Ordinance No. 12,579 ORDINANCE 12,579
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
AUTHORIZING CHANGE ORDER NO. 1 WITH PM CONSTRUCTION&REHAB,L.P.,
FOR THE 2014 ANNUAL WATERLINE REHABILITATION CONTRACT;
AUTHORIZING PAYMENT BY THE CITY OF BAYTOWN, IN THE AMOUNT OF
TWO HUNDRED FIFTY THOUSAND AND NO/100 DOLLARS ($250,000.00); AND
PROVIDING FOR THE EFFECTIVE DATE THEREOF.
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the City Council does hereby authorize Change Order No. 1 with PM
Construction &Rehab, L.P.,for the 2014 Annual Waterline Rehabilitation Contract. A copy of said change
order is attached hereto, marked Exhibit"A"and made a part hereof for all intents and purposes.
Section 2: That the City Council of the City of Baytown hereby authorizes the payment in an
amount of TWO HUNDRED FIFTY THOUSAND AND NO/100 DOLLARS ($250,000.00) to PM
Construction & Rehab, L.P., for the change order authorized in Section 1 hereinabove.
Section 3: This ordinance shall take effect immediately from and after its passage by the City
Council of the City of Baytown.
INTRODUCED, READ and PASSED by the affirmative vote the City Council of the City of
Baytown this the 1 Oth day of July, 2014.
EP DONCARLOS, Mayor
jAEST:
o
\ o
a�
d
0
® co
LETICIA BRYSC , ity Clerk
APPROVED AS TO FORM:
ACIO RAMIREZ, SR., City A orney
11COBFS011LegallKaren\FileslCityCouncitlOrdinances\2014Vuly 10',ChangeOrderNolAnnualWaterlineRehabilitationContract.doc
Exhibit "A"
J. CITY OF BAYTOWN
Change Order No. 1
BAY
TOz �wlv TI 2014 Annual Water Line Rehabilitation Project
�/ July 1, 2014
Brief Description of Changes:
This Change Order is for the increase of the contract by 25%. This will allow the for the City to use the pipebursting
method to rehabilitate existing waterlines.
Add or Delete Items:
Item Description Unit Quantity Unit Price Total
Original Contract Amount $ 1,000,000.00
CO#1 (Will change the contract amount by
Change Order increasing the contract amount
by 25%) $ 250,000.00
Revised Contract Amount $ 1,250,000.00
Contract Summary:
Original Contract Amount $ 1,000,000.00
Previous Change Orders $ -
This Change Order 50,000.00
Revised Contract Amount $ 1,250,000,00
Original Contract Duration-Calendar Days 365
Previous Time Extensions
This Change Order 0
Revised Contract Duration-Calendar Days 365
PM Construction&Rehab. L.P. Date Director of Engineering Date
Director of Finance Date City Manager Date
CITY OF BAYTOWN
Change Order No. 1
BAW0� ■ ,� T 2014 Annual Water Line Rehabilitation Project
N July 1, 2014
Brief Description of Changes:
This Change Order is for the increase of the contract by 25%. This will allow the for the City to use the pipebursting
method to rehabilitate existing waterlines.
Add or Delete Items:
Item Description Unit Quantity Unit Price Total
Original Contract Amount $ 1,000,000.00
CO#1 (Will change the contract amount by
Change Order increasing the contract amount
by 25%) $ 250,000.00
Revised Contract Amount $ 1,250,000.00
Contract Summary:
Original Contract Amount $ 1,000,000.00
Previous Change Orders $ _
This Change Order ,
Revised Contract Amount $ 1,250,000.00
Original Contract Duration-Calendar Days 365
Previous Time Extensions
This Change Order
Revised Contract Duration-Calendar Days 365
,\� -7/,/If MOL f 1
PM nstruction&RehW. L.P. Date D' ector of Engineering Date
Director of Finance Date City Manager Date