Ordinance No. 12,926ORDINANCE NO. 12, 926
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
AUTHORIZING AND DIRECTING THE CITY MANAGER AND CITY CLERK TO
EXECUTE AND ATTEST TO A CONTRACT WITH LEM CONSTRUCTION CO.,
INC., FOR THE CDBG NON - HOUSING CENTRAL DISTRICT WASTEWATER
TREATMENT PLANT FLOOD IMPROVEMENTS PROJECT; AUTHORIZING
CHANGE ORDER NO. 1 WITH LEM CONSTRUCTION CO., INC, FOR SAID
PROJECT AUTHORIZING PAYMENT OF A SUM OF SIXTEEN MILLION ONE
HUNDRED EIGHTY THOUSAND SEVEN HUNDRED AND NO /100 DOLLARS
($16,180,700.00); AUTHORIZING MAKING OTHER PROVISIONS RELATED
THERETO; AND PROVIDING FOR THE EFFECTIVE DATE THEREOF.
****************************************************** * * * * * * * * * * * * * * * * * * * * * * * * * * * * * **
WHEREAS, the City Council of the City of Baytown did advertise for bids for the CDBG Non -
Housing Central District Wastewater Treatment Plant Flood Improvements Project to be received on
February 24, 2015; and
WHEREAS, notice to bidders as to the time and place, when and where the bids would be
publicly opened and read aloud was published pursuant to provisions of Texas Local Government Code
Annotated § 252.041; and
WHEREAS, all bids were opened and publicly read at City Hall at 2:00 o'clock p.m., Tuesday,
February 24, 2015, as per published notice to bidders; NOW THEREFORE
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That subject to the Change Order authorized in Section 2 hereof, the City Council
of the City of Baytown hereby accepts the bid of LEM Construction Co., Inc., for the CDBG Non -
Housing Central District Wastewater Treatment Plant Flood Improvements Project according to the plans
and specifications set forth by the City's engineer, and the City Manager and the City Clerk of the City
are hereby authorized and directed to execute and attest to a contract with LEM Construction Co., Inc.,
for the above - described project, said contract containing the plans, specifications, and requirements of the
City's engineer and appropriate bond requirements in accordance with the provisions of Texas
Government Code, Chapter 2253.
Section 2: That the City Council does hereby authorize Change Order No. 1 with LEM
Construction Co., Inc., for the CDBG Non - Housing Central District Wastewater Treatment Plant Flood
Improvements Project. A copy of said change order is attached hereto, marked Exhibit "A" and made a
part hereof for all intents and purposes.
Section 3: That the City Council hereby authorizes payment of an amount not to exceed
SIXTEEN MILLION ONE HUNDRED EIGHTY THOUSAND SEVEN HUNDRED AND NO /100
DOLLARS ($16,180,700.00) based upon the unit prices specified in the bid together with the additions
and reductions in Change Order No. 1 authorized in Section 2 hereof.
Section 4: That pursuant to the provisions of Texas Local Government Code Annotated
§ 252.048, the City Manager is hereby granted general authority to approve any change order involving a
decrease or an increase in costs of FIFTY THOUSAND AND N01100 DOLLARS ($50,000.00) or less,
subject to the provision that the original contract price may not be increased by more than twenty -five
percent (25 %) or decreased by more than twenty -five percent (25 %) without the consent of the contractor
to such decrease.
Section 5: This ordinance shall take effect immediately from and
City Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote of the
Baytown this the 13`h day of August, 2015. r
4 ST:
ETICIA "BRYSCH, o
APPROVED AS TO FORM:
S
passage by the
Council of the City of
Mayor
R:Xareo•.Files +.City CounciLOrdinances\2015Wugust 13W wardCDBGNon- HousingCentralDistrictWastewaterTreatmentP lant FloodlmprovementsProject.doc
2
oc
�
y1'
passage by the
Council of the City of
Mayor
R:Xareo•.Files +.City CounciLOrdinances\2015Wugust 13W wardCDBGNon- HousingCentralDistrictWastewaterTreatmentP lant FloodlmprovementsProject.doc
2
Exhibit "A"
Texas General Land Office
Disaster Recovery
Construction Contract Change Order Request Form
Engineer
Owner (Contractor Locality):
Contractor:
KIT Professionals. Inc
City of Baytown
LEI-I Construction Company, Inc
2000 VV Sam Houston Pkwy S
2401 Market Street
10849 Kinghursl
Suite 1400
Baytown Texas 77522
Suite 150
Houston Texas 77042
Phone No.:(281) 420 -5311
Houston, Texas 77099
Phone No.:(713) 783 -8700
Agreement Date:
Phone No.:(281) 495 -9550
Date: July 30, 2015
Contract For (Project Description):
GLO Contract No.
