown Area Water Authority (`BAWA") enters into the same; and
WHEREAS, on December 6, 2017, the Board of Directors of BAWA approved a construction contract
with Pepper Lawson Waterworks, LLC, for the BAWA 6 MGD Surface Water Treatment Plant Project and approved
Change Order No. 1 for such project; and
WHEREAS, the City of Baytown desires to approve such agreement; NOW THEREFORE,
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the recitals set forth hereinabove are hereby found to be true and correct and are hereby
adopted.
Section 2: That the City Council of the City of Baytown, Texas, hereby approves the construction contract
between the Baytown Area Water Authority and Pepper Lawson Waterworks, LLC, for the BAWA 6 MGD Surface
Water Treatment Plant Project and approves Change Order No. 1 for such project, which change order is attached hereto
as Exhibit "A" and incorporated herein for all intents and purposes.
Section 3: This ordinance shall take effect immediately from ander its passage by the City Council of
the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the�C Councilofthe City of Baytown this the
14°i day of December, 2017. 1
ATT T:
LETICIA BRYSCH, City Clerk
APPROVED AS TO FORM:
a
NACIO RAMIREZ, SR., V
Attomey
DONCARLOS, Mayor
.cobfsOI.legalUCaren\Files',CityCouncillOrdinances\201TDecember WApprovingBEAST.doc
EXHIBIT A
Baytown Area Water Authority
,--JOT �V_ Change Order No. 1
6 MGD Surface Water Treatment Plant
Brief Description of Changes:
This change order is issued as value engineering options for the BAWA 6 MGD Surface Water Treatment Plant
Add or Delete Items:
Item
Description
Unit
Quantity
Unit Price
Total
1
Remove lime stabilized Fill Materials from
Roads
1
(275,000.00)
$ (275,000.00)
2
Eliminate earthwork at all future structures
1
(1,200,000.00)
$ (1,200,000.00)
3
Substitute concrete pavement with crushed
concrete pavement at non main drive and
roads
48,242
1
i
(110,000.00)
$ (110,000.00)
4
Delete Concrete Pavement
18000
1
(90,000.00)
$ (90,000.00)
5
Remove Clay Liner from forebay
1
(125,000.00)
$ (125,000.00)
6
delete scope associated with second lagoon
1
(75,000.00)
$ (75,000.00)
7
Delete horizontal control joints to allowed for
continuous pour walls
1
(15,000.00)
$ (15,000.00)
8
delete backwash clarifier
1
(650,000.00)
$ (650,000.00)
9
delete maintenance building
1
(850,000.00)
$ (850,000.00)
10
Change 5 Type "D" Manholes to Type C
1
(72,000.00)
$ (72,000.00)
11
Eaton Vs. Square D package
1
(333,600.00)
$ (333,600.00)
12
Delete redundant feeder and transformer
1
(610,000.00)
$ (610,000.00)
13
Delete generator and gear
1
(1,658,000.00)
$ (1,658,000.00)
14
Change ductbank concrete from 3000psi to
2000psi
1
(30,000.00)
$ (30,000.00)
1ota1 $ (6,093,600.00)
Contract Summary
Original Contract Price
$ 52,186,000.00
Previous Change Orders
$
This Change Order
$ (6,093,600.00)
Revised Contract Price
$ 46,092,400.00
Original Contract Duration - 1095
Previous Time Extensions 0
This Change Order 0
Revised Contract Duration - Calendar Days 1095
Pepper Lawson
Date
Director of Finance Date
Consultant
City Engineer Date
General Manager
Date