HomeMy WebLinkAboutOrdinance No. 16,569 (Item 7.p.)ORDINANCE NO. 16,569 AN ORDINANCE OF THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS, AUTHORIZING CHANGE ORDER NO. 2 FOR THE GARTH ROAD RECONSTRUCTION PROJECT PHASE A & B WITH HARPER BROTHERS CONSTRUCTION LLC, IN AN AMOUNT OF THIRTY-FOUR THOUSAND TWO HUNDRED FORTY-ONE AND 10/100 DOLLARS ($34,241.10); AND PROVIDING FOR THE EFFECTIVE DATE THEREOF. BE IT ORDAINED BY THE CITY COUNCIL OF THE CITY OF BAYTOWN, TEXAS: Section 1: That the City Council does hereby authorize Change Order No. 2 for the Garth Road Reconstruction Project —Phase A & B Utility with Harper Bothers Construction, LLC, in an amount of THIRTY-FOUR THOUSAND TWO HUNDRED FORTY-ONE AND 10/100 DOLLARS ($34,241.10). A copy of said change order is attached hereto, marked Exhibit "A" and made a part hereof for all intents and purposes. Section 2: This ordinance shall take effect immediately from and after its passage by the City Council of the City of Baytown. INTRODUCED, READ and PASSED by the affirmative vote of the City Council of the City of Baytown this the 27th day of August, 2026. CHARLES JOHNSON, Mayor ATTEST: ANGELA JACKSON, City Clerk APPROVED AS TO FORM: Scott Lemond, City Attorney R:\Ordinances and Resolutions\Ordinance Drafts\2026-08-27\cliangeOrderNo 2-Garth Road Reconstruction PhaseA&B with Harper Brothers.docx I! A BAYTOVYN Date of Issuance: Contractor: Designer: EXHIBIT A CITY OF BAYTOWN PUBLIC WORKS & ENGINEERING 2123 Market St. Baytown, Texas 77520 CHANGE ORDER Garth Road Reconstruction Project - Phase A & B 5/29/2026 Harper Brother Construction, LLC Kimley-Horn & Associates, Inc Explanation: This change order encompasses the following: Change Order No.: CoB Project No.: P.O. No.. RDWY1901 4260009 This change order adds a new item to compensate the contractor (Harper Brothers, LLC) for the removal of stockpiled asbestos concrete drainage pipe from a prior contract, that is currently stored along West Archer Road. It also establishes a new cement treated base item to replace the lime treated subgrade items previously under Line Items 27 and 28. It also adds a new precast junction box item and revises existing drainage items associated with the changes resulting from Reqest for Information (RFI) #19. In addition, it adds compensation to the contractor for the elimination of existing pavement markings throughout the project limits. No contract time adjustments will be made as part of this change order. The project provides for the full reconstruction and widening of the Garth Road facility consisting of grading, lime -treated subgrade, cement - treated base, asphalt pavement, continuous reinforced concrete pavement, inlets, storm sewers, culverts, illumination, signals, signing, and pavement markings, The contractor, Harper Brothers Construction, LLC ("HB"), remains on -site and continues to perform the contract according to the plans and the TxDOT 2024 Standard Specifications, TxDOT controlling CSJ is 0912-72-359. All change order work is within the project limits. 1. Disposal of Asbestos -Cement Waterline Pipe At the beginning of the project, Harper Brothers Construction, LLC ("HB") identified a stockpile of asbestos cement ("A/C") waterline pipe located along West Archer Road, near the project field office at 1210 West Archer Road. The City confirmed that this material was left in place under a previous contract that was terminated prior to the start of the HB contract for Garth Road Project, Phase A & B. As such, the stockpiled A/C pipe was not included in the original contract scope or associated bid quantities for the current project. While the Garth Road Project does include contract items for the removal and disposal of A/C waterline pipe encountered as part of the planned construction work, the existing stockpiled material was separate from those anticipated quantities and was not accounted for in the original HB contract. Because the removal and disposal of A/C material requires a specialized contractor licensed to handle hazardous materials, the City determined that the most efficient and expedient approach was to add the disposal of this existing stockpiled material to the current HB contract. Incorporating this additional work into the project will allow the material to be removed more quickly and in coordination with ongoing project activities, while ensuring proper handling and disposal in accordance with applicable requirements. The City requested pricing from HB on March 10, 2026, and received a response on April 13, 2026. Upon review, the City has determined the submitted pricing to be fair and reasonable for the proposed scope of work. Harper Brothers will remove all A/C pipe currently stored along West Archer Road in accordance with the safety practices outlined in the American Water Works Association publication "Work Practices for A/C Pipe." (Line Item #240. 1). All recommended procedures within this publication must be strictly followed. Compensation for this work will be made on a lump sum basis for the complete disposal of all asbestos cement pipe currently stored along West Archer Road. 2. Cement Treated Base (CTB) in Lieu of Lime treated Subgrade (LTS) The proposed roadway typical section depicted in the plans consists of a 6-inch lime treated subgrade (LTS), a 6-inch cement treated base (CTB), a l-inch asphalt bond breaker, an 1 1-inch continuously reinforced concrete pavement (CROP), and Cement Stabilized Backfill (Line Item 62). These components are quantified and incorporated into the overall estimated quantities for the roadway items. However, plan sheet 13 includes a typical section applicable to all areas where the top of the proposed reinforced box culverts (RCB) extends into the planned 6-inch LTS. In these locations. the typical section indicates that the LTS is to be omitted over the RCB and for 10 feet on either side, and instead replaced with a thickened section of cement treated base. Furthermore, this detail specifies that any additional CTB required shall be considered subsidiary to Line Items 68 & 69. Construction 1 of D16 Revised 5/2026 After reviewing the standard section and mapping of its application on the project plans, it was observed that only a narrow area along the center of the roadway is not covered by this detail. This segment, which varies in width, is generally estimated to be between 1 I and 15 feet wide. Due to the limited quantity and logistical challenges associated with LTS placement, Harper Brothers Construction submitted a request for approval to use CTB instead of LTS throughout the project limits. This change eliminates all LTS installation from the scope of the project and establishes a revised typical section consisting of two 6-inch layers of CTB, a 1-inch bond breaker, and an 1 l -inch CRCP. The city reviewed this request and has approved the proposal. To comply with TxDOT testing requirements and maintain accurate project documentation, the city will issue a change order to replace the two Line Items (27 & 28) related to LTS installation with one new line item for 6" cement treated base (Line Item 29.1). The unit cost is set to match the Square Yard (SY) cost of lime treated subgrade, as this change to the typical section is intended for contractor convenience rather than correcting any issues in the plans that would prevent installation as originally specified. 3. Drainage Revisions Associated with Reaest for Information #19 (RFI #19) The original storm sewer plan sheets showed Trunk Lines B and D connecting directly into the proposed cross culvert at Independence Boulevard without the use ofjunction boxes. However, no connection detail was provided in the plans for these tie-ins. As a result, the contractor submitted RFI #19 requesting clarification of the Engineer of Record's (EOR) intent and asking that a connection detail be provided. At the time RFI #19 was submitted, the contractor had already begun installation of the Independence Boulevard cross culvert and requested an expedited response in order to avoid impacts to production. Due to the time required to fully design and detail the proposed connections, the FOR determined that the original concept could not be completed within the contractor's schedule. To prevent delays to ongoing work, the FOR elected to revise the design and utilize precast junction boxes at the two Phase 1 connection locations associated with Trunk Lines B and D. The revised plan sheets were issued to the contractor as part of the official RFI # 19 response on April 5, 2026. Included in the revisions was the elimination of the proposed cross connection at Sta. 182+00 between Trunk Lines C and D. This connection was removed in an effort to help offset costs associated with the addition of the junction boxes. Where applicable, existing contract items will be utilized to compensate for the adjustments associated with RFI #19 (Line Items 68,69,83). However, a new contract item will need to be established for the proposed 13' x 13' junction box (Line Item 84.5), as no comparable item currently exists within the contract. The contractor subsequently submitted a detailed cost breakdown outlining the labor, equipment, and materials required for installation of the proposed 13' x 13' junction box. After review, the City has determined the submitted pricing to be fair and reasonable for the scope of work involved. 4. Elimination of Existing Pavement Markings Throughout the Project Limits After completion of the traffic switch into the Phase 1 Step 3/4 configuration striping, the subcontractor, Traffic Signs & Lines (TS&L), notified the prime contractor that the existing contract did not include compensation for the removal of existing pavement markings required to facilitate the traffic transition. The work proceeded while field personnel monitored and documented the removal activities to ensure accurate records of the work performed and quantities involved were maintained. Following completion of the traffic switch, TS&L submitted a formal change order request seeking the addition of contract pay items specifically associated with the removal of existing pavement markings. The proposed change order and associated quantities were subsequently reviewed by the Engineer of Record (EOR), Kimley-Horn, to verify the legitimacy and extent of the additional work. As part of this review process, the FOR not only evaluated the quantities submitted by TS&L for the recently completed Phase 1 Step 3/4 traffic switch, but also performed a comprehensive forward -looking quantity analysis for future traffic control phases anticipated throughout the project. This expanded review ensured that all anticipated pavement marking removal quantities associated with upcoming traffic switches were identified and incorporated in advance, reducing the likelihood of future discrepancies or repeated contract modifications. The final approved quantities therefore accounted for both the work already completed during the Phase 1 Step 3/4 switch and the anticipated removals required for subsequent traffic phase transitions. The city reviewed the quantities as well as the submitted pricing from the sub -contractor (TS&L) and has determined the submitted pricing to be fair and reasonable for the proposed scope of work (Line Items 21.1, 21.2. 21.3, 21.4, 21.5). The unit cost established as part of this change order is full compensation for the elimination method used and materials, equipment, tools, labor, and incidentals. Removal of the Raised Pavement Makers (RPMs) is included in the contractors pricing, and will not be an additional cost. Construction 2 of 4 D 16 Revised 5/2026 • Change Order 2 will result in the addition of new items: o Line Item #29.1 — 276 - CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(6")(CO-02), with a unit cost of $12.82, and a total quantity of 67,682.00 SY. All work paid under this item is to be performed in accordance with Item 276 of 2024 TxDOT specifications. o Line Item #84.5 — 465 — JCT BOX (COMPL)(SPL)(I YX 13'), with a unit cost of $64,017.51, and a total quantity of 1 EA. All work paid under this item is to be performed in accordance with Item 465 of 2024 TxDOT specifications. o Line Item #240.1 — COB — DISPOSE EXISTING ASBESTOS CEMENT (A/C) PIPE, with a unit cost of $8,287.81, and a total quantity of 1 LS. All Work paid under this item is to be performed in accordance with City of Baytown Specification 2510 - Water Mains. o Line Item #21.1 - 677 - ELIM EXIST PAV MRK & MRKS (4"), paid for by the LF with a quantity of 20,905 LF and a unit price of $0.48/LF. o Line Item #21.2 - 677 - ELIM EXIST PAV MRK & MRKS (8"), paid for by the LF with a quantity of 1,899 LF and a unit price of $0.95/LF. o Line Item #21.3 - 677 - ELIM EXIST PAV MRK & MRKS (24"), paid for by the LF with a quantity of 667 LF and a unit price of $3.18/1-F. o Line Item #21.4 - 677 - ELIM EXIST PAV MRK & MRKS (ARROW), paid for by the EA with a quantity of 27 EA and a unit price of $68.93/EA. o Line Item 421.5 - 677 - ELIM EXIST PAV MRK & MRKS (WORD), paid for by the EA with a quantity of 13 EA and a unit price of $68.93/EA. Change Order 2 will result in the adjustment to the following existing items o Line Item #27 — 260 — LIME TRT (EXIST MATL)(6") o Line Item #28 — 260 — LIME (COM OR QK)(SLURRY) OR QK(DRY) o Line Item #62 - 400 - CEM STABIL BKFL o Line Item #68 — 462 — CONC BOX CULV (8 FT X 4 FT) o Line Item #69 — 462 — CONC BOX CULV (10 FT X 5 FT) o Line Item#83 —465 —JCT BOX (COMPL)(SPL)(I 1'XI 1') Modified Plan Sheets: 24, 216, 217, 218, 219 Added Plan Sheets: 274A, 274E The revisions covered by this change order are estimated to overrun the funds authorized for this project by $34,241.10. This change order has been discussed with the appropriate personnel from the City of Baytown and is being submitted for approval. Description of Work 