Ordinance No. 13,187ORDINANCE NO. 13,187
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
AUTHORIZING CHANGE ORDER NO. 3 WITH INLAND ENVIRONMENTS, LTD,
FOR THE DEMOLITION OF 1105 DECKER DRIVE, IN AN AMOUNT NOT TO
EXCEED ONE HUNDRED SIXTY -TWO THOUSAND FOUR HUNDRED EIGHTY -
THREE AND 50 1100 DOLLARS ($162,483.50); AND PROVIDING FOR THE
EFFECTIVE DATE THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the City Council does hereby authorize Change Order No. 3 with Inland
Environments, LTD, for the demolition of 1105 Decker Drive. A copy of said change order is attached hereto,
marked Exhibit "A" and made a part hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby authorizes the payment in an
amount not to exceed ONE HUNDRED SIXTY -TWO THOUSAND FOUR HUNDRED EIGHTY -THREE
AND 50 1100 DOLLARS ($162,483.50) to Inland Environments, LTD, for the change order authorized in
Section 1 hereinabove.
Section 3: This ordinance shall take effect immediately from and after its passage by the City
Council of the City of Baytown. 11-2
INTRODUCED, READ and PASSED by the affirmative vote o',Clie City Council of the City of
Baytown this the 26`'' day of April, 2016. z
"ST:
APPROVED AS TO FORM:
JN"ACIO RAMIREZ, SR., Attorn ey
. DONCARLOS, Mayor
�o�Op,YTO{NN rF�
ca ff •�•�N
i
RAKarenTiles.City Council.Ordinances\20l6\Apol 26'. ChangeOrderNo34SanJacintoDemolition .doc
Exhibit "A"
CITY OF BAYTOWN
Change Order No. 3
1105 Decker Drive
BAYTOWN 4/28 /2016
S
Brief Description of Changes:
This change order removes the demolition of the parking lot from the scope of work and adds fill material to backfill
the basement, crawlspace and grade entire site (excluding parking areas) to drain properly.
Add or Delete Items:
Item
Description
Unit
Quantity
Unit Price
Not to Exceed
1
Remove cost to demolish the parking lot -
162,482.60
Revised Contract Price (not to exceed)
$
895,598.60
Asphalt
SF
110,545
$ (0.10)
$ (11,054.50)
2
Remove cost to demolish the parking lot -
Concrete
SF
42,746
$ (0.15)
$ (6,411.90)
3
Additional till material-to backtill basement,
crawlspace and grade entire site (excluding
parking areas) to drain properly (Note: Total
quantity/cost reflects a "not to exceed "
amount
CY
12,853.5
$ 14.00
$ 179,949.00
4
$ -
5
$ -
6
$ _
7
$ _
Total
Contract Summary_:
162,482.60
Original Contract Price
$
716,482.00
Previous Change Orders
$
16,634.00
This Change Order (not to exceed)
$
162,482.60
Revised Contract Price (not to exceed)
$
895,598.60
Original Contract Duration
112
Previous Extensions
0
This Change Order
0
Revised Duration - Calendar Days
112
Contractor Date Planning Director Date
Director of Finance Date
City Manager Date