Ordinance No. 13,529ORDINANCE NO. 13,529
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS, AUTHORIZING CHANGE ORDER NO. 1 WITH E.P. BRADY LTD,
FOR THE PARTIAL SERVICE AREA DIVERSION TO THE NORTHEAST
WASTEWATER TREATMENT PLANT SERVICE AREA ALTERNATIVE
PROJECT, IN THE AMOUNT NOT TO EXCEED FIVE HUNDRED NINETY-
THREE THOUSAND FOUR HUNDRED FIFTY-SIX AND 10/100 DOLLARS
($593,456.10); AND PROVIDING FOR THE EFFECTIVE DATE THEREOF.
******************************************************************************
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the City Council does hereby authorize Change Order No. 1 with E.P.
Brady Ltd, for the Partial Service Area Diversion to the Northeast Wastewater Treatment Plant Service Area
Alternative Project. A copy of said change order is attached hereto, marked Exhibit "A" and made a
part hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby authorizes the payment in
an amount not to exceed FIVE HUNDRED NINETY-THREE THOUSAND FOUR HUNDRED
FIFTY-SIX AND 10/100 DOLLARS ($593,456.10) to E.P. Brady Ltd, for the change order
authorized in Section 1 hereinabove.
Section 3: This ordinance shall take effect immediately from and after its passage by the
City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of City Council of the City
of Baytown this the 27th day of July, 2017.
AT -TEST:
� V
LETICIA BRYSCH, City i3lbrk
APPROVED AS TO FORM:
[JA
CHRIS PRESLEY, Mayor Pro Tem
C: Users\Karcn.Homer\DesktopUuly 271ChangeOrderNol forPartialServiceAreaDiversionNEWWTPServiceAreaaltemativeProject.doc
Exhibit "A"
CITY OF BAYTOWN
Change Order No.1
BMTOWNPartial Service Area Diversion to the Northeast
Wastewater Treatment Plant Service Area Alternative
7/19/2017
PO: 1706985
Brief Description of Changes:
Additional work to include limits of sanitary sewer included in Contract A.
Add or Delete Items:
Item
Description
Unit
Quantity
Unit Price
Total
1
Mobilization
LS
1
$ 35,000.00
$ 35,000.00
2
Flagmen
LS
1
$ 17,500.00
$ 17,500.00
3
Traffic Control and Regulation
LS
1
$ 17,500.00
$ 17,500.00
4
Storm Water Pollution Prevention
LS
1
$ 500.00
$ 500.00
5
Control of Groundwater
LS
1
$ 40,000.00
$ 40,000.00
7
Site Restoration
LS
1
$ 7,500.00
$ 7,500.00
8
Trench Excavation Protection
LS
1
$ 500.00
$ 500.00
5 -foot Diameter FM discharge manhole (STA
13
12+51)
EA
1
$ 9,000.00
$ 9,000.00
5 -foot Diameter Manhole (STA 12+91 and
14
STA 15+41)
EA
2
$ 4,215.00
$ 8,430.00
Extra Depth 5 -foot Diameter Manhole (STA
15
12+91 and STA 15+41)
7
$ 167.00
$ 1,169.00
18
6 -inch Manhole Drop Connection (STA 12+91)
EA
1
$ 1,480.00
$ 1,480.00
19
8 -inch Manhole Drop Connection (STA 15+41)
EA
1
$ 1,675.00
$ 1,675.00
6 -inch Inside Diameter Gravity Sanitary
32
Sewer by Open Cut Construction (STA 12+9)
LF
18
$ 211.00
$ 3,798.00
8 -inch Inside Diameter Gravity Sanitary
33
Sewer by Open Cut Construction (STA 15+41)
LF
20
$ 110.00
$ 2,200.00
10 -inch Diameter Sanitary Sewer Force Main
35
by Open Cut Construction (STA 12+40)
LF
25
$ 125.00
$ 3,125.00
24 -inch Diameter Gravity Sanitary Sewer Pipe
in 36 -inch Steel Casing, All Depths by
41
Trend -less Construction at Roadway and
LF
60
$ 1,354.15
$ 81,249.00
Driveway Crossings
Dotal
Contract Summary
593,456.10
Original Contract Price
24 -inch Diameter Gravity Sanitary Sewer in
$ 3,319,754.10
Previous
$
This Change Order
$ 593,456.10
36 -inch Steel Casing by Open Cut
$ 3,913,210.20
42
Construction up to 10 feet depth (top of pipe)
LF
293
$ 971.70
$ 284,708.10
(STA 12+51 to STA 16+04)
Temporary Plug 6 -inch Sanitary Sewer (STA
43
12+91)
EA
1
$ 245.00
$ 245.00
Temporary Plug 10 -inch Sanitary Sewer Force
44
Main (STA 12+40;STA 15+30;STA 16+20)
EA
3
$ 245.00
$ 735.00
Temporary Plug 24 -inch Sanitary Sewer (STA
45
16+18)
EA
1
$ 600.00
$ 600.00
10 -inch Inside Diameter Sanitary Sewer Force
46
Main with 18 -inch Steel Casing by Trenchless
LF
145
$ 480.00
$ 69,600.00
Construction (STA 11+00 to STA 12+51)
Remove Pavement and Install Temporary
47
Crushed Concrete
SY
267
$ 26.00
$ 6,942.00
Dotal
Contract Summary
593,456.10
Original Contract Price
$ 3,319,754.10
Previous
$
This Change Order
$ 593,456.10
Revised Contract Price
$ 3,913,210.20
Original Contract Duration
217
Previous Extensions
0
This Change Order
90
Revised Duration - Calendar Days
307
Contractor: EP Brady, Ltd.
Date 7/19/17
Engineering Director
Consultant: KIT Professionals, Inc. Date 7/19/17 City Manager
Date
Date