1 Line Item #27 — 260 — LIME TRT (EXIST MATL)(6") 2 Line Item #28 — 260 — LIME (COM OR QK)(SLURRY) OR QK(DRY) 3 Line Item #29.1-276—CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(6")(CO-02) 4 Line Item #62 — 400 — CEM STABIL BKFL 5 Line Item #68 — 462 — CONC BOX CULV (8 FT X 4 FT) 6 Line Item #69 — 462 — CONC BOX CULV (10 FT X 5 FT) 7 Line Item #83 — 465 — JCT BOX (COMPL)(SPL)(I VX I l') 8 Line Item #84.5 —465 — JCT BOX (COMPL)(SPL)(I YX 1 Y) 9 Line Item #240.1 — COB — DISPOSE EXISTING ASBESTOS CEMENT (A/C) PIPE 10 Line Item #21.1 — 677 — ELIM EXIST PAV MRK & MRKS (4") 11 Line Item #21.2 — 677 — ELIM EXIST PAV MRK & MRKS (8") 12 Line Item #21.3 — 677 — ELIM EXIST PAV MRK & MRKS (24") 13 Line Item 421.4 — 677 — ELIM EXIST PAV MRK & MRKS (ARROW) 14 Line Item #21.5 — 677 — ELIM EXIST PAV MRK & MRKS (WORD) Please attach back-up documentation Cost & Time Change Summary Original Contract: Previous Change Order(s): Contract prior to this change order: Net increase (decrease) from this change order Cost Time $ (541,456.00) 0 Days $ (326,600.00) 0 Days $ 867,683.24 0 Days $ (5,603.50) 0 Days $ (32,630.56) 0 Days $ (57,826.72) 0 Days $ 41,652.61 0 Days $ 64,017.51 0 Days $ 8,287.81 0 Days $ 10,034.40 0 Days $ 1,804.05 0 Days $ 2,121.06 0 Days $ 1,861.11 0 Days $ 896.09 0 Days Cost Time $ 48,825,786.15 845 Days $ 25,000.00 0 Days $ 48,850,786.15 845 Days $ 34,241.10 0 Days Construction 3 of D16 Revised 5/2026 Revised Contract: Percent increase (decrease) this Change Order Percent increase (decrease) all Change Orders RECOMMENDED: By: Date: 07/23/2026 Design Engineer ACCEPTED*: 07/29/2026 By: Cory Halley Date: Contractor BRECOMMENDED: 07/29/2026 y (�' P Date: Project Manager VERIFIED: 08/3/2026 By:� Date: Business Asset Team Member + 0.070% + 0.121% $ 48,885,027.25 RECOMMENDED: By: 845 Days Date: 8/7/2026 Carol Haddock, P.E., Director, Public Works & Engineering FINANCE APPROVAL: By: � ,4alp Date: 08/10/26 Teresa McKenzie, Chfef Financial Officer APPROVED: By: Date: Jason E. Reynolds, City Manager *Contractor agrees to perform change(s) included in this Change Order for the price and time indicated. The prices for changes included all costs associated with this Change Order. No work is to be done until this change order is executed. No payment to the Contractor (or Consultant) shall be made for work included in the change order until the Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, this Change Order governs. Upon execution by all parties, the following changes identified for the contract value and/or contract time shown, are made part of the contract. Construction 4 of 4 D 16 Revised 5/2026 Attachment A Change Order Quantity Summary Project: Garth Rd. Phase A RDWY 1901 IH10 to South of Archer Rd. County: Harris CSJ #0912-72-359 City of Baytown - Garth Rd. Phase A&B RDWY 1901 CSJ #0912-72-359 Change Order #002 - Unit Cost Breakdown Line Number Item Code Description Current Quantity Unit Price Unit Total Qty Change Revised Quantity CO Extension 27 260 LIME TRT (EXIST MATL)(6") 67,682.00 8.00 SY (67,682.00) - $ (541,456.00) 28 260 LIME (COM OR QK)(SLURRY) OR QK(DRY) 920.00 355.00 TON 1920.00) - $ (326,600.00) 62 400 CEM STABIL BKFL 17,175.00 70.00 CY (80.05) 17,094.95 $ (5,603.50) 68 462 CONC BOX CULV (8 FT X 4 FT) 1,956.00 709.36 LF (46.00) 1,910.00 $ (32,630,56) 69 462 CONC BOX CULV (10 FT X 5 FT) 4,903.00 1,032.62 LF (56.00) 4,847.00 $ (57,826.72) 83 465 1CT BOX (COMPL)(SPL) (11'xll') 1.00 41,652.61 EA 1.00 2.00 $ 41,652.61 29.1 276 CEM TRT(PLNT MX)(CL N)(TY E)(GR 4)(6")(CO-02) - $ 12.82 SY 67,682.00 67,682.00 $ 867,683.24 84.5 465 1CT BOX (COMPL)(SPL)(13'X13') - $ 64,017.51 EA 1.00 1.00 $ 64,017.51 240.1 COB DISPOSE EXISTING ASBESTOS CEMENT (AC) PIPE - $ 8,287.81 LS 1.00 1.00 $ 8,287.81 TOTAL: $ 17,524.39 Garth Rd. CO#002 Combined - Quantity Summary Updated: 5/20/2026 CO Summary (BREAKDOWN) 9:49 AM Project: Garth Rd. Phase A RDWY 1901 IH10 to South of Archer Rd. County: Harris CSJ #0912-72-359 City of Baytown - Garth Rd. Phase A&B RDWY 1901 CSJ N0912-72-359 Change Order #003 - ELIMINATE EXISTING STRIPING Line Number Item Code Description Current Quantity Unit Price Unit Total QtyRevised Change Quantity CO Extension 21.1 677 ELIM EXIST PAV MRK & MRKS (4") - $ 0.48 LF 20,905.00 20,905.00 $ 10,034.40 21.2 677 ELIM EXIST PAV MRK & MRKS (8") - $ 0.95 LF 1,899.00 1,899.00 $ 1,804.05 21.3 677 ELIM EXIST PAV MRK & MRKS (24") - $ 3.18 LF 667.00 667.00 $ 2,121.06 21.4 677 ELIM EXIST PAV MRK & MRKS (ARROW) - $ 68.93 EA 27.00 27.00 $ 1,861.11 21.5 1 T77-1 ELIM EXIST PAV MRK & MRKS (WORD) - $ 68.93 EA 13.00 13.00 $ 896.09 TOTAL: $ 16,716.71 Garth Rd. - Strping Elimination - Quantity Summary Updated: 5/26/2026 CO Summary (BREAKDOWN) 2:22 PM Unit Cost Calcs Item Sub Markup Bond Total Unit Cost Sub unit Cost 5% Sub unit cost + 5%markup 1% 21.1 677 ELIM EXIST PAV MIRK & MRKS (4") 0.45 0.0225 0.4725 0.004725 0.48 21.2 677 ELIM EXIST PAV MIRK & MRKS (8") 0.9 0.045 0.945 0.00945 0.95 21.3 677 ELIM EXIST PAV MIRK & MRKS (24") 3 0.15 3.15 0.0315 3.18 21.4 677 ELIM EXIST PAV MIRK & MRKS (ARROW) 65 3.25 68.25 0.6825 68.93 21.5 677 ELIM EXIST PAV MIRK & MRKS (WORD) 65 3.25 68.25 0.6825 68.93 1. Disposal of Asbestos -Cement Waterline Pipe Contractor Pricing Submittal Bryce Watson From: Cory Halley <Cory.Halley@harperbro.com> Sent: Monday, April 13, 2026 1:20 PM To: Bryce Watson; Javier Sauceda Cc: Brian Hancock Subject: Force Account AC Pipe Removal Attachments: AC Pipe Removal.xlsx; HOUP000543 ADDTITONAL PIPE REMOVAL.pdf Follow Up Flag: Follow up Flag Status: Completed Bryce, Please see the attached for the additional Ac Pipe Removal. Thanks Cory Halley Project Manager 1310 Rankin RD, Suite 200 Houston, TX 77073 C:817.751.8412 dm CHARPER BROTHERS <; 0Ir S'RU4Ti•?'J CHANGE ORDER Project: Garth Rd Phase A&B Control: 0912-72-359 Scope of Work: Removal of AC Pipe HBC LABOR ITEMS QUANTITY UOM: MANHOURS HOURLY RATE COST ......................................................................................................................... .................................................... ............... . ........................................ . .......................................... .................................................. ......................................................................................................................... .................................................... ........ . ..... 4 ........................................ ....... . ................................... ................................................... ........................................................................................................................ ..... . .................................................. $ ................................................................. i ...................................................... .................................................. . .............. . ........................................ : . ........................................... . .................................................. ......................................................................................................................... ............................. ............................................$ ............................................. ............................................................................................ I ............................ .................................................... ............... ........................................ ............................................ .................................................. $ ......................................................................................................................... ................................................... ............... ........................................ . ........................................... . ................................................... ......................................................................................................................... ......................................... ................... ............................................ ................................................................................................ . ....................... ................................. .................. ............... ........................................ 4 ............ ......................................................................................................................... ................................................... ............... . ........................................ . ............................................ ....... ................................................... ......................................................................................................................... ............................ 4 ............................................ ......................................................................................................................... ................................................... ............... ............. ........................... ............. ........................ .. ............................................................................................... ................................................... ............... . ........................................ A .......................................... . ......... ......................................................................................................................... ................................................... .......................... ......... ......................................................................................................................... .................................................... ............... ........................................ 4 ............ ......................................................................................................................... .................................................... ............... ........................................ ............... $ ......... ....................................................................................................................................... SUBTOTAL HBC LABOR::: $ : .................................................................. ................ , .......... . ........... ............ ............ 55-00% $ ........................................................................................................................................................................................................... ................ ..................... .............. I ............................. ....................... LABOR MARK-UP::: 25.00% $ ...................... TOTAL TSC LABOR:: $ HBC MATERIAL ITEMS QUANTITY UOM UNIT COST COST $ ......................... .............................................................................................. .................................................... ............... ........................................ .......................................... 4 ......................................................................................................................... ........... ................ ...................................................................................... ......... ........................................................................................................................ .................................................... ..... ..................... ............................................ .......... ? ................... ................................................... ..................................................................................................................... .................................................... ............... ........................................ ........................................... ................................................... SUBTOTAL TSC MATERIAL:: ............................................................................................................................................................................................................ $ ............ .................................................. MATERIAL $ TOTAL TSC MATERIAL::: $ HBC EQUIPMENT ITEMS QUANTITY HOURS HOURLY RATE COST ......................................................................................................................... .................................................... .............. ........................................ ........................................... ................. ......................................................................................................................... .................................................... .............................. ................................................... ............................ ................................. ......................................................................................................................... $ ......................................... ............. .............. ........................................ ........................................... . ......................................................................... : ............................................... ................................... .................. ........ 7 ............................................................................... .......................................... .................................................... ............... ........................................ ............................................ ? ..................................... ................................................................................................................... .................................................... ............................ ............................ .................................................. ...... $ ............................................................................... .......................................... ................................................... ............... .......................... .............. ............................................ ............................................ ......................................................................................................................... ............ .................... ............................................ ................................... ........ SUBTOTAL TSC EQUIPMENT::: $ ..................................................................................................................................................... ............................................................................ ............................................ .................................................. EQUIPMENT MARK-UP: 15.00% $ TOTAL TSC EQUIPMENT:: $ SUBCONTRACTOR ITEMS QUANTITY UOM UNIT COST COST Remove Additional Asbestos containing 1.00 1 LS ! $ 7,815.00 $ .....................................................1 ..................................... 9n9 pips 7,815.00 .................................................... ............... . ........................................ ................................................................................................ ......................................................................................................................... ................................................... ............... ........................................ ........................................... .................................................. ............................................................................... .......................................... .................................................... $...................................."... ............... . ........................................ ........................................... ......................................................................................................................... .................................................... ............... ........................................ ............................................ .................................................. ......................................................................................................................... . ...................................................... .............. . ......................................................................... ... ? ........................................... ..... ......................................................................................................................... .................................................... ............... ........................................ 4 ............................................ ................................... .... . ........ ......................................................................................................................... ................................................... . ............... . ........................................ ........................................... 4 ................................................... SUBTOTAL SUBCONTRACTOR:;: $ ............................................................................................................................................................................................................. .............................. * .......... 7,815.00 SUBCONTRACTOR 5.00% ]$ ................ 390.75 TOTAL SUBCONTRACTED ITEMS::: $ 8,205.75 TOTAL HBC ITEMS: $ - TOTAL SUBCONTRACTOR ITEMS: $ 8,205.75 SUBTOTAL $ 8,205.75 BOND 1% $ 82.06 TOTAL $ 8,287.81 1 PRIORITY ABATEMENT • IAQ • DECONTAMINATION REQUEST FOR CHANGE ORDER Job Number: HOUP000543 Change Order Number: 01 Date: 04/06/26 Project Name: Baytown Pipeline abatement Job Address: Bavtown Customer Name: Harper Brothers This Change Order is subject to the terms and conditions as set out in the Contract Agreement for this project. The following changes to the Scope of Work and Price modifications are as listed below: Changes to the Scope of Work: Change Item 1: Remove additional asbestos containing pipe. 1 Priority will provide labor and disposal including prep of the dumpster. Client (harper brothers) will provide equipment to load pipe ACM pipe into dumpster. Change Item 1 will (increase) (decreased) ( qed) the total duration by-1-2 workday(s). Workdays are consistent with original proposal or contact. Price Information: Original Contract Value: $98,569.00 Previously Authorized Change Orders: $0,000.00 RFCO #-Item 1: +$7,815.00 Contract Value including requested changes: $106,384.00 CUSTOMER Print: Signature: Date 1 PRIORITY ENVIRONMENTAL SERVICES, LLC. Name: Joe Ramirez Signature: Y" zMa eiZ Date: 04/06/26 1 PRIORITY. YOUR SOLI MUM. 1 Priority Environmental Services, LLC., 4028 Daley Ave, Fort Worth, Texas 76180 24-Hour Emergency (866) 595-0790 • (817) 595-0790 Office (817) 595-4480 Fax www.go1 priority. com City Request for Pricing Submittal from Contractor Bryce Watson From: Cory Halley <Cory.Halley@harperbro.com> Sent: Tuesday, March 10, 2026 12:46 PM To: Bryce Watson; Brian Hancock Cc: danielle.caii Johana.Campos-Estrada; Monica.Cisneros; Javier Sauceda; Denise Schott; Christopher Scullion; Rafael. Errisuriz Subject: Re: Harth Rd. Phase A&B - Disposal of Asbestos Pipe Yes, sir, not a problem. I will review and get back to you. Thanks From: Bryce Watson <WWatson@bgeinc.com> Sent: Tuesday, March 10, 2026 12:20 PM To: Brian Hancock <brian.hancock@harperbro.com>; Cory Halley <cory.halley@harperbro.com> Cc: danielle.cain <danielle.cain@baytown.org>; Johana.Campos-Estrada <johana.campos-estrada@baytown.org>; Monica.Cisneros <monica.cisneros@baytown.org>; Javier Sauceda <JSauceda@bgeinc.com>; Denise Schott <dschott@bgeinc.com>; Christopher Scullion <CScuIlion@bgeinc.com>; Rafael. Errisuriz <rafael.errisuriz@baytown.org> Subject: Harth Rd. Phase A&B - Disposal of Asbestos Pipe Brian/Cory, As we discussed during the progress meeting yesterday, the city would like to request that Harper submit pricing to dispose of the asbestos pipe currently stored on the South side of Archer Rd. near the field office. The intent is to add this scope of work to the contract via change order. Let me know if you have any questions. Thanks, min= Bryce Watson, P.E. Project Manager, Construction Management BGE, Inc. 10777 Westheimer Suite 400 Serving. Houston, TX 77042 Leading. bwatson@bgeinc.com Solving. +1 (346) 320-1383 p +1 (806) 676-3715 m www.bgeinc.com ®@0 CONFIDENTIAL Tres e-mail and any files transmitted •.with it are confidential and intended solely for the use of the individual or entity to whom they are addressed. If you are not the person to whom this message is addressed. be aware that disclosing. copying. distributing. or taking any action in reliance on the contents of this message is strictly prohibited. If you received this in error. please contact the sender and immediately delete this e-mail and any attachments. Applicable Specification Items City of Baytown Item 2510 CITY OF BAYTOWN WATER MAINS Section 02510 WATER MAINS 1.0 GENERAL 1.01 SECTION INCLUDES A. Installation of water mains, including valves, fire hydrants, wet connections, cut and plug of mains, disinfection, and hydrostatic testing for pipelines. B. References to Technical Specifications: 1. Section 01200 - Measurement and Payment Procedures 2. Section 01350 - Submittals 3. Section 02514 - Fire Hydrant Assembly 4. Section 03300 - Cast -in -Place Concrete 5. Section 02512 - Polyethylene Wrap 6. Section 02417 - Augering Pipe for Water Lines 7. Section 02515 - Water Tap and Service Line Installation 8. Section 02318 - Excavation and Backfill for Utilities 9. Section 02980 - Pavement Repair 10. Section 01450 - Testing Laboratory Services 11. Section 02634 - Ductile Iron Pipe and Fittings C. Referenced Standards: 1. Texas Commission on Environmental Quality (TCEQ) 2. American Water Works Association (AWWA) 3. American Society for Testing and Materials (ASTM) 1.02 MEASUREMENT AND PAYMENT A. Measurement for water mains open cut or augered, with or without casing is on a linear foot basis for each size of pipe installed. Mains: Measure along axis of pipe and include fittings and valves. Branch Pipe: Measure from axis of main to end of branch. B. Refer to Section 01200 — Measurement and Payment Procedures. 1.03 QUALITY ASSURANCE A. Regulatory Requirements: Pipe shall bear Underwriter's Laboratories (UL) or Factory Mutual (FM) label. 03/2020 02510 - 1 of 22 CITY OF BAYTOWN WATER MAINS 2. Pipe material acceptable without penalty to State's community fire insurance rating agency. 3. System acceptable to City and TCEQ. 4. Bacteriological disinfection acceptable to local health officials and Texas Department of Health, and TCEQ. 5. Water taps and draws off lines in compliance with local municipal specifications and regulations. 1.04 SUBMITTALS A. Make Submittals required by this Section under the provisions of Section 01350 — Submittals. B. Product Data: 1. Obtain from pipe manufacturer installation instructions, manuals, and printed recommendations, except for Owner furnished pipe. 2. Retain product data on job site for reference. 3. Submit certified record of tests of pipe, fittings, or valves upon request of Engineer. 4. Submit hydrant manufacturer flow and friction loss curve. C. Samples: 1. Notify City when system is pressure tested and disinfected. City will take all samples for bacteriological testing as required by TCEQ. 1.05 PRODUCT HANDLING A. Deliver pipe to trench in sound, undamaged condition. B. Cut pipe neatly avoiding sharp, ragged, or unbeveled, plain ends and do not damage lining by cutting. C. Remove damaged or rejected materials from project site. 1.06 ENVIRONMENTAL REQUIREMENTS A. Do not lay pipe when it is raining or when trench is muddy, soft, or contains standing water. 03/2020 02510 - 2 of 22 CITY OF BAYTOWN WATER MAINS 2.0 PRODUCTS 2.01 POLYVINYL CHLORIDE (PVC) PRESSURE PIPE A. Conform to requirements of Section 02534 - PVC Pipe. All pipe used for water mains shall be blue. 2.02 HIGH DENSITY POLYETHYLENE A. Conform to requirements of Section 02532W - HDPE 2.03 STEEL PIPE AND FITTINGS FOR LARGE DIAMETER WATER LINES A. Conform to requirements of Section 02513 - Steel Pipe and Fittings for Large Diameter Water Lines. 2.04 DUCTILE IRON PIPE AND FITTINGS A. Conform to requirements of Section 02634 - Ductile Iron Pipe and Fittings. 2.05 FIRE HYDRANTS A. Conform to requirements of Section 02514 - Fire Hydrant Assembly. 2.06 VALVES A. General: Conform to requirements of Section 02541 — Water and Wastewater Line Valves. 1. Manual operators: a. Provide hand wheel manual operators for in -plant valves. b. Equip buried valves with 2 in. square operating nuts. 2. Furnish no less than one operating key with each lot of 10 buried valves with nut operators. 3. Rotation: a. Direction: OPEN COUNTERCLOCKWISE (OPEN LEFT). 4. Shop coating: a. Shop coat ferrous metal surfaces of valves both interior and exterior for corrosion protection. b. Protect internal and external iron surfaces of valves with coating of 4 mils of two-part thermosetting epoxy: AWWA C 550. 5. Working and test pressures: a. Valves 2 in. through 12 in.: 200 psi working pressure, 400 psi hydrostatic test pressure. b. Valves 14 in. through 36 in.: 150 psi working pressure, 300 psi hydrostatic test pressure. 03/2020 02510 - 3 of 22 CITY OF BAYTOWN WATER MAINS B. Gate Valves (2 in. Through 36 in.): 1. Buried valves: a. Comply with AWWA C500, non -rising stem (NRS); resilientwedge. b. Epoxy -coated ductile iron body and bonnet, inside screw. C. Bronze: Seat and disc rings, stem and mountings, and disc wedges. d. "O" ring sealed stem and 2 in. square operating nut. e. Valves 2 in. through 12 in.: Vertical type without by-passes. f. Valves 16 in. through 36 in.: Horizontal type with enclosed steel bevel gears resilient wedge, standard size by-pass valves. g. Stuffing box and bonnet bolts and nuts to be 304 stainless steel. h. Install in section of horizontal pipe. i. Mechanical joint ends with gasket complying with AWWA C 111. j. Acceptable product: 1) East Jordan, American Flow Control, Mueller Co. "A-2380 Series" C. Tapping Valves and Tapping Sleeves: 1. Tapping sleeves shall be solid stainless steel and valves shall conform with all others as mentioned above. D. Valve Boxes: 1. Cast iron, threaded screw extension sleeve type, adjustable suitable for depth of cover over pipe, with base and cover. 2. 3/ 16 in. thick, 5 in. diameter minimum. 3. Provide with suitable cast iron bases and covers. 4. Covers: Cast name designating type of service, e.g., "WATER" for water service. 2.07 RELATED MATERIALS A. Concrete: As specified in Section 03300 — Cast -in -Place Concrete. 03/2020 02510 - 4 of 22 CITY OF BAYTOWN WATER MAINS B. Meter Box: l . Cast iron to Owner's dimensions: ASTM A 48. C. The service line between Curb stop and Corporation Stop shall be CTS Polyethylene, SDR — 9. D. Corporation and Curb Stops and Fittings: ASTM B 62, NSF 61 lead free 3.0 EXECUTION A. Conform to requirements in Section 02534 - PVC Pipe, Section 02634 - Ductile Iron Pipe and Fittings, Section 02532W — HDPE, Section 02635 Steel Pipe and Fittings, and Section 02513 - Steel Pipe and Fittings for Large Diameter Water Lines. 