Project Code No.:
Central District Wastewater
Treatment Plant Flood
Improvements Project
Bid Package No.:1
Change Order No.: 1
You are hereby requested to comply with the following changes from the contract plans and specifications
Item
Description of Changes Quantities, Units, Unit Prices.
Decrease in
Increase in
No
Change in Completion Scheduled, Etc
Contract Price
Contract Price
1
Delete Extra Unit Price Bid Items No 2 through No
$321,675
-
30 as noted in Section 2.0 of the Bid Form and
Section 01 -22 -13 Measurement and Payment
2
Reduce Allowance No. 1 for Laboratory Appliances.
$235.000
as noted in Section 3.0 of the Bid Form and Section
01 21 00 Allowances, from $250,000 to $15,000
3
Delete Allowance No. 2 as noted in Section 3.0 of the
$500,000
Bid Form and Section 01 21 00 Allowances
Delete Add Alternative No. 1 for No. 41 Texas Avenue
$530,000
-
4
Lift Station Improvements as noted in Section 4.0 of
the Bid Form and Section 01 -22 -13 Measurement and
Payment
5
Delete Add Alternative No. 2A for No. 46 Country
$390,000
Club Lift Station Improvements as noted in Section
4.0 of the Bid Form and Section 01 -22 -13
Measurement and Payment
6
Delete Add Alternative No 2B for Diesel Driven Pump
$85,000
at No. 46 Country Club as noted in Section 4.0 of the
Bid Form and Section 01 -22 -13 Measurement and
Payment
7
Delete Add Alternative No. 3A for Rollingbrook Lift
$290,000
-
Station Improvements as noted in Section 4.0 of the
Bid Form and Section 01 -22 -13 Measurement and
Payment
8
Delete Add Alternative No 3B for Diesel Driven Pump
$80,000
at Rollingbrook as noted in Section 4.0 of the Bid
Form and Section 01 -22 -13 Measurement and
Payment
9
Delete Add Alternative No. 4A for No. 73 Country
$260,000
-
Club Estates Lift Station Improvements as noted in
Section 4.0 of the Bid Form and Section 01 -22 -13
Measurement and Payment
10
Delete Add Alternative No. 4B for Diesel Driven Pump
$80.000
at No 73 Country Club Estates as noted in Section
4.0 of the Bid Form and Section 01 -22 -13
Measurement and Payment
11
Delete requirement for 6,000 pound capacity Freight
$250.000
-
Elevator at Administration Building, as specified in
Section 14 21 00 MRL Freight Elevator, and replace it
with pedestrian rated elevator and mechanism to
remove blowers A $50,000 allowance for changes
required for the mechanism to remove the blowers is
included.
12
Change requirement for stairway on west end of
$10,300
-
Blower Building, as specified in Section 05 51 13
Metal Pan Stairs and detailed on Drawing AO -4
Typical Details, and change to a steel stairway, as
specified in Section 05 51 00 Pre - Engineered Steel
Stairs and detailed on drawing SO -2 Typical Details
and change all tread nosing to checkered plate and
handrail reinforcing to hollow tube.
13
Delete replacement of blower intake and discharge
$38,000
-
butterfly valves and discharge check valves
14
Delete motor operator on 10'x10' overhead door 100C
$3,467
in Blower Building as specified in Section 08 33 23
Overhead Coiling Doors, Part 2.1.A.3
15
Delete clarifier scum collector and RAS trough
$717,000
-
modifications for Secondary Clarifier No, 1 and
Secondary Clarifier No. 2, including scum beaches,
scum baffle replacement, scum pump station and
associated yard piping.
17
Delete protective coatings for concrete floors and
$31,470
-
trenches in the Disinfection Building as required in
Table 09 91 00 B -3: Painting Schedule and specified
Section 09 96 35 Concrete Toppings
18
Delete required for spark resistant and explosion
$30,000
proof trolly /hoist in the Disinfection Building
19
Delete motorized operators on scrubber ductwork in
$9,600
the Disinfection Building
20
Delete requirement for Unit Heaters UH -3, UH -4, UH-
$11,000
-
5, UH -6, and UH -7 to be explosion proof as specified
on Drawing HO -3 HVAC Schedule
21
Delete protective coatings for concrete floors in the
$26,630
-
Dewatering Building as required in Table 09 91 00 B-
3: Painting Schedule and specified Section 09 96 35
Concrete Toppings
22
Delete motor operators on overhead doors 100A and
$6,933
-
100B in Dewatering Building as specified in Section
08 33 23 Overhead Coiling Doors, Part 2.1.A.3
23
Change material requirement of bar screen to allow
$11,500
for Type 304 stainless steel in lieu of a Type 316
stainless steel with painted steel components, as
specified in Section 46 21 11 Climber -Type Bar
Screen.
