2026 01 21 BAWA MinutesIII
MINUTES OF THE REGULAR MEETING OF THE BOARD OF DIRECTORS
OF THE BAYTOWN AREA WATER AUTHORITY
January 21, 2026
The Board of Directors of the Baytown Area Water Authority (BAWA) met in a Regular
Meeting on January 21, 2026, at 5:00 P.M., in the Baytown Conference Room of the Baytown
City Hall, 2401 Market Street, Baytown, Texas with the following in attendance:
Brenda Bradley Smith President
Frank McKay III Vice President
Alyssa Linares Director
David Start,Jr. Director
Brant Gary Assistant General Manager
Scott Lemond General Counsel
Miriam Hernandez Acting Assistant Secretary
President Brenda Bradley Smith convened the January 21, 2026, BAWA Board Regular Meeting
with a quorum present at 5:01 P.M.,all members were present.
1. CITIZEN COMMENTS
President Brenda Bradley Smith announced no one signed up to speak.
2. PROPOSED RESOLUTIONS
a. Consider a resolution authorizing the purchase of construction services for the
renovation of the Baytown Area Water Authority Administration Building Project from
Buyboard Contractor Brown and Root Industrial Services,LLC.
Public Works and Engineering Assistant Director of Utilities, Sterling Beaver, presented Agenda
Item 2.a. and provided the Board Members with an overview of the agenda items. Mr. Beaver
stated this proposed resolution authorizes the purchase of construction services for the renovation
of the Baytown Area Water Authority ("BAWA") Administration Building Project from Brown
and Root Industrial Services, LLC, and the scope of work includes Americans with Disabilities
Act ("ADA") renovations for compliance purposes, which includes renovations to the interior
men's and women's restrooms, unisex restroom, kitchen, front receptionist desk, and locker
room.
President Brenda Bradley Smith asked if this facility is the old plant off of Thompson Road and
Mr. Beaver confirmed that it is. Additionally, Frank McKay questioned if ADA compliance
items are mandatory to fix and Director of Public Works and Engineering Frank Simoneaux
responded it is mandatory,but that it does not have to be done all at one time; however, we have
to provide a plan to show we are pursuing compliance.
BAWA Board Regular Meeting Minutes
January 21,2026
Page 2 of 3
A motion was made by Director David Start, Jr., and seconded by Vice President Frank McKay
III to approve Resolution No. 2026-1,related to Item 2.a. The vote was as follows:
Ayes: President Brenda Bradley Smith, Vice President Frank McKay III, Director David
Start,Jr.
Nays: None
Other: Director Alyssa Linares(Abstain)
Approved
RESOLUTION NO. 2026-1
A RESOLUTION OF THE BOARD OF DIRECTORS OF THE BAYTOWN
AREA WATER AUTHORITY AUTHORIZING PAYMENT IN THE AMOUNT
OF ONE HUNDRED TWENTY-FIVE THOUSAND EIGHT HUNDRED FIFTY
FIVE AND 00:100 DOLLARS ($125,855.00) TO BROWN AND ROOT
INDUSTRIAL SERVICES, LLC FOR THE PURCHASE OF CONSTRUCTION
SERVICES FOR THE RENOVATION OF BAYTOWN AREA WATER
AUTHORITY ADMINISTRATION BUILDING PROJECT THROUGH THE
TEXAS LOCAL GOVERNMENT PURCHASING COOPERATIVE
BUYBOARD), CONTRACT #728-24; MAKING OTHER PROVISIONS
RELATED THERETO; AND PROVIDING FOR THE EFFECTIVE DATE
THEREOF.
3. REPORTS
a. Receive a report on the status of the Baytown Area Water Authority East
Expansion Project.
Director of Public Works and Engineering Frank Simoneaux presented the status report for the
Baytown Area Water Authority East Plant Expansion Project. (Exhibit A)
b. Receive the Baytown Area Water Authority's Annual Financial Report for the fiscal
year ended September 30,2025.
This item was pulled and no action was taken.
c. Receive the Baytown Area Water Authority Quarterly Financial and Investment
Reports for the Quarter Ending September 30, 2025.
Director of Finance Teresa McKenzie presented the Quarterly Financial and Investment Report
to the Board for quarter ending September 30, 2025, and the Board considered the report as
received. (Exhibit B)
4. MANAGER'S REPORT
BAWA Board Regular Meeting Minutes
January 21,2026
Page 3 of 3
a. The next Baytown Area Water Authority meeting is scheduled for Wednesday,
February 11, 2026, at 5:00 p.m., in the Council Chamber located at City Hall, 2401 Market
Street,Baytown,Texas 77520.
Assistant General Manager Brant Gary reminded Board Members of their next Baytown Area
Water Authority meeting, which is scheduled for Wednesday, February 11, 2026, at 5:00 P.M.
Additionally, Mr. Gary announced the upcoming retirement of Director of Public Works and
Engineering, Mr. Frank Simoneaux, and praised him for his years of service to the City of
Baytown and to the Baytown Area Water Authority.
5. ADJOURN
A motion was made by Director David Start, Jr., and seconded by Director Alyssa Linares to
adjourn the January 21, 2026 Baytown Area Water Authority Board Regular Meeting at 5:23
P.M. The vote was as follows:
Ayes: President Brenda Bradley Smith, Vice President Frank McKay III, Director David
Start, Jr.,Director Alyssa Linares
Nays: None
Approved
a okoilltiiii,.
Atia .. 0 -.:'--1`.
2.: 44
Angela J.t: on,A i s =N. '*4
City of Baytown. /
f'+'
ff1*
1i1 it.\,``
EXHIBIT "A"
PROGRESS REPORT
104.
Project: BAWA East Surface Water Treatment Plant Phase 2 Expansion
Owner's Advisor
Date.January 2026 Progress Report
1, Previous Months Activities BAWA East Water Plant
A GMP