3.02 PREPARATION A. Thoroughly clean pipe interiors of foreign matter before being lowered into trench. B. Clean hydrant and valve interiors of foreign matter before installation. C. Employ workmen who are skilled and experienced in laying pipe of type and joint configuration being furnished. Provide watertight pipe and pipe joints. D. Lay pipe to lines and grades shown on Drawings and Details. E. If asbestos -cement (A.C.) pipe is encountered, follow safety practices outline in American Water Works Association's publication, "Work Practices for A/C Pipe". Strictly adhere to "recommended practices" contained in this publication and make them "mandatory practices" for this project. F. For pipe diameters 36 inches and greater, clearly mark each section of pipe and fitting with unique designation on inside of pipe along with pressure class. Locate unique identifying mark minimum of five feet away from either end of each section of pipe. Provide one unique identifying mark in middle of each fitting. Place markings at consistent locations. Use permanent black paint and minimum letter height of 4 inches to mark designations. G. Contractor is responsible for assuring chosen manufacturer fulfills requirements for extra fittings and, therefore, is responsible for costs due to downtime if requirements are not met. 3.03 INSTALLATION A. Inspection: Carefully examine each piece of pipe for soundness and specifications compliance after delivery at trench before placing in trench. 03/2020 02510 - 5 of 22 CITY OF BAYTOWN WATER MAINS 2. Remove rejected pipe and fittings from site of work and replace with sound pipe. 3. Pipe and fittings will be rejected because of any of the following: a. Cracks in pipe or fittings. b. Damaged or cracked ends. c. Damaged gaskets or gasket grooves. d. Less than minimum wall thickness. e. Defects and defonnations. B. Cleaning: l . Clean interior of pipe and fittings of foreign matter before laying. 2. Keep interiors and ends clean during installation. 3. Keep joint contact surfaces clean during installation. 4. Take precautions to prevent foreign material from entering pipe during installation. 5. Do not place rubbish, tools, rags, or other materials in pipe. 6. Whenever pipe laying is stopped, place plugs in uncompleted ends of pipe. C. Installation: 1. Install pipe, couplings, and fittings in accordance with pipe manufacturer's recommendations. Conform to applicable installation specifications for types of pipes use. 2. Install gaskets and lubricants as recommended by manufacturer. 3. Full length of each barrel of pipe shall rest solidly on pipe bed with recesses excavated to accommodate bells and joints. 4. Take up and relay pipe that has grade or joint disturbed. 5. Do not joint pipe with water in trench. 6. Keep water out of trench until jointing is completed. 7. Do not lay water pipe closer than 10 ft. horizontally from sanitary sewer. 8. Do not locate joints at cross-overs with sanitary sewers closer than 9 ft. from cross -over point. 03/2020 02510 - 6 of 22 CITY OF BAYTOWN WATER MAINS 9. Where water lines cross sanitary sewers, construct in accordance with the City of Baytown Engineering Design Criteria Manual for water line or TCEQ standards whichever is more stringent10. Where pipe ends are left for future connections, install valve and plug or cap end. Forty feet minimum line section required between valves and plug or cap end. 11. Install concrete thrust blocking at bends and tees and at ends of lines to provide adequate reaction backing. 12. Lay not more than 100 feet of pipe in trench ahead of backfilling operations. 13. Dig trench proper width as shown in details. When trench width below top of pipe becomes 4 feet wider than specified, install higher class of pipe or improved bedding, as determined by Engineer. No additional payment will be made for higher class of pipe or improved bedding. 14. Use adequate surveying methods and equipment; employ personnel competent in use of this equipment. Horizontal and vertical deviations from alignment as indicated on Drawings shall not exceed 0.10 feet. Measure and record "as built" horizontal alignment and vertical grade at maximum of every 100 feet on record drawings. 15. Before assembling couplings, lightly coat pipe ends and outside of gaskets per manufacturer's specification. 16. Prevent damage to coating when placing backfill. Use backfill material free of large rocks or stones, or other material which could damage coatings. D. Setting Valves, Valve Boxes and Fire Hydrants: Set plumb. 2. Center valve boxes on valves. 3. Where feasible, locate valves outside area of roads and streets. 4. Carefully tamp back fill around each valve box to distance of 4 ft. on all sides or to undisturbed trench face if less than 4 ft. 5. Set hydrants at elevation so that connecting pipe will not have less cover than mains. 6. Set hydrants on concrete pad. 7. Depth of bury of hydrant is defined as distance from bottom of inlet pipe to ground line. 03/2020 02510 - 7 of 22 CITY OF BAYTOWN WATER MAINS Place concrete thrust block back of hydrant opposite pipe connections set against vertical face of trench to prevent from blowing off line. 9. Use 5/8 in. stock stainless steel bridle rods and rod collars. 10. Place not less than 5 cu. ft. of broken stone around base of hydrant to ensure drainage. 11. Compact backfill to grade in accordance with specification section 02318 — Excavation and Backfill for Utilities 12. Tighten stuffing boxes. 13. Test hydrant and valve in opened and closed position to ensure that parts are in working condition. E. Joints and Jointing: Rubber Gasketed Bell -and -Spigot Joints for PVC, Steel, and Ductile Iron Pipe: 2. a. After rubber gasket is placed in spigot groove of pipe, equalize rubber gasket cross section by inserting tool or bar recommended by manufacturer under rubber gasket and moving it around periphery of pipe spigot. b. Lubricate gaskets per manufacturer's specification. c. Fit pipe units together in manner to avoid twisting or otherwise displacing or damaging rubber gasket. d. After pipe sections are joined, check gaskets to ensure that no displacement of gasket has occurred. If displacement has occurred, remove pipe section and remake joint as for new pipe. Remove old gasket, inspect for damage and replace if necessary before remaking joint. e. Where preventing movement of 16-inch diameter or greater pipe is necessary due to thrust, use restrained joints as shown on Drawings. 1) Include buoyancy conditions for soil unit weight when computing thrust restraint calculations. 2) Do not include passive resistance of soil in thrust restraint calculations. f. Except for PVC pipe, provide means to prevent full engagement of spigot into bell as shown on Drawings. Means may consist of wedges or other types of stops as approved by Engineer. 03/2020 02510 - 8 of 22 CITY OF BAYTOWN WATER MAINS 2. Flanged Joints where required on Ductile Iron Pipe, or Steel Pipe: a AWWA C 207. Prior to installation of bolts, accurately center and align flanged joints to prevent mechanical pre -stressing of flanges, pipe and equipment. Align bolt holes to straddle vertical, horizontal or north -south center line. Do not exceed 3/64 inch per foot inclination of flange face from true alignment. b. Use full -face gaskets for flanged joints. Provide 1/8-inch-thick cloth inserted rubber gasket material. Cut gaskets at factory to proper dimensions. C. Use stainless steel nuts and bolts to match flange material. Use stainless steel nuts and bolts underground. Tighten bolts progressively to prevent unbalanced stress. Maintain at all times approximately same distance between two flanges at points around flanges. Tighten bolts alternately (180' apart) until all are evenly tight. Draw bolts tight to ensure proper seating of gaskets. d Full length bolt isolating sleeves and washers shall be used with flanged connections. e. For in -line flange joints 30 inches in diameter and greater and at butterfly valve flanges, provide Pyrox G-10 with nitrite seal, conforming to ANSI A 21.11 mechanical joint gaskets. For in -line flange joints sized between 12 inches in diameter and greater and 24 inches in diameter and smaller, provide Phenolic PSI with nitrite seal gasket conforming to ANSI A 21.11 mechanical joint gaskets. 3. Welded Joints (Steel Pipe): a Prior to starting work, provide certification of qualification for welders employed on project for type of work procedures and positions involved. b. Joints: AW WA C 206. Full -fillet, single lap -welded slip -type either inside or outside, or double butt -welded type; use automatic or hand welders; completely penetrate deposited metal with base metal; use filler metal compatible with base metal; keep inside of fittings and joints free from globules of weld metal which would restrict flow or become loose. Do not use mitered joints. For interior welded joints, complete backfilling before welding. For exterior field -welded joints, provide adequate working room under and beside pipe. Use exterior welds for 30-inch and smaller. 03/2020 02510 - 9 of 22 CITY OF BAYTOWN WATER MAINS C. Furnish welded joints with trimmed spigots and interior welds for 36- inch and larger pipe. d Bell -and -spigot, lap -welded slip joints: Deflection maybe taken at joint by pulling joint up to 3/4 inch as long as 1 '/2 inch minimum lap is maintained. Spigot end may be miter cut to take deflections up to 5 degrees as long as joint tolerances are maintained. Miter end cuts of both ends of butt -welded joints may be used for joint deflections of up to 5 degrees. e. Align piping and equipment so that no part is offset more than 1/8 inch. Set fittings and joints square and true, and preserve alignment during welding operation. For butt welded joints, align abutting ends to minimize offset between surfaces. For pipe of same nominal wall thickness, do not exceed 1/16 inch offset. Use line-up clamps for this purpose; however, take care to avoid damage to linings and coatings. f. Protect epoxy or cement lining during welding by draping an 18-inch wide strip of heat resistant material over top half of pipe on each side of lining holdback to avoid damage to lining by hot splatter. Protect tape coating similarly if external welding is required. g. Welding rods: Compatible with metal to be welded to obtain strongest bond, E-7018. Root or "Stringer" pass shall be performed with 6011 rods and Filler and Cap shall be done using 7018 rods. h Deposit metal in successive layers to provide at least 2 passes or beads for automatic welding and 3 passes or beads for manual welding in completed weld. i. Deposit no more than 1/4 inch of metal on each pass. Thoroughly clean each individual pass with wire brush or hammer to remove dirt, slag or flux. j. Do not weld under weather condition that would impair strength of weld, such as wet surface, rain or snow, dust or high winds, unless work is properly protected. k Make tack weld of same material and by same procedure as completed weld. Otherwise, remove tack welds during welding operation. L Remove dirt, scale, and other foreign matter from inside piping before tying in sections, fittings, or valves. m Welded Joints for Large Diameter Water Lines: 03/2020 02510 - 10 of 22 CITY OF BAYTOWN WATER MAINS 1) Furnish pipe with trimmed spigots and interior welds for 36 inch and larger pipe. 2) Use exterior welds for 30 inch and smaller. 3) Only one end may be miter cut. Miter end cuts of both ends of butt -welded joints may be used for joint deflections of up to 2 degrees. 4) For large diameter water lines, employ an independent certified testing laboratory, approved by Engineer, to perform weld acceptance tests on welded joints. Include cost of such testing and associated work to accommodate testing in contract unit price bid for water line. Furnish copies of test reports to Engineer for review. Engineer has final decision as to suitability of welds tested. A) Weld acceptance criteria: i) Cracking. ii) Lack of fusion/penetration. iii) Slag which exceeds one-third (t) where (t) equals material thickness. iv) Porosity/Relevant rounded indications greater than 3; 16 inch; rounded indication is one of circular or elliptical shape with length equal to or less than three times its width. v) Relevant linear indications in which length of linear indication exceeds three times its width. vi) Four or more relevant 1/ 16 inch rounded indications in line separated by 1/16 inch or less edge to edge. n After pipe is joined and prior to start of welding procedure, make spigot and bell essentially concentric by jacking, shimming or tacking to obtain clearance tolerance around periphery of joint except for deflected joints. o. Furnish each welder employed steel stencil for marking welds, so work of each welder can be identified. Mark pipe with assigned stencil adjacent to weld. When welder leaves job, stencil must be voided and not duplicated. Welder making defective welds must discontinue work and leave project site. Welder may return to project site only after recertification P. Provide cylindrical corrosion barriers for epoxy lined steel pipe 24 inch diameter and smaller, unless minimum wall thickness is 0.5 inches or greater. 03/2020 02510 - 11 of 22 CITY OF BAYTOWN WATER MAINS 1) In additional to welding requirements contained herein Paragraph 3.06; conform to protection fitting manufacturer's installation recommendations. 2) Provide services of technical representative of manufacturer available on site at beginning of pipe laying operations. Representative to train welders and advice regarding installation and general construction methods. Welders must have 12 months prior experience installing protection fittings. 3) All steel pipe is to have cutback 3/4 inch to no greater than 1 inch of internal diameter coating from weld bevel. 