Ordinance No. 12,530ORDINANCE NO. 12,530
AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS,
AUTHORIZING CHANGE ORDER NO. 2 WITH LEM CONSTRUCTION CO., INC.,
FOR THE CENTRAL DISTRICT WASTEWATER TREATMENT PLANT INFLUENT
LIFT STATION IMPROVEMENT PROJECT; AUTHORIZING PAYMENT BY THE
CITY OF BAYTOWN, IN THE AMOUNT OF ONE HUNDRED SEVENTY-TWO
THOUSAND SIX HUNDRED FIFTY-ONE AND 50!100 DOLLARS ($172,651.50); AND
PROVIDING FOR THE EFFECTIVE DATE THEREOF.
************************************************************************************
BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS:
Section 1: That the City Council does hereby authorize Change Order No. 2 with LEM
Construction Co., Inc., for the Central District Wastewater Treatment Plant Influent Lift Station Improvement
Project. A copy of said change order is attached hereto, marked Exhibit "A" and made a part hereof for all
intents and purposes.
Section 2: That the City Council of the City of Baytown hereby authorizes the payment in an
amount of ONE HUNDRED SEVENTY-TWO THOUSAND SIX HUNDRED FIFTY-ONE AND 501100
DOLLARS ($172,651.50) to LEM Construction Co., Inc., for the Central District Wastewater Treatment Plant
Influent Lift Station Improvement Project.
Section 3: This ordinance shall take effect immediately from and after its passage by the City
Council of the City of Baytown. ,
INTRODUCED, READ and PASSED by the affirmative vote ofAej City Council of the City of
Baytown this the 24'h day of April, 2014.
ATTEST:
LETICIA BRYSCH, City
APPROVED AS TO FORM:
ACID RAMIREZ, SR., Ci A orney
R'%Karem,Files'+City Council Ordinances12014Wpril 24%.ChangeOrderNo2CentralDistnctWWTPlnfluentLiftStationlmprovementProj
HEN H. DONCARLOS, Mayor
ect doc
3� •
r
0
• u.
:O
CP %
.�
ACID RAMIREZ, SR., Ci A orney
R'%Karem,Files'+City Council Ordinances12014Wpril 24%.ChangeOrderNo2CentralDistnctWWTPlnfluentLiftStationlmprovementProj
HEN H. DONCARLOS, Mayor
ect doc
Exhibit "A"
CITY OF BAYTOWN
BAYTOWN Change Order No. 2
Central District Influent Lift Station Project
4/15/2014
Brief Description of Changes:
Removal of 300 LF of existing 16 -inch asbestos cement piping and replacement with C-900. The existing 16 -inch
asbestos cement water line was not constructed at the depth the record drawings indicated. The work includes various
appurtenances including valves, additional 8 -inch water line, and additional by-pass pumping.
Add or Delete Items:
Item
Description
Unit
Quantity
Unit Price
Total
1
16 -inch Water Line Relocate
LS
1
$ 172,651.50 $
172,651.50
Total
Contract Summary:
$ 172,651.50
Original Contract Price $ 7,247,500.00
Previous Change Orders $ 13,956.25
This Change Order ,
Revised Contract Price $ 7,434,107.75
Original Contract Duration - Calendar Das 54C
Previous Time Extensions C
This Change Order 2
Revised Contract Duration - Calendar Days 561
LEM Construction Co., Inc.
Director of Finance Date
ARCADIS Date
Director of Engineering Date
City Manager Date