24
Delete requirement for screening of influent
$51,500
-
wastewater during the bypass pumping operations
25
Delete grinder (GRD -1), PV -609, PV -610 and all
$29,000
-
associated electrical and instrumentation
26
Add penetration near the top of the sludge digester
-
$4,900
tanks and modify piping so that TSP -01 and TSP -02
discharge near the top of the tanks.
27
Change requirement for buried ductile iron pipe
$7,800
-
fittings as specified in Section 40 05 19 Ductile Iron
Process Pipe from ANSI /AWWA C110 (full body) to
ANSI /AWWA C153 (compact)
28
Change pipe material of PW, DR, NPW, and SAN
$33,000
from ductile iron, as specified in Table 33 05 05 -A
Buried Piping Schedule, to PVC
29
Change joint requirements of 48 -inch diameter CE
$30,100
-
pipe from restrained, as specified in Table 33 05 05 -A
Buried Piping Schedule, to push -on joints
30
Delete requirement for PVC privacy slats in chain -link
$8,600
-
fencing and change requirement of gate operators to
allow for '/2 horsepower motors, as specified in
Section 32 31 00 Fencing
31
Change requirement for aboveground raceways to
$92,300
-
allow for the use of aluminurn raceways
32
Change 24 strand armored fiber optic cable
$24,000
-
requirement, as specified in Section 27 13 23
Communication Optical Fiber Backbone Cabling to 12
strand fiber optic cable
33
Delete VT SCADA software license for blower PLC
$12,000
-
control panel
Change in Contract Price
ACCEPTED-
Change in Contract Time
(Calendar Days)
OWNER
CONTRACTOR
Original Contract Price
$20,381,675.00
Original Contract Time
730 days
Previous Change Order(s)
Net Change From Previous
No. N/A to No. N/A
$0.00
Change Orders
0 days
Contract Price Prior to
Contract Time Prior to
this Change Order
$20,381,675.00
this Change Order
0 days
Net Increase /Decrease of
Net Increase /Decrease of
this Change Order:
($4,200,975.00)
this Change Order.
0 days
Contract Price With all
Contract Time With all
Approved Change Orders:
$16,180,700.00
Change Orders-
730 days
Cumulative Percent Change in Contract Price ( +1 -):
Grantee Contract End Date:
-20.6%
(mm /dd /yy) !
I
Construction Contract Start Date:
Construction Contract End Date
(mm /dd /yy) /
/
(mm /dd /yy) I
I
Reimbursements of costs included in this change order are subject to review by the GLO -DR program
This document may be executed prior to submission for GLO -DR program review, but all parties
involved will be held responsible if the change order or the amendment warranted as a result of
this change order is not in compliance with CDBG or HUD requirements.
RECOMMENDE
ENGINEER
Date b'-4-1
APPROVED.
ACCEPTED-
By:
Y
By:
OWNER
CONTRACTOR
Date,
Date I,,;- I Lf I i
JUSTIFICATION FOR CHANGE
1
Will this Change Order increase or decrease
the number of beneficiaries? ❑ Increase
❑ Decrease CI No Change
If there is a change, how many beneficiaries will be affected?
Total L/M
2
Effect of this change on scope of work ❑ Increase
O Decrease ❑ No Change
3
Effect on operation and maintenance costs ❑ Increase
❑ Decrease 1K No Change
4
Are all prices in the change order dependent upon unit prices
found in the original bid? ❑ Yes EJ No
If "No ", explain The changes are negotiated cost reductions based on scope changes
5 Has this change created new circumstances or environmental
conditions which may affect the project's impact, such as
concealed or unexpected conditions discovered during actual
construction? ❑ Yes 0 No
If "Yes ", is an Environmental Re- assessment required?
6. Is the Texas Commission on Environmental Quality (TCEQ)
clearance still valid? (if applicable) Fx1 Yes ❑ No
7. Is the TCEQ permit approval still valid? (sewer projects only) O Yes ❑ No
8. Are the handicapped access requirements /approval
still valid? (if applicable) 0 Yes ❑ No
9. Are other Disaster Recovery contractual special condition clearance
still valid? O Yes ❑ No
(If no, specify)
NOTE:
* Generally, a cumulative change In the contract price in excess of 25% cannot
be reviewed (18% decrease for counties).