4) Furnish steel fittings with cylindrical corrosion barriers with shop welded extensions to end of fittings. Extension length to measure no less than diameter of pipe. Shop applies lining in accordance with AWWA C210 or AWWA C213. 5) All steel pipe receiving field adjustments are to be cold cut using standard practices and equipment. No cutting using torch is to be allowed. 4. Restrained Joints: a For existing water lines and water lines less than 16 inches in diameter, restrain pipe joints with concrete thrust blocks. b. Thrust restraint lengths shown on Drawings are minimum anticipated lengths. These lengths are based on deflections indicated for large diameter lines and ductile iron pipe for small diameter lines. Adjustments in deflections or use of other pipe material may result in reduction or increase of thrust lengths. Perform calculations by pipe manufacturer to verify proposed thrust restraint lengths. Submit calculations for all pipe materials sealed by a registered Professional Engineer in State of Texas for review by Engineer. Make adjustments in thrust restraint lengths at no additional cost to City. C. Passive resistance of soil will not be permitted in calculation of thrust restraint. d For 16 inch lines and larger use minimum 16 foot length of pipe in and out of joints made up of beveled pipe where restraint joint lengths are not identified on Drawings. Otherwise, provide restraint joints for a minimum length of 16 feet on each side of beveled joints. e. Installation: 03/2020 02510 - 12 of 22 CITY OF BAYTOWN WATER MAINS 1) Install restrained joints mechanism in accordance with manufacturer's recommendations. 2) Examine and clean mechanism; remove direct, debris and other foreign material. 3) Apply gasket and joint NSF 61 FDA per manufacturer's specification. 4) Verify gasket is evenly seated. 5) Do not over stab pipe into mechanism £ Prevent any lateral movement of thrust restraints throughout pressure testing and operation. g. Place 2500 psi concrete conforming to Section 03315 - Concrete for Utility Construction, for blocking at each change in direction of existing water lines, to brace pipe against undisturbed trench walls. Finish placement of concrete blocking, made from Type I cement, 4 days prior to hydrostatic testing of pipeline. Test may be made 2days after completion of blocking if Type I1 cement is used. 5. Joint Grout (Steel Pipe): a Mix cements grout mixture by machine except when less than 1/2 cubic yard is required. When less than 1/2 cubic yard is required, grout may be hand mixed. Mix grout onlyin quantities for immediate use. Place grout within 20 minutes of mixing. Discard grout that has set. Retempering of grout by any means is not permitted. b. Prepare grout in small batches to prevent stiffening before it is used. Do not use grout which has become so stiff that proper placement cannot be assured without retempering. Use grout for filling grooves of such consistency that it will adhere to ends of pipe. C. Surface Preparation: Remove defective concrete, laitance, dirt, oil, grease and other foreign material from concrete surfaces with wire brush or hammer to sound, clean surface. Remove rust and foreign materials from metal surfaces in contact with grout. 03/2020 02510 - 13 of 22 CITY OF BA YTOWN WATER MAINS d Follow established procedures for hot and cold weather concrete placement. e. Complete joint grout operations and backfilling of pipe trenches as closely as practical to pipe laying operations. Allow grouted exterior joints to cure at least 1 hour before compacting backfill. f. Grouting exterior joint space: Hold wrapper in place on both sides of joint with minimum 5/8-inch-wide steel straps or bands. Place no additional bedding or backfill material on either side of pipe until after grout band is filled and grout has mechanically stiffened. Pull ends of wrapper together at top of pipe to form access hole. Pour grout down one side of pipe until it rises on other side. Rod or puddle grout to ensure complete filling of joint recess. Agitate for 15 minutes to allow excess water to seep through joint band. When necessary, add more grout to fill joint completely. Protect gap at top of joint band from backfill by allowing grout to stiffen or by covering with structurally protective material. Do not remove band from joint. Proceed with placement of additional bedding and backfill material. g. Interior Joints for Pipe 24 inches and Smaller: Circumferentially butter bell with grout prior to insertion of spigot, strike off flush surplus grout inside pipe by pulling filled burlap bag or inflated ball through pipe with rope. After joint is engaged, finish off joint grout smooth and clean. Use swab approved by Project Manager for 20-inch pipe and smaller. h Protect exposed interior surfaces of steel joint bands by metallizing, by other approved coatings, or by pointing with grout. Joint pointing may be omitted on potable water pipelines if joint bands are protected by zinc metalizing or other approved protective coatings. Remove and replace improperly cured or otherwise defective grout. j. Strike off grout on interior joints and make smooth with inside diameter of pipe. k When installed in tunnel or encasement pipe and clearance within casing does not permit outside grout to be placed in normal manner, apply approved flexible sealer, such as Flex Protex or equal, to outside joint prior to joint engagement. Clean and prime surfaces receiving sealer in accordance with manufacturer's recommendations. Apply sufficient quantities of sealer to assure complete protection of steel in 03/2020 02510 - 14 of 22 CITY OF BA YTOWN WATER MAINS joint area. Fill interior of joint with grout in normal manner after joint closure. l Interior Joints for Water Lines 30 inches and Larger: Clean joint space, wet joint surfaces, fill with stiff grout and trowel smooth and flush with inside surfaces of pipe using steel trowel so that surface is smooth. Accomplish grouting at end of each work day. Obtain written acceptance from Project Engineer of inside joints before proceeding with next day's pipe laying operation. During inspection, insure no delamination of joint mortar has occurred by striking joint mortar lining with rubber mallet. Remove and replace delaminated mortar lining. M. Work which requires heavy equipment to be over water line must be completed before mortar is applied to interior joints. n Do not apply grout to joints that are out of tolerance until acceptable repairs are made. 6. Large Diameter Water Main Joint Testing: In addition to testing individual joints with feeler gauge approximately 1 /2 inch wide and 0.015-inch thick, use other joint testing procedure approved or recommended by pipe manufacturer which will help ensure watertight installation priorto backfilling. Perform tests at no additional cost to City. 7. Make curves and bends by deflecting joints or other method as recommended by manufacturer and approved by the Engineer. Submit details of other methods of providing curves and bends which exceed manufacturer's recommended deflection prior to installation. a Deflection of pipe joints shall not exceed maximum deflection recommended by pipe manufacturer, unless otherwise indicated on Drawings. b. If deflection exceeds that specified but is less than 5 percent, repair entire deflected pipe section such that maximum deflection allowed is not exceeded. C. If deflection is equal to or exceeds 5 percent from that specified, remove entire portion of deflected pipe section and install new pipe. d Replace, repair, or reapply coatings and linings as required. e. Assessment of deflection may be measured by the Engineer at location along pipe. Arithmetical averages of deflection or similar average measurement methods will not be deemed as meeting intent of standard. 03/2020 02510 - 15 of 22 CITY OF BAYTOWN WATER MAINS f. When rubber gasketed pipe is laid on curve, join pipe in straight alignment and then deflect to curved alignment. 8. Closures Sections and Approved Field Modifications to Steel Pipe and Fittings: a Apply welded -wire fabric reinforcement to interior and exterior of exposed interior and exterior surfaces greater than 6 inches in diameter. Welded -wire fabric: minimum W l; maximum spacing 2 inches by 4 inches; 3/8 inch from surface of steel plate or middle third of lining or coating thickness for mortar thickness less than 3 4 inch. b. Fill exposed interior and exterior surfaces with nonshrink grout. C. For pipe diameters 36 inches and greater, perform field welds on interior and exterior of pipe. d For large diameter water lines, provide minimum overlap of 4 inches of butt strap over adjacent piece on butt -strap closures. F. Cathodic Protection Appurtenances: Where identified on Drawings, modify pipe for cathodic protection as detailed on Drawings and specified. Unless otherwise noted, provide insulation kits including test stations at connections to existing water system or at locations to isolate one type of cathodic system from another type, between water line, access manhole piping and other major openings in water line, or as shown on Drawings. 2. Bond joints for pipe installed in tunnel or open cut, except where insulating flanges are provided. Weld strap or clip between bell and spigot of each joint or as shown on Drawings. No additional bonding required where joints are welded for thrust restraint. Repair coatings as specified by appropriate AWWA standard, as recommended by manufacturer, and as approved by the Engineer 3. Bonding Strap or Clip: Free of foreign material that may increase contact resistance between wire and strap or clip. 03/2020 02510 - 16 of 22 CITY OF BAYTOWN WATER MAINS G. Anchorage of Fittings: Anchor tees, elbows and plugs in water mains with concrete thrust blocks. 2. Place blocks so that joints will be accessible for inspection and repair. H. Handling: Place pipe along project site where storm water or other water will not enter or pass through pipe. 2. Load, transport, unload, and otherwise handle pipe and fittings to prevent damage of any kind. Handle and transport pipe with equipment designed, constructed and arranged to prevent damage to pipe, lining and coating. Do not permit bare chains, hooks, metal bars, or narrow skids or cradles to come in contact with coatings. Where required, provide pipe fittings with sufficient interior strutting or cross bracing to prevent deflection under their own weight. 3. Hoist pipe from trench side into trench by means of sling of smooth steel cable, canvas, leather, nylon or similar material. 4. For large diameter water lines, handle pipe only by means of sling of canvas, leather, nylon, or similar material. Sling shall be minimum 36 inches in width. Do not tear or wrinkle tape layers. 5. Use precautions to prevent injury to pipe, protective linings and coatings. a. Package stacked pipe on timbers. Place protective pads under banding straps at time of packaging. b. Pad fork trucks with carpet or other suitable material. Use nylon straps around pipe for lift when relocating pipe with crane or backhoe. C. Do not lift pipe using hooks at each end of pipe. d. Do not place debris, tools, clothing, or other materials on pipe. 6. Repair damage to pipe or protective lining and coating before final acceptance. 7. For cement mortar line and coated steel pipe, permit no visible cracks longer than 6 inches, measured within 15 degrees of line parallel to pipe longitudinal axis of finished pipe, except: a. In surface laitance of centrifugally cast concrete. b. In sections of pipe with steel reinforcing collars or wrappers. C. Within 12 inches of pipe ends. 03/2020 02510 - 17 of 22 CITY OF BAYTOWN WATER MAINS 8. Reject pipe with visible cracks (not meeting exceptions) and remove from project site. Cleaning: Thoroughly clean and dry interior of pipe and fittings of foreign matter before installation, and keep interior clean until Work has been accepted. Keep joint contact surfaces clean until jointing is completed. Do not place debris, tools, clothing or other materials in pipe. After pipe laying and joining operations are completed, clean inside of pipe and remove debris. J. Inspection: Before installation, inspect each pipe and fitting for defects. Reject defective, damaged or unsound pipe and fittings and remove them from site. 3.04 WET CONNECTIONS A. Definitions: Wet connections consist of isolating sections of pipe to be connected with installed valves, draining the isolated sections, and completing the connections. 2. Connection of 2 inch or smaller lines, which may be referred to on Plans as "2 inch standard connections" or "gooseneck connections" will be measured as 2" wet connections. This item is not to be used as any part of a 2-inch service line. B. Materials: Corporation stops and saddles shall conform to requirements of Section 02515- Water Tap and Service Line Installation. 2. Valves shall conform to requirements of Section 02541 — Fire Hydrant Assembly. 3. Brass fittings shall conform to requirements of AWWA C800. C. Execution: Plan wet connections in such manner and at such hours as to least inconvenience public. Notify Public Works Department at least 48 hours in advance of making connections. 2. DO NOT OPERATE VALVES ON MAINS IN USE BY OWNER. Owner will handle, at no cost to Contractor, all operations involving opening and closing valves for wet connections. 3. Conduct connection operations when Inspector is at job site. Connection work shall progress without interruption until complete, once existing mains have been cut or plugs have been removed for making connections. 03/2020 02510 - 18 of 22 CITY OF BAYTOWN WATER MAINS D. 2-Inch Wet Connections: 1. Tap water main. Provide and install corporation stops, saddles, as required for line and grade adjustment; and brass fittings necessary to adapt to existing main. Provide one Corporation Stop at main line and one Curb Stop at meter. The service line between Curb Stop and Corporation Stop shall be CTS Polyethylene, SDR-9. 