Ordinance No. 13,318ORDINANCE NO. 13,318
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN,
TEXAS, AUTHORIZING CHANGE ORDER NO. 1 WITH SKE
CONSTRUCTION, LLC, FOR THE GARTH ROAD WATERLINE
REHABILITATION PROJECT, IN THE AMOUNT OF TWO HUNDRED SIXTY -
FIVE THOUSAND SEVEN HUNDRED SIXTY -TWO AND 81/100 DOLLARS
($265,762.81); AND PROVIDING FOR THE EFFECTIVE DATE THEREOF.
*********************************************** * * * * * * * * * * * * * * * * * * * * * * * * * * * * * **
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the City Council does hereby authorize Change Order No. 1 with SKE
Construction, LLC, for the Garth Road Waterline Rehabilitation Project, A copy of said change
order is attached hereto, marked Exhibit "A" and made a part hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby authorizes the payment in
an amount of TWO HUNDRED SIXTY -FIVE THOUSAND SEVEN HUNDRED SIXTY -TWO
AND 81/100 DOLLARS ($265,762.81) to SKE Construction, LLC, for the change order authorized
in Section 1 hereinabove.
Section 3: This ordinance shall take effect immediately from and after its passage by the
City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative voof the City Council of the City
of Baytown this the 13th day of October, 2016. \,
ATT ST:
L TICIA BRYSCH, Ci Clerk
APPROVED AS TO FORM:
ACID RAMIREZ, SR., Ci Attorney
S,7EPHEN H. DONCARLOS,
6
p(TOWAl '
01 ~•~ T
h
�Or�TE OF
1lcobfs0lllegal\Karen\Files.City Council. Ordinanccs\2016 October 13` ChangeOrderNol4GarthRoadWaterlineRehabilitationProject .doc
Exhibit "A"
CITY OF BAYTOWN
Change Order No.1
Gat-th Rd Waterline Rehabilitation
BAYS 8/31/2016
Brief Description of Changes:
This change order is necessary due to unforeseen conditions, which require the directional drilling method in lieu of pipe bursting, to place the new
water line below all existing utilities and pipelines. The drilling will be from the intersection of Garth Road and Cedar Bayou Lynchburg to the
southern limits of the adjacent pipeline corridor (located just south of Cedar Bayou Lynchburg).
Add or Delete Items:
Item
Description
Unit
Quantity
Unit Price
Total
1
T6", install pipe burst HDPE pre chlorinated water line, upsize 12 to 16",
complete in place
LF
-963
181.00
$ (174,303.00)
2
12 , install pipe burst prechionnated water line, in place of same of
one size smaller water line, complete in place
LF
-15
109.00
$ (1,635.00)
3
12" flow stop, complete in place
EA
-2
9,850.00
$ (19,700.00)
4
3/4" service tap, install on 12 " -16" waterline, complete in place
EA
-14
1,050.00
$ (14,700.00)
5
1" service tap, install on 8 " -16" water line, complete in place
EA
0
1,200.00
$
6
1.5" service tap, install on 8 " -16" water line, complete in place
EA
3
1,425.00
$ 4,275.00
7
2" service tap, install on 8 " -16" water line, complete in place
EA
-2
2,225.00
$ (4,450.00)
8
Reconnect service -short & long side, all depths
EA
-18
749.00
$ (13,482.00)
9
Extra length for service laterals after 10'
LF
-170
11.00
$ (1,870.00)
10
Install 16" tee, to any size, complete in place
EA
8
3,250.00
$ 26,000.00
11
Install 4" to 8" tee, to any size, complete in place
EA
-2
2,200.00
$ (4,400.00)
12
Extra Cement stab. Sand backfill 2.0 sacks /tn