3.05 CUT, PLUG AND ABANDONMENT OF MAINS A. Materials: Concrete for thrust blocks: Class B conforming to requirements of Section 03305. 2. Plugs and clamps shall be suitable for type of pipe to be plugged. B. Execution: Do not begin cut, plug and abandonment operations until replacement main has been constructed, disinfected, and tested, and all service lines have been transferred to replacement main. 2. Install plug, clamp, and concrete thrust block and make cut at location shown on Plans. 3. Main to be abandoned shall not be valved off and shall not be cut orplugged other than at supply main or as shown on Plans. 4. After main to be abandoned has been cut and plugged, check for other sources feeding abandoned main. If sources are found, notify Engineer immediately. Cut and plug abandoned main at point of other feed as directed by Engineer. 5. Plug or cap all ends or openings in abandoned main in an acceptable manner approved by Engineer. 6. Remove and dispose of all surface identifications such as valve boxes and fire hydrants. Valve boxes in improved streets, other than shell, may be poured full of concrete after removing cap. 7. Backfill all excavations in accordance with Section 02318 — Excavation and Backfill for Utilities. 8. Repair all street surfaces in accordance with Section 02980 — Pavement Repair. 03/2020 02510 - 19 of 22 CITY OF BAYTOWN WATER MAINS 3.06 HYDROSTATIC TESTING A. Hydrostatically test all new water pipelines for liquids before connecting to water distribution system. B. Pipelines shall be tested in lengths between valves, or plugs, of not more than 1,500 feet unless greater length is approved by Engineer. C. Conduct hydrostatic tests in presence of Engineer. D. Preparation: Disinfect water system pipelines prior to hydrostatic testing. E. Test Procedures: Furnish, install, and operate connections, pump, meter and gages necessary for hydrostatic testing. 2. Allow pipeline to sit minimum of 24 hours from time it is initially disinfected until testing begins, to allow pipe wall or lining material to absorb water. Contractor should be aware that periods of up to 7 days may be required for mortar lining to become saturated. 3. Expel all air and apply a minimum test pressure of 125 psi or 150 psi as directed by Engineer. 4. Maintain test pressure for 8 hours. If a large quantity of water is required to maintain pressure during test, testing shall be discontinued until cause of water loss is identified and corrected. F. Allowable Leakage for Water Mains: During hydrostatic tests, no leakage will be allowed for sections of water mains consisting of welded joints. 2. Maximum allowable leakage for water mains with rubber gasketed joints: 11.65 gallons per inch nominal diameter per mile of pipe per 24 hours while testing at the required pressure. G. Correction for Failed Tests: Repair all joints showing visible leaks on surface regardless of total leakage shown on test. Check all valves and fittings to ensure that no leakage occurs that could affect or invalidate test. Remove any cracked or defective pipes, fittings and valves discovered during pressure test and replace with new items. 2. Repeat test until satisfactory results are obtained. 03/2020 02510 - 20 of 22 CITY OF BA YTOWN WATER MAINS 3.07 DISINFECTION A. All waterlines constructed shall be promptly disinfected before any tests are conducted on waterlines and before waterlines are connected to water distribution system. B. Water for disinfection and flushing will be furnished without charge to Contractor. C. Preparation: Furnish all required temporary blind flanges, cast-iron sleeves, plugs, and other items needed to facilitate disinfection of new mains prior to connecting them to water distribution system. Normally, each valved section of waterline requires two each 3/4-inch taps. A 2-inch minimum blow -off is required for waterlines up to and including 6-inch diameter. 2. .Fire hydrants shall be used as blow -offs to flush newly constructed waterlines 8-inch diameter and above. Where fire hydrants are not available on waterlines, locations and designs for blow -offs shall be as indicated on Plans. Install temporary blow -off valves and remove promptly upon successful completion of disinfection and testing. Abandon by turning off core and using a stainless steel cap. 3. Slowly fill each section of pipe with water in a manner approved by Engineer. Average water velocity when filling pipeline should be less than 1 fps and shall not, under any circumstance, exceed 2 fps. Before beginning disinfection operations, expel all air from pipeline. 4. All excavations made shall be backflled immediately after installation of risers or blow -offs. 5. Install blow -off valves at end of main to facilitate flushing at all dead-end water mains. Install permanent blow -off valves/auto flusher per drawing Ll D. Disinfection: 1. Use not less than 100 parts of chlorine per million parts of water. Introduce chlorinating material to water lines in accordance with AWWA C651. After contact period of not less than 24 hours, flush system with clean water until residual chlorine is no greater than 1.0 parts per million parts of water. Open and close valves in lines being sterilized several times during contact period. If super -chlorinated water (i.e. chlorine concentration above 4mg/1) is used for cleaning water main disinfection and flushing, the water must be dechlorinated prior to discharge. The water discharged into the stormsewer system or natural waterway must meet the Clean Water Act (33 USC § 1251 et seq.) and any subsequent amendments thereof. 2. If a chemical compound is used for a sterilizing agent, it shall be placed in pipes as directed by Engineer. 03/2020 02510 - 21 of 22 CITY OF BAYTOWN WATER MAINS E. Bacteriological Testing: After disinfection and flushing of waterlines, bacteriological tests will be performed by Owner or testing laboratory in accordance with Section 01450 — Testing Laboratory Services. If test results indicate need for additional disinfection of waterlines based upon Texas Department of Health and TCEQ requirements, Contractor shall perform additional disinfection operations at no additional cost to the Owner. E. Completion: Upon completion of disinfection and testing, remove risers except those approved for use in subsequent hydrostatic testing, and backfill excavation promptly. END OF SECTION 03/2020 02510 - 22 of 22 2. Cement Treated Base (CTB) in Lieu of Lime treated Subgrade (LTS Plan Sheets Z oOW p XNJ � d tipZ C mtOQi mpZ 2X¢ Or ¢ WO ¢ O O Z ¢ - oa Q N W O ¢ ¢ v ? ¢ r z DmQ O Z W -wOQ O Z J-< rOO�UZ¢NO z¢ma -JJ-¢- NN- ¢NpUr ¢ ¢ > p ¢ Z¢ < N a¢¢ai0 U ; - ZO ¢ 0 Jmz -p0�Z <wwu- O-w i1-J¢WW ¢¢ N¢ Z u-O Z U¢ O >• S Z¢ O - Y U J -x zW02Wsp¢ N u� 70a aa- ¢�Nu> N�-zaz¢az Y �awo uNJ ;s Wa U Z N W¢ p O W W N N d Owl 0z Z Q J Q z 0 1 Y O ¢w¢-o;wWNzu zNZNWNa -; wwz i Oww¢¢J¢ pWW�Z-waY OJY- 2N Oc�z� - -¢uwiQdd�a�a�i-zuma��Nu7—z —oo az — O M ONO O N ONw W ¢d OF NO¢ N ~ NNUW Jz x N 0 2 ZJX Z p�uOxuaWOwO rY Ou-J��Oowwr¢ O O ZZNW�¢U d!-I. JQJ Nti¢NI- <2S 23U0 . •-pa-N-WF¢w- aoo�ou u<uiJ pJJwawuW.-a1-J N- ¢Qwawa-w w z Na�w-Jwxawzay O o ,jo < ouwu¢ww¢wwo-JW OZa pu.-w-�OaON¢a�OZwr W x^OxOaSWOwx-wuWW¢arz-2wwww¢J-a20ZZOwW r- <VNO = N N1 P N �p r QD Di MMI ISIX3 w' o e MOtl -Ls 1X3 —1 l� u _ a Z Q N Z O 0 ¢a<Zo 0 o am z � Um LL ¢�0 o OZJ rv<� zz a pNa _ow ¢w-u amp _ M% 1STx3— —_ d�'^o .uz MO8 Z8d NI pJ 000 ¢u ¢Oz wi rc o s �D'I dAL-N]2-Id] IMNIDJ"" '1\I@11) 10111 —d\�!9iD - \OA9DUD!99d\�D!�an��v In —I L-1011/9 1071101d �D'I dAL-N]2-Id] IMNIDJ"" '1\I@11) 10111 —d\�!9iD - \OA9DUD!99d\�D!�an��v In —I L-1011/9 1071101d 3. Drainage Revisions Associated with RFI 19 Attachment A Change Order Quantity Summary Project: Garth Rd. Phase A RDWY 1901 IH10 to South of Archer Rd. County: Harris CSJ #0912-72-359 City of Baytown - Garth Rd. Phase A&B RDWY 1901 C51#0912-72-359 Change Order - Unit Cost Breakdown Line Number Item Code Description P Current Quantity Q Y Unit Price Unit Total Qty Change Revised Quantity CO Extension 62 400 CEM STABIL BKFL 17,175.00 70.00 CY (80.05) 17,094.95 $ (5,603.64) 68 462 CONC BOX CULV (8 FT X 4 FT) 1,956.00 709.36 LF (46.00) 1,910.00 $ (32,630.56) 69 462 CONC BOX CULV (10 FT X S FT) 4,903.00 1,032.62 LF (56.00) 4,847.00 $ (57,826.72) 83 465 1CT BOX (COMPL)(SPL) (11'xll') 1.00 $ 41,652.61 EA 1 2.00 $ 41,652.61 84.5 465 1CT BOX (COMPL)(SPL) (13'xl3') - $ 64,017.51 EA 1 1.00 $ 64,017.51 TOTAL: $ 909.20 Garth Rd. COti004 - RA 19 - Quantity Summary Updated: 5/18/2026 CO Summary (BREAKDOWN) 11:52 AM Contractor Pricing Submittal Bryce Watson From: Cory Halley <Cory.HaIley@harperbro.com> Sent: Monday, May 11, 2026 12:15 PM To: Bryce Watson Cc: Brian Hancock Subject: 13xl3 Junction Box C.O. Attachments: 13x13 Junction Box.pdf Follow Up Flag: Follow up Flag Status: Completed Bryce, Please see the attached. Thanks Cory Halley Project Manager 1310 Rankin RD, Suite 200 Houston, TX 77073 C:817.751.8412 HARPER BROTHERS Project: Garth Rd Phase A&B Control: 0912-72-359 Scope of Work: 13x13 Junction Box HBC LABOR ITEMS QUANTITY UOM MANHOURS HOURLY RATE COST Foreman Undergrond 1.00 FA 20.00 $ 56.00 $ 1,120.00 _ .. ......... Grademan .......... 1.00 EA s._......__..__..__... 20.00 $ 20.00E ., $ ...... ..... _., 400.00 _ Laborer, Storm ..»._._..«__._.«._..»._.__._..__._._...--_...._......«__... 2.00 EA 20.00 ......_......._....... _..._._...._....__...._........«.._;...._.__...._.._..._..., $ 20.00 i $ 800.00 _ _......_._.__. Pipelayer ..--..._...--........ .__.._...__......_......._.«..«._.._....- ....... , _ 1.00 _ ....:_.......____._._._.. EA 20.00 _......................... $ 21.00 ._........_...__...... $ . 420.00 ..................,............ .......... Operator, Backhoe_ ... ......--_..------- __«..«....._»»_._...A.....«..««.«..»..._.....» . 1.00 _...»_.._.._....___..«...., EA .L........._.._.__ 20.00 _.... $ 28.50 «L»....----.«...._..._ $ 570.00 Operator, Crane _._.___....._.__._-.____._..-----.___.__._._ 1.00 EA ._... 20.00 $ 38.00 $ ......... 760.00 ._.____................. Operator, Loader ........ _....... ............. _ ... ., .. 1.00 EA 20.00 $ 26.00 $ 520.00 __.__._......_...._.__..«._.......«__.._......_.«..«__«__.�_._.....__..__.._._._.... �..... .......... i $ - i f f ! $ - f f $ - f f $ f i $ - i f , ! $ f t f $ SUBTOTAL HBC LABOR: $ 4,590.00 ........ ............. ... _.«.......... ___..... .......................... _«.._._._._._.......... _....... _.......... _....... _...... _........_ BURDEN @: 55.00% $ 2,524.50 _._._..... LABOR MARK-UP: 25.00°% ...,....,. $ _ 1,147.50 TOTAL TSC LABOR: $ 8.262.00 13x13 Juniction Box 7% CEM STAB Sand 1 TOTAL TSC MATERIAL: $ 41.522.81 1 232.07 _.....a ....__...._----------------- ............ ............ ........ __................ .. f TOTAL HBC ITEMS: $ 63,383.68 TOTAL SUBCONTRACTOR ITEMS: $ - SUBTOTAL 63,383.68 BOND 1% $ 633.84 TOTAL $ 64,017.51 3,481.05 1,189.95 459.75 .............. Page 1 of e' 0 Oldcastle Infrastructure' Contract & Proposal A CRH COMPANY 2120 FM 359 South Oldcastleinfrastructure.com Quote Number: Q-401206-1 Brookshire TX, 77423-9023 (281)-733-3276 Quote Date: 04/28/2026 Customer Number: 1010205697 Quote To: HARPER BROTHERS CONSTRUCTION, LLC 654 N SAM HOUSTON PKWY E. STE 330 Houston TX, 77060-5919 Contact: Phone: Email: Notes: Ship To: Job Name: Garth Rd Garth Rd Baytown TX, 77521 Quote Expiration: 05/28/2026 Terms: Payment: Delivery Terms: Standard or LTL Tax Exempt: Yes Product Description Qty Unit Mark Unit Price Amount PH10000015 13X13 JUNCTION BOX 1 EA Includes: 13X13 clamshell junction box with risers or cone, grade rings, and loose 32" cast iron ring & cover * Send signed approved quote to: david.newton@oldcastle.com Signature for Approval Signature Title $32,790.00 $32,790.00 Subtotal $32,790.00 Est Sales Tax $0.0C Subtotal $32,790AC Quote Total (US) S32,790.0C Print Name Date Purchase Order Number Heidelberg Materials Heidelberg Materials HM South Texas Stabilized Sand LLC P.O. BOX 1830 SUGAR LAND, TEXAS 77487-1830 281/491-7376 FAX 281/491-2756 Quotation Submitted by: lErnest Lizcano I Today's Date I Bid Date lEnd Date Mobile: 832-278-9576 1 5/18/2026 8/20/2025 2/16/2026 Customer: Harper Brothers Type: Choose between Sub/sub/, Sub, Prime, Home Bldr or Owner Contact: Brian Phone: 346.323.0686 Email: Brian.Hancock(qharperbro.com Project Name: Garth Rd. Phases A&B Project Address: From 1 10 to Archer Rd P.O.# Job # Total Tonnage: 1 30,000 Plant: 1 12 Zone: I 6 Key Map: 1501 B Accepted by: (Contractor) Date: Is this job tax exempt? (Type Yes or No in box to the left) **Sales Tax is due and payable until a properly executed exemption certificate is received** GCSM Approved by: Stabilized Sand Products Delivered Price FOB Price 1.1 sack per ton 5% stabilized sand per ton 100 PSI per ton 1.5 sack per ton 7% stabilized sand per ton $ 28.55 $ 23.00 2.0 sack per ton 200 PSI/ 2.5 sack per ton Mortar sand per ton Bank Sand per load Select fill per load Bank Sand per ton $ 18.10 Other Date: Due to the shortage of trucks, HM South Texas Stabilized Sand LLC cannot guarantee daily delivered tonnage BANK SAND BASED ON AVAILABILITY OF TRUCK. Effective 5/23/2022: All prices must be accepted within 15 days from date of quote to secure pricing. Prices are firm for 6 months only (unless noted and agreed upon in writing on quote.) All prices are subject to 5 % escalation every six months. Prices are also firm as whole job prices only. Prices do not include sales tax if applicable. Prices quoted are for a minimum of 14 tons freight. EquipmentWatch . www.equipmentwatch.com All prices shown in US dollars ($) Internal Charue Rate* May 11, 2026 Tadano GR-1000XL-2 Rough Terrain Hydraulic Cranes Size Class: 80.5 - 110.4 mt Weight: Configuration for GR-1000XL-2 Axle Configuration 4 X 4 Maximum Boom Length 154.2 ft Maximum Lift Capacity 90.7 Ibs Horsepower 267 hp Power Mode Diesel Hourly Ownership Costs Standard Value User Adjusted Value Variance Depreciation USD $91.95/hr Cost of Facilities Capital (CFC) USD $39.621hr Overhead USD $57.72/hr Overhaul Labor USD $8.16/hr Overhaul Parts USD $68.12/hr Total Hourly Ownership Cost: USD S265.57/hr User Defined Adjustments: Hourly Operating Costs Standard Value User Adjusted Value Variance Field Labor USD $4.08mr Field Parts USD $95.751hr Ground Engaging Component (GEC) USD $0.00/hr Tire USD $11.47/hr Electrical/Fuel USD $55.51/hr Lube USD $13.90/hr Total Operating Ownership Cost: USD $180.721hr User Defined Adjustments: Total Standard Value User Adjusted Value Variance Hourly Ownership Costs USD $265.57/hr Hourly Operating Costs USD $180.72/hr Total Hourly Cost USD $446.29 Non -active use rates Standby Idle Active Rate Standard Value USD $189.29/hr USD $321.09/hr Internal Charge Rate displayed using default cost factors Revised Date: 2nd quarter 2026 * lormody known as Custom Cost Evaluator User Adjusted Value The equipment represented in this report has been exclusively prepared for (bids@harperbro.com) Variance USD $446.29 EquipmentWatch . www.equipmentwatch.com All prices shown in US dollars ($) Internal Charue Rate* Ford SUPER DUTY F-250 XLT 4X4 GAS Light Duty Trucks Size Class: 2 Weight: N/A Configuration for SUPER DUTY F-250 XLT 4X4 GAS Power Mode Gasoline Wheelbase 142 Inches Model Trim XLT Gross Vehicle Weight Rating 10000 Pounds Hourly Ownership Costs May 11, 2026 Standard Value User Adjusted Value Variance Depreciation USD $5.10/hr Cost of Facilities Capital (CFC) USD $2.64/hr Overhead USD $3.49/hr Overhaul Labor USD $1.17fhr - - Overhaul Parts USD $5.041hr Total Hourly Ownership Cost: USD $17.45/hr User Defined Adjustments: Hourly Operating Costs Standard Value User Adjusted Value Variance Field Labor USD $2.491hr Field Parts USD $4.88/hr Ground Engaging Component (GEC) USD $0.00thr Tire USD $0.71/hr Electrical/Fuel USD $4.411hr Lube USD $0.711hr - Total Operating Ownership Cost: USD $13.201hr User Defined Adjustments: Total Standard Value User Adjusted Value Variance Hourly Ownership Costs USD $17.45/hr Hourly Operating Costs USD $13.20/hr Total Hourly Cost USD S30.65 Non -active use rates Standard Value User Adjusted Value Variance Standby USD $11.23/hr Idle USD $21.86/hr Active Rate Internal Charge Rate displayed using default cost factors USD $30.65I Revised Date: 2nd quarter 2026 formerly known as Custom Cost Evaluator The equipment represented in this report has been exclusively prepared for (bids@harperbro.com) EquipmentWatch_ www. equipmentwatch.com All prices shown in US dollars ($) Internal Charae Rate* Volvo L90H 4-Wd Articulated Wheel Loaders Size Class: 175-199hp Weight: NIA May 11, 2026 Configuration for L90H Horsepower 184.0 hp Hourly Ownership Costs Standard Value User Adjusted Value Variance Depreciation USD $14.08/hr - - Cost of Facilities Capital (CFC) USD $6.19/hr Overhead USD $11.51/hr Overhaul Labor USD $4.781hr Overhaul Pans USD $5.761hr - - Total Hourly Ownership Cost: User Defined Adjustments: USD S42.32/hr Hourly Operating Costs Standard Value User Adjusted Value Variance Field Labor USD $5.91/hr Field Parts USD $5.62/hr Ground Engaging Component (GEC) USD $0.75/hr Tire USD S3.80/hr Electrical/Fuel USD $17.36/hr Lube USD $3.56/hr - - Total Operating ownership Cost: USD S37.0211hr - - User Defined Adjustments: Total Standard Value User Adjusted Value Variance Hourly Ownership Costs USD $42.32/hr Hourly Operating Costs USD $37.02/hr Total Hourly Cost USD $79.33 Non -active use rates Standard Value User Adjusted Value Standby USD $31.78/hr Idle USD $59.681hr - Active Rate Internal Charge Rate displayed using default cost factors Revised Date: 2nd quarter 2026 'formerly known as Custom Cost Evaluatot The equipment represented in this report has been exclusively prepared for (bids@harperbro.com) Variance USD $79.33 EquipmentWatch . www.equipmentwatch.com All prices shown in US dollars ($) Internal Charge Rate* May 11, 2026 Hitachi ZAXIS 45OLC-3 Crawler Mounted Hydraulic Excavators '=3 --ti Size Class:- 40.5 - 50.4 mt Weight: 1061M lbs Configuration for ZAXIS 45OLC-3 Horsepower 348.0 hp Operating Weight 48.2 mt Power Mode Diesel Hourly Ownership Costs Standard Value User Adjusted Value Variance Depreciation USD $49.281hr Cost of Facilities Capital (CFC) USD $19.901hr Overhead USD $32.76/hr Overhaul Labor USD $17.14/hr Overhaul Parts USD $31.41/hr Total Hourly Ownership Cost: USD $150.501hr User Defined Adjustments: Hourly Operating Costs Standard Value User Adjusted Value Variance Field Labor USD $2.99/hr Field Parts USD $31.19/hr Ground Engaging Component (GEC) USD $4.991hr Tire USD $0.00/hr ElectricaliFuel USD $33.53/hr Lube USD $8.87/hr Total Operating Ownership Cost: USD $81.581hr - - User Defined Adjustments: Total Standard Value User Adjusted Value Variance Hourly Ownership Costs USD $150.50/hr Hourly Operating Costs USD $81.58/hr Total Hourly Cost USD $232.07 Non -active use rates Standard Value User Adjusted Value Variance Standby USD $101.95/hr Idle USD $184.031hr Active Rate Internal Charge Rate displayed using default cost factors USD $232.071 Revised Date: 2nd quarter 2026 ' formerly knotun as Cuslnm Cost Evalualor The equipment represented in this report has been exclusively prepared for (bids@ harperbro. com) RFI 19 Response and Revised Plan Sheets Public Works & Engineering Project: RW1901 Garth Road Reconstruction Phase A & B 2123 Market St Baytown, Texas 77521 ' I Baytown, Texas 77520 P: (281) 420-7154 BAYTOWN RFI #19: Independence RCB Connection Error Revision 0 Status Closed on 04/06/26 To Tyler Barrows (Kimley-Horn and Associates) From Brian Hancock (Harper Brothers Construction, LLC) Stephen Kelly (Kimley-Horn and Associates) Date Initiated Mar 30, 2026 Due Date Apr 8, 2026 Location Project Stage Cost Impact Schedule Impact Spec Section Cost Code Drawing Number Reference Linked Drawings Received From Copies To Geovanna Arguelles (City of Baytown), Tyler Barrows (Kimley-Horn and Associates), Johana Campos (City of Baytown), Monica Cisneros (City of Baytown), Rafael Errisuriz (City of Baytown), Cory Halley (Harper Brothers Construction, LLC), Brian Hancock (Harper Brothers Construction, LLC), Martin Hernandez (City of Baytown), Troy Leal (Harper Brothers Construction, LLC), Javier Sauceda (BGE, Inc), Christopher Scullion (BGE, Inc) , Bryce Watson (BGE, Inc) Activity Question Question from Brian Hancock Harper Brothers Construction, LLC on Monday, Mar 30, 2026 at 11:59 AM EDT At the intersection of Independence, the RCB at the cross culvert is connecting to a perpendicular run that travels south to north. This RCB connection is not shown in the details and according to the manufacturer is not feasible with RCB alone due to the wall thickness and length of the RCB units. Harper Brothers recommends the installation of junction boxes to combine the RCB at the point of intersection. This problem exists in multiple areas on this segment of the drainage. Attachments RFI 19.pdf Official Response Response from Tyler Barrows Kimley-Horn and Associates on Sunday, Apr 5, 2026 at 02:38 PM EDT See attached revised plan sheets and additional junction box details for the connections on the West side of Garth Road. An 11'x11' junction box is to be added to the 8'x4' RCB connection and a 13'x13' Junction box is to be added at the 10'x5' connection. The 8'x4' RCB is no longer required at station 182+00 and has been removed. A cost breakdown has been provided minus the cost for the additional 13'x13' junction box as this does not have a unit cost associated with it yet. We will issue connection details for the connections on the East side of Garth at a later time. Attachments RFI-19 Plan Sheet Revisions.pdf, RFI-19 Cost Breakdown.xlsx Public Works & Engineering Page 1 of 1 Printed On: May 12, 2026 12:30 PM CDT �0 �ian�uunMn �ian�uunMnu ire ��Illl�llli �9GIIIHp�III'IIiI@� �9GIIIHp�III'IIiI@� ��I61111118ENIIINI� ��I61111118ENIIINI� �I�11�11�11 �I�11�11�11 �lill@�911i8�!@I I�IIII��1�� III�IIIIIII�III� amwmn�i�n 9111w1h1 IYI�11� ano�um ano�um SMINIIIIIIIIIIIIIIIIII � � IIIIh�l9 Iwo ot� wp•i0'ltl01lIS-�d]tl1tlY]�ioiaia`! •��i81v1 iwide: YYO - I�oiotl�0; vap�uo; l�n�avumay uan]-82099vt90�i:�: ]'lgtl�:v QYYNdIII § 6 - o o z u ¢ o I>., w < % wo a •¢x. Z w ap z J ¢.-.F>¢amoa; LJLLuo u 1 O z>- I as < "1aiz7 wa¢ 8— 'o-8 zo>,zW All ®ru dZJQ O— W 0 ii�'z Im P o-> uN- <Na oi¢1^I�uopwuzu �¢a�u�Ni o 00 au0 00 uN o 0 0¢ axz N--. ~iJou - w¢w¢w ° o oa �ozr1. iouoz<zoo¢aao "0 iowow ¢:No- �o N ' 2I I I 1 ¢swz �.-Names¢-a¢2wina mmLL �. 22w¢Jw�-J-�w¢ U wN ~ • W T• ¢ O i — m WI a0ia¢.¢opu �iwir�iNZ ��N�uvwi� R O mN 9 I I Z ry n P N inn s 00.29L V1S 3NIl HO1VW o 1 11II J� O O ¢— W OQ O - S i I QU � •u'mv: oo u Oa J vOi a ¢o i II ux o oo zP 0 ¢ N / Z IZ'01. 181 tl1s H121tl0 IQ — iz•IE=dot c- ul3 o IJ O J¢1 O Z w¢ O� O — O I ¢ H Id VO ZZ UO a2_ xN� ¢ O O- NZ a sz¢ oJ- �N U ? mw? J — _ — — � � .O _ .20100a wF r0 l —Ro i r� '� U FN O j? 03U -. I Z wU Nw OU0 Qj U O w N oo wZ dtYI�U w mo U Z U '^- HUNT ¢ Wm °zn Ipo 0 mW= �T / i zz! o of t I i o 5'r.. Aq ,I a V s71 rTNN u cM ow"V - wwvz Z J ^4�I I Q aW u fN158o£ZS?bX9B 1W nr Or-L6.8L1 V1S H16VO o0 Q I b9'1£=HMS 8-(1)3 qq Fc I� W Z o i Iloo� Z N ne O < lum a r m - ¢ V a "¢ u I'- ffif is p yl n _ ti 1 �—rrl n z „ w 0 w ).. o^ u <o F > m I I; o ZWw — - a w wo ? IO N U ~ram ``I Ovr¢ O 109 Ioa I1 p„iw w� ^ o - i + ¢ Lz=Z=.,81 (S'NI OS'LZ=.ZX .9 3 "7_`u"'P Ja po _¢p - N �I IL'IE=d01 mo ¢oiP N¢p w 4 I OS'G£•9L1 VIS H1HVO (1-(1)3) HMS 00 .11: n aN a w w dObd �nJ a Jo i, 0 �„�_ (3155'GZ=..81 3J - ¢m (S'N)8b'LZ=.ZX,9 3J 1 1 1 a SZ•9L1 V1S HiNVO sc•I£=dot z-(1)3 I ,,. 00.9L1 V1S 3NII HDIVW 0 ° w eH-9orwis-�tla-le�tlimo\a°w:°tea s\lew 1 �\,a5 �itl\ ,vad �\°�o0�aap\�: P��,awaatl Ws•Y6Z099tl190\I;^: Tllpu\:a Imvx9�u GO B 0 N ZN < a O u Q W o zi wow ws i "o ?o ',irrr 1Lio mrm rvO 3t mzx A mz ^' z a ¢ Ja_>z¢zWiuw �-. a ¢ o a o] cao_ ¢ N ¢ W w N 3 J aio�aai.z> OU Ourc1a �U�Opppo rIr`S4 O ~Nx Oxr W 000 0 0 Wai. ]Z~lyy Q p2 Z_ Nr¢ < o 0 o - - - o 0 o0z 7X X 0<00 n �za�w Noowz-�>N Nw - - -o ` ¢a Q Z Qu u�¢ 0 0 Xaa wo J �`.ww-wtto0 .�-o�l ¢ia�Nam.-¢ou a¢¢awN II 2 a ; � 7Q�O�oOwNOiNz�Zwowwo y� �• N 3 w N u W 1 J I OI 0 I I z 0 a 00•Z9l V1S 3NIl HOiVW a I lo' ¢ z fi ma o a o ¢ u N Imo. _ o wa U / �OO¢ I �I - I o I 2-0100 I z � HUNrRD Ia f� i o� ¢a Jm w ^ 1 lal t t - t I .0 V CNN Ja � O IQ _ a Iu� - Iw o LL mom 11 as =ioJo I� N wa.mo- �Q _ 2 o¢z raLL w z 00.9LI V1S 3N] 1 N oLL m� a xx'No i ; 'GZ•.Zx,9 71 OS'tI.6L1 tl1S H""'o 9" I£=d01 0-(1)1 0 0 a+ (M)06 'LZ •..81 (S'N)LL OS '16•9[I O15 H1tl70 Z9'If=tl1 (1-(1)1) HY15 dOdd (11)OH'LZ=.. 91 1 (S'N)IS'LZ=.ZX,9 71 00'0b•9L1 V1S H18VO 19'If•d01 £-(1)d o I0 wo'BS'S\199Y1 I d3lra5 —4—l-0 - r�o•o0w;9a0�w;ran�r9waatl ua�o�-92099r190�i:•:]"lgN��r 3rIVN3l11 O Iz r OZO ¢ J y ¢o O a < L Z W ¢ O WV�1-.1 �rWYLL; y Jio�ai � a z w z ¢ ¢ a i z p¢ w w� o u N a- w z o_ oa AJN z> rva �m-¢aai ¢ z )p_ zbi Y,II� 00 O O NUj=U Vw m w; N N N m ¢ a .0 -- - O- O-- -- 0 0 0 a az a a¢ Z NOOOZ-haw o oa o o u ' wo -¢�� �yo4�w¢so •moo %] ZI II mm-P=¢�Ws�LLw¢�w � NM NZ - 16�: 0 0 00.991 V1S 3Nll HOIVYY anie t o 3:)N3aN3d3aNI o.00 a � oX♦ i � . �•; Fl, 1 7 m it row N N� ¢lii uv f m I ~ ¢ N x - I 0 0 o mz- .0 IF F x I„; z Uaw jI N¢ I II I` aN O� ¢ goo Zro V Om u- O V_p !0 Z JT N O•. O - U ~ 1 w ¢ � 010 z Ja uu'a � xII ' I O I N = I v O •I I Z O m I i I z Q Lu oW J J ry N a U- m- -< o Ww cm o F v a SNF QZ Ucyl N Q Q 00 ry - N o 0 mF;O�03 (N)60'£Z=.S%,01 7J o u� fL'06.98t V1S H1HV9 89'0£=d01 6Z- UlV 18 .10'£Z 89'£Z 13 .V%.Zl BZ'BL•981 V1S HIHV (M)'IN)60'£Z=.V%,8 � £B'V9.981 tl1S H1HVO VS'0£•d01 £-(1)0 13)Z6 'b2=..81 71 00'OL•981 V1S HiHV0 Lt'O£=d01 V-(110 win iW z ¢J uJ ¢O w Z-- O U- m (3)OE'SZ=..Bt 1 (S)'(N)SS '£Z=.VX.B I 00•ZBI V15 H1Htl0 0 LS'0£=d01 9-11)0 0 N - o wY'BN-LO/Itl15-Otl0-ld]N1tlY0\��:0�0 'S\19911 I AJ\1�9 �Itl\�!v a0 - Y\olo0wo!va0\VO!i��ivVOavtl V1�00-9L099vL90\1:�!0-f10N\xY ,3Y1'IN3111 U Z 000 LL o ` oo JF O o i Q U U Z m w O Q Z .r F N o w ¢rcwi¢O- Oo n N R Lu ¢m J J Om O a a o Z w N> w 0 w w c O s �� a m w 3¢ w ¢ �`eq, z 8iww3 3¢ <� 2 n0 V �i'bJ,�Ii� oN�o zo�o u F 4 /\ as •'r' /"� ® ZZ oa O o _ 0 W 'om-a Q w z osu yyyya- i a a a w �' a z z_ a "' a J=oaai a.e 0 3 r a ? a ¢ w W r O U N 3 W ¢w Z O .o¢�u� zi mF �a ain ¢- OZ Opeaa a !' ,�rlj a IaN Q Op OFF l m W 3 VI N Vi N N 3 000 O O m �- ,���.iiii.''J s+ /� 1 NU z2ioU wZi uOZ>6 W M QQ Z p W m Q N¢Q O - O - - - O O O a aZ ¢ ¢ ¢ z O '?2aw v+00uz-�rwp Nw 4P Q ¢a Z 2 a - U¢ x¢ x x¢¢ Oa O a�=p"�wrcoa>+1.,a ir¢�¢o~x�oaaa..rao¢wo ja�0¢w¢OwwOUw y� I 2 ¢ _ (.7 0 Z,-ZwOwwO K W - O W O O .I z 00.99L V1S 3NIl H3101 c v n roi ry ry - o �w a.w wm I 3= rr mm v ania �Zz ¢� aNW m ox I 3JN34N3d30N1(� z'oa _p amu wu- ¢ ¢7 10'00 J O xa awzozo. Nod z —c> � a¢a Iao¢ a- ¢ - z pU t of ♦ a r ion d01 I o zl r ¢ f o z - UP '131E0'£Z=,SX,01 I _ f O£'£6.991 V1S H18VO ,� OL 'OE=HWS OE-(l)V _ r •• Re'91.901 V15 H%V9 •• mN (M)'(3)EO'E2= bX.B JJ � w I �• �T �,p� -.I ~ - ¢ o oQ• rvmo £9'OC = d01 BZ'b9.981 V1S H18VO 9S'OE=d01 O WLL O ,. Z x ORry o omu O a�- o' _ - ¢�`xa IMI ZH'bZ=..81 I (S)'INI LO '£Z=.bX.B 1J w w �i u OD ,_ L9'L6.991 V15 H1tlV0 0 o m Oa a a w xa �I_p p m (5) l o O_ Q I 00'OL•98! v1S H18VO a x "' I Gl'0£=d01 Z-1110 _ woo. sorb zuum n l p o w' -zzZ OU- I Z v UO`U tiJp J wN o x dux poQ I O N mw; xI NJ 0 po¢ N n o U o z;� Im I (A= W z m Z n Z ¢ m o IS)'(NI Ob'£Z= x.B l u a I p 6b'08•b81 V15 HldV0 m SS'OE•d01 £-(1)0 z _ o I ¢xa m - I z w- - ix _ o I iW W mz az a -0.p _ ¢- w > o ¢p I OJ ¢O u a ¢ •mop o Fa u cr'Q �o i mJ � I o -- UO m - - a I IS) '(N109'EZRio - I ?mao ory OS'Z9•E81 V1S H18VO w� LZ '0£=d01 b-U10 I o iQ pxs �Nm rI� O- u ; OW rv- LLU mN N +p J y r N VNz ZZ NZ ¢U ¢- ¢� Wa O w I Z z� wJ y wJ z_ m m -is0. J I a+ I a� wyUw W. ¢O w U El —Z ¢z_ 0 o ¢ I¢ N n¢O a wpry L I ® = w= vw > D;o N¢ U - OO•Z8l V1S HlbV9 0 6S'0£=HY15 S-(LO 00•Z9l V1S 3NIl H31VY4 �eo'as ioru�s-aen-�.����•n�aeao,om c��r�o i ewx ooi e�m,aan - r.o,ome,un�w,.m„awo,,, na or nz n vzozisie :a3uoid �,no.nzoaa.+ao��,.•rrxw... .a..r.n(� Z O ¢ O v a p N Z O w 2W W O ~ QO 3 2 Q jw z m Z N OW U K �Q wW O~ ¢ W O K 0_ ¢ ZNw Zao ~r OZuf o Om ZU Ou KWin Fw r.~.ZW pX Z N U U J 2 0 mop uiz awvi ez azal oo u Qaw ow o aom aW- z�a o —wW 7o aaN �ux,3W ox ¢ zJ 0 N¢ m K 2 3 S¢ Q O 3 Z OQ w az _�oww o�N- ¢� owww ¢= o apx - 0 xso> wN F S> WZ O aZUW N3 w Nw00 o=w xao �a Nw oo ¢u zu — `oow2= a r3N N ¢ aQia aZVf� ¢ ZWN—o J Q wU W 2 U .m W Q p02 Z 2 Z -OJUOm�� w-+i- U 42- pa O •moN2v �•a N ¢ ZxZ JOOp W NQi-�¢a a mavi ¢aw Nr N V-M a 8 zNN Boa i�Nwo F�xi,aoz NFz �zaa QQ z~ mo p�oi�wN Q iQ2 our] o-a iwoN- _- aU aZ 00.-. ¢ NU!OJ�Ow��Zaa JO¢a ~mZW p Z x � m� uz zu+wz.,;---O- Q O z w w- W m_ro--mN vwiu owJJNa a o`W �za xo JOJa oNo wa Ja N Joy Nz¢Q"zNa i pzrvv N m0 �O�rvo¢iiirOWr �iaJ aJw?~J �1 J ao u3 3 p1-Jzu�-zJu Z w� U OW wO Q z a a p wi0 U �u 0 NO •¢Z¢u O Z O� ZU J U N Z Z- - D_ .� Q U r ow- - a m waaox-.-oopoQwcawowuQ op--�, NoaJNoww3Nu QNi-•ww¢NUwUm¢ J¢¢¢i. ¢f-W J�OrCQwU�aw>QQL- o_ ao•�-Jua aQpzwu ozzouom ��no�W-az+f� Jipa Jozo�w�uowuoz�,o sx-¢wr-Nw�J�pa Q�awamac�vaawau--maauQaJaQao�¢a¢��--¢uaoaa z J o- iv -mo J N N 3« u� Oa O 0 o At a Cf] ! m U W Ln N CLR uOp •BO VOB0�531 v130-�m0u:0�0 'S�!B9v! ! d11— - ; u+-0-9Z0991f90\1:•!]'OOtl��v �D19N331f z �ry pN J z uw w �u J r =¢ N aaF w " ¢_ ; - L o Q _u o�R < W ovxi oz m2 ¢ W�w x o w- a� a m� - z m vi Q W y N S iNw iao¢wo ¢a ¢ b u Z. OV ¢WN FW<mU Wu Z iOp O- Z UJ¢O �ZU -¢ QrrJ iS/IU N W c ¢ -z NWN ;z ¢Z- 00 4 ¢<w O V °���= p X - ¢m au- Z. o uu oxx a do aw aNa wu L'W-x aN u N;w Ox w �.,"'.'.a'`�,.�, a ^ /� gR oa 6 �W- v o z o� ax zJ -u-� i a z.- •a d1 a_ {h ' m `� Na �O¢�Z ixa o ;Zp¢ NZ ¢p y _ <OF pa NUzo WN �``.:... ZZUuO"N¢ OW �ZUw N; F LLw X O�w x w �a� W ® 02 O N�OOS NIA - o a �mOa zwzN-;np¢ sW f ¢wateN m aQ ¢UwQuZ zuttU2 pa pU_AWw ¢ .z 2xO.T Z N Jar wz- m —H2O - pW _6 Ny d¢w Oz N.-. Z JZ.--NJ�Q W. Jp; W Wyp F m0 ZOO �U� m 9 N U xwo-- N-Ja a¢ NZ� w NU O° owm>� �Z� p g mWp W~O�oZWw_ i a =-a m-- uz zu.�+wou o-mN Nuow..JNa ONO NWa JQZ.U- Nr¢Jr�JON NZ¢¢UZN4< Z F mZ QOZNNJ�~ w Z< p-- ZwJ NWZ N O S¢OOWaUUSZWSJ« J OJO-� N 2U ZJp NO•-NO¢N ZI-OrrJ2 V d--w N Ji J OOZ OJZ Ur Ow-•-UN^QNU <U�¢NZr -a a0 WUU U; ; Zw a.-l--ZJV Z F-S¢ I...3SV¢ U N^Z ZWOWZ-<Wa¢ Waw N¢ ¢wf UOW zwOWZa QOw�O VIVO .xW g U¢Z .iJU-UZN�W-NZZWUZZJwrOm ¢UU aU�ZNr'fm 5 O¢ QaO�a Q - <ox m o.o -n¢3Ow>W¢a+¢;^ONaYU wu t--um¢ ¢¢¢pyu4}.Gy¢QW?"?oWa-a 'o ^a< i w¢ozJuz1oYvaJNoxinWrcaiNrcuJio io �Wapo¢ Nf ... ¢�ONWa^wWam¢!\!aaZ^u-maQa .0_.V a - N Lo N J O u w0 .m U 10' X 5' o a RCB v� • s� s �! m u a° 0 O] [17 • Z N - m O � N U a u W N o In - 9-.1 Y/2 " CLR TYP x ¢ 10' X 5' w wN_ a RCB N¢ � N wi a� ►I� J O a � M ON x + m o; w o� LLI 00 10' X 5' + RCS Q _ �'/x" ClR H lP . L J TYP #0 ! 10'XS' RCB BJB -w N— Z J a 9-.l FLO(L J l' .sx.ol r a N 1 ; 1 Q it x O m ¢ o� O 0oa •d oo• zo¢NJ ~ W «NQJwY; U .O (n ¢aa�r=o IS Z o NF- O N x¢oaN- � ; zw <NO�rV!NO - ¢a a o 0= Uwxi 22wwaU� O� a a�az v 3Nm--�O O J N N; 0+ O Nm J W^_W aD •d a•� �O « e u0o'60XOB!'\S 119130-\90ou;oi0 'S\(09�1 ! d]\=K �id\�!•w �\oao0u6!vY0♦W!�r.��suoab IW 60 =81=! 9ZOZ/SII MMWII u��o9-B20991L90\I!n!]-lION\�Y =31�M311f 4. Elimination of Existing Pavement Markings Throughout the Project Limits Contractor Pricing Submittal Bryce Watson From: Brian Hancock <Brian.Hancock@harperbro.com> Sent: Tuesday, April 28, 2026 2:47 PM To: Bryce Watson Cc: Cory Halley Subject: CO 01 - Elimination of Striping Attachments: CO 01 - Eliminate Striping.xlsx; Invoice_12780_from_Traffic_Signs_Lines_LLC.pdf Follow Up Flag: Flag for follow up Flag Status: Completed Bryce, Please seethe attached Change order and back-up for the elimination of striping that was missed on the plans. Please let me know if there are any discrepancies or needed corrections. Brian Hancock Project Engineer 1310 Rankin RD, Suite 200 Houston, TX 77073 C: 346.323.0686 CM HARPER BROTHERS 7-7004 CHANGE ORDER Project: Garth Road Phase A & B Control: D912-72-359 Scope of Work: Elimination of Exisiting Striping HBC LABOR ITEMS QUANTITY UOM i MANHOURS HOURLY RATE CO: EA $ SUBTOTAL HBC LABOR:: ; $ TOTAL HBC EQUIPMENT ITEMS QUANTITY HOURS HOURLY RATE CO; ............................................................... EQUIPMENT I.1MyTI.rT-X. Itv1:i11V,1 1.299.00 600.00 LF i $ 0.90 ...... _......... ....... ...... .... ............ ................ ..._.... ... ......................... .............. ................................................... ............................................... ...... ......... ..... ....... . _ .1.................... ..... SUBCONTRACTOR MARK-UP 5.00% $ TOTAL SUBCONTRACTED ITEMS:; $ 1 TOTAL HBC ITEMS: $ - TOTAL SUBCONTRACTOR ITEMS: $ 16,503.22 SUBTOTAL 16,503.22 BOND 1°o $ 165.03 TOTAL $ 16,668.25 Traffic Signs & Lines LLC 914 Broadway Ave Pasadena, TX 77506 +13464440043 trafficsignsandlinesQa gmail. com INVOICE BILL TO Harper Brothers Construction LLC 1310 Rankin Road. Bldg 18 Ste 200 Houston, TX 77073 USA TS&L- INVOICE # 12780 DATE 03/27/2026 DUE DATE 04/26/2026 TERMS Net 30 DATE ACTIVITY ACTIVITY -- RATE AMOUNT 03/18/2026 Striping CHANGE ORDER #3 10,694 0.45 4,812.30 FOR DATES: 03/18/2026 & 03/19/2026 (ITEM#0677-6001) ELIM EXIST PAV MRK & MRKS (4„) (LF)=10,694 03/18/2026 Striping (ITEM#0677-7004) 1,299 0.90 1,169.10 ELIM EXIST PAV MRK & MRKS (8") (LF)=1299 03/18/2026 Striping (ITEM#0677-6005) 298 3.00 894.00 ELIM EXIST PAV MRK & MRKS (24") (LF)=298 03/18/2026 Striping (ITEM#0677-6008) 11 65.00 715.00 ELIM EXIST PAV MRK & MRKS (ARROW) (LF)=11 03/18/2026 Striping (ITEM#0677-6012) 7 65.00 455.00 ELIM EXIST PAV MRK & MRKS (WORD) (LF)=7 PROJECT: BAYTOWN GARTH RD PH A & B SUBTOTAL 8,045.40 ID GARTH RD PH A & B RW-1901 CHANGE TAX 0.00 ORDER #3 TOTAL 8,045.40 PAYMENT IS DUE WITHIN 30 DAYS OF THE INVOICE DATE. A LATE INTEREST CHARGE WILL BE APPLIED TO ANY BALANCE DUE $8,045.40 OUTSTANDING BALANCE" Confirmation of CO From FOR Bryce Watson From: Barrows, Tyler <Tyler.Barrows@kimley-horn.com> Sent: Wednesday, May 13, 2026 3:47 PM To: Bryce Watson Subject: RE: CO 01 - Elimination of Striping Bryce, Yes, this will have to be a change order. I reviewed the plans and didn't see where we noted that it was subsidiary to other items. Thank you, Tyler Barrows, P.E. Kimley-Horn 111233 Shadow Creek Pkwy Suite 450, Pearland, TX Direct: 281 836 4372 1 Main: 281 895 1210 Connect with us: Twitter I Linkedln I Facebook I Instagram I Kimley-Horn.com Celebrating 19 years as one of FORTUNE's 100 Best Companies to Work For From: Bryce Watson <BWatson@bgeinc.com> Sent: Wednesday, May 13, 2026 3:43 PM To: Barrows, Tyler <Tyler.Barrows@kimley-horn.com> Subject: Re: CO 01 - Elimination of Striping Tyler, Just to confirm, I assume by you providing the updated CO quantities that you would agree that this would constitute a CO? I have gone through them but I just wanted to be sure there is no where in the pans that would point to this work being incidental? Bryce Watson, P.E. BGE, Inc. +1 (346) 320-1383 p +1 (806) 676-3715 m From: Barrows, Tyler <Tyler.Barrows@kimley-horn.com> Sent: Wednesday, May 13, 2026 10:47 AM To: Bryce Watson <dyyatsonLa)bgeinc.com>; danielle.cain < ']in@baytown.org> Cc: Javier Sauceda <JSauceda@bgeinc.com>; Johana.Campos-Estrada <iohana.cameos-estrada@baytown.org>; Monica.Cisneros <monica.cisneros@baytown_ >; Martin. Hernandez <martin.hernandez@baytown.org>; Denise Schott <�schott@bgeinc.com> Subject: RE: CO 01 - Elimination of Striping Good Morning Bryce, Please see the attached excel file with the additional pavement marking removal quantities. Thank you, Tyler Barrows, P.E. Kimley-Horn 111233 Shadow Creek Pkwy Suite 450, Pearland, TX Direct: 281 836 4372 1 Main: 281 895 1210 Connect with us: Twitter I Linkedln I Facebook I Instagram I Kimley-Horn.com Celebrating 19 years as one of FORTUNE's 100 Best Companies to Work For From: Bryce Watson <BWatson@bgeinc.com> Sent: Tuesday, May 5, 2026 2:51 PM To: danielle.cain <danielle.cain@baytown.orC1>; Barrows, Tyler <Tyler.Barrows@kimley-horn.com> Cc: Javier Sauceda <JSauceda@bgeinc.com>; Johana.Campos-Estrada <johana.campos-estrada@baytown.org>; Monica.Cisneros <monica.cisneros@baytown.or9>; Martin. Hernandez <martin.hernandez@baytown.org>; Denise Schott <dschott@bgeinc.com> Subject: FW: CO 01- Elimination of Striping Tyler/Danielle, Please see the attached change order request for removal of existing striping from the recent traffic switch into the Phase 1, Step 3/4 configuration. reviewed the plans and specs and didn't see anything indicating this work is subsidiary to another item. The general notes reference Item 677 (Eliminating Existing Pavement Markings & Markers), but there's no direction on how it's to be paid and no bid item included in the contract. The contractor's pricing comes out to $8,532.15 for the removals completed so far. If we agree this work should be paid and isn't subsidiary, we'll also need to include quantities for upcoming traffic switches. Per the 2024 TxDOT specs, Item 677 is a plans quantity item, so we'll need to review the upcoming TCP, determine a total quantity, and apply the unit price to build out the final change order. Let me know what you think. Thanks, Bryce Watson, P.E. BGE, Inc. +1 (346) 320-1383 p +1 (806) 676-3715 m From: Brian Hancock <Brian.Hancock@harperbro.com> Sent: Tuesday, April 28, 2026 2:47 PM To: Bryce Watson <WWatson@bgeinc.com> Cc: Cory Halley <Cory.Halley@harperbro.com> Subject: CO 01 - Elimination of Striping Bryce, Please see the attached Change order and back-up for the elimination of striping that was missed on the plans. Please let me know if there are any discrepancies or needed corrections. TxDOT Specification Item 677 Eliminating Existing Pavement Marking and Markers 2024 Specifications 677 Item 677 rM EliminatingExistingPavement Markings MarkersJ�Te. gpTianspoRafion 1. DESCRIPTION Eliminate existing pavement markings and raised pavement markers (RPMs). 2. MATERIALS Furnish surface treatment materials in accordance with the following Items. ■ Item 300, "Asphalts, Oils, and Emulsions' ■ Item 302, "Aggregates for Surface Treatments" ■ Item 315, "Fog Seal' ■ Item 316, "Seal Coat' Use approved patching materials for repairing damaged surfaces. Use a commercial abrasive blasting medium capable of producing the specified surface cleanliness. Use potable water when water is required. 3. EQUIPMENT Furnish and maintain equipment in good working condition. Use moisture and oil traps in air compression equipment to remove all contaminants from the blasting air and prevent the deposition of moisture, oil, or other contaminants on the roadway surface. 4. CONSTRUCTION Eliminate existing pavement markings and markers on both concrete and asphaltic surfaces such that color and texture contrast of the removed area and surrounding pavement surface will be held to a minimum. Remove all markings and markers with minimal damage to the roadway to the satisfaction of the Engineer. Repair damage to asphaltic surfaces such as spalling and shelling greater than 1i8 in, deep resulting from the removal of pavement markings and markers. Dispose of markers in conformance with federal, state, and local regulations. Use any of the following methods unless otherwise shown on the plans. Refer to the Pavement Marking Handbook for additional information on removal types and best practices. 4.1. Surface Treatment Method. Apply surface treatment material at the rates shown on the plans, or as directed. Place a surface treatment at least 2 ft. wide to cover the existing marking. Place a surface treatment, thin overlay, or microsurfacing at least one lane in width in areas where directional changes of traffic are involved or other areas as directed. 4.2. Burn Method. Use an approved burning method. For thermoplastic pavement markings or prefabricated pavement markings, heat may be applied to remove the bulk of the marking material before blast cleaning. When using heat, avoid spalling pavement surfaces. Ensure the burning heads are not left in one place too long to prevent pavement damage. Sweeping or light blast cleaning may be used to remove minor residue. 4.3. Blasting Method. Use a blasting method such as high-pressure water blasting, abrasive blasting, water abrasive blasting, shot blasting, slurry blasting, water -injected abrasive blasting, or brush blasting as approved. Use high-pressure water blasting for removal of pavement markings for lane shifts on concrete surfaces. 920 2024 Specifications 677 4.4. Mechanical Method. Use any mechanical method except grinding. Do not use flail milling on grooved concrete or porous asphalt. 4.5. Corrective Actions. Whenever removed markings on asphalt surfaces continue to simulate pavement markings to an extent determined by the Engineer to cause driver confusion, apply a fog seal or slurry at least 2 ft. wide over the area where pavement markings were removed as approved. 5. MEASUREMENT This Item will be measured by each word, symbol, or shape eliminated; by the foot of marking eliminated; or by any other unit shown on the plans. This is a plans quantity measurement Item. The quantity to be paid is the quantity shown in the proposal, unless modified by Article 9.2., "Plans Quantity Measurement." Additional measurements or calculations will be made if adjustments of quantities are required. 6. PAYMENT The work performed and materials furnished in accordance with this Item and measured as provided under "Measurement" will be paid for at the unit price bid for "Eliminating Existing Pavement Markings and Markers" of the type and width as applicable. This price is full compensation for the elimination method used and materials, equipment, tools, labor, and incidentals. Removal of RPMs will not be paid for directly, but will be subsidiary to pertinent Items. 921