TON
- 307.39
33.00
$ (10,143.87)
13
Point rpr /obst. Rmv - pipe bursting, all depths
EA
-7
1,275.00
$ (8,925.00)
14
Well point, all depths, extra length over 20 LF
EA
-3
2,300.00
$ (6,900.00)
15
Well point, all depths, extra length over 20LF
LF
-82
29.00
$ (2,378.00)
16
Trench safety, all depths
LF
757
11.00
$ 8,327.00
17
Install 16" mechanical joint wet connection, to any size, complete in place
EA
6
3,550.00
$ 21,300.00
18
Install 10" wet connection to any size, complete in place
EA
-2
2,000.00
$ (4,000.00)
19
Install 12" wet connection to any size, complete in place
EA
3
2,685.00
$ 8,055.00
20
Install 12" tapping sleeve, to any size, complete in place
EA
-4
3,875.00
$ (15,500.00)
21
Install 16" tapping sleeve, to any size, complete in place
EA
-1
4,000.00
$ (4,000.00)
22
Install 16" gate valve and valve box, complete in place
EA
-7
9,800.00
$ (68,600.00)
23
Post TV Inspection - included tapes and written report (to verify no
sewer line damage from laterals)
LF
-1000
1.00
$ (1,000.00)
24
Relocate mailboxes, road signs, etc, as necessary to accomplish work
EA
-3
200.00
$ (600.00)
25
Rmv /rpl up to 5" concrete sidewalk /driveway (includes saw cutting,
reinforcement)
SY
-200
129.00
$ (25,800.00)
26
Rmv /rpl up to 8" concrete sidewalk /driveway /pavement (incl. saw cut,
reinf., base repair)
SY
-243
168.00
$ (40,824.00)
27
Rmv /rpl up to 2" HMAC, Type D (incl. saw cut, tack, coat, base repair)
SY
-96
115.00
$ (11,040.00)
28
1" rock with no fines for bedding (incidental to point repairs)
TON
108.49
32.00
$ 3,471.68
29
Annular and void space grouting
CY
-50
85.00
$ (4,250.00)
30
Sodding
SY
1050
5.00
$ 5,250.00
31
Remove and replace Fire Hyddant assmebly, to include gate valve and bo
EA
-4
3,100.00
$ (12,400.00)
32
Install new Fire Hydrant assembly, to include gate valve and box,
complete in place
EA
5
6,000.00
$ 30,000.00
33
Insertion Valves (6" thru 8 ")
EA
5
8,190.00
$ 40,950.00
34
Insertion Valves (10" thru 12 ")
EA
3
13,650.00
$ 40,950.00
35
16" Connection to 30" (Hanson) BAWA Transmission line
LS
0
72,525.00
$ -
36
Contingency allowance (to be used at the direction of the City Engineer) I
LS
- 0.44895
100,000.00
$ (44,895.00)
Pothole and exploratory digging
LS
2
20,000.00 1
$ 40,000.00
Total $ 265,762.81
Original Contract Price $ 1,260,945.00
Previous $
This Change Order $ 265,762.81
Revised Contract Price $ 1,526,707.81
Original Contract Duration 240
Previous Extensions 365
This Change Order 0
Revised Duration - Calendar Days 605
Contractor
Date
Engineering Director Date
Consultant Date City Manager Date
Drill 16" HDPE
LF
1270
339.00
$ 430,530.00
24" Steel Casing at Pipeline
LF
130
75.00
$ 9,750.00
16" Insertion Valve
EA
2
34,000.00
$ 68,000.00
Relocate/Replace Shipley's Donut sign
EA
1
15,000.00
$ 15,000.00
8" MJ gate valve
EA
2
2,750.00
$ 5,500.00
12" MJ Gate Valve
EA
1
4,200.00
1 $ 4,200.00
Total $ 265,762.81
Original Contract Price $ 1,260,945.00
Previous $
This Change Order $ 265,762.81
Revised Contract Price $ 1,526,707.81
Original Contract Duration 240
Previous Extensions 365
This Change Order 0
Revised Duration - Calendar Days 605
Contractor
Date
Engineering Director Date
Consultant Date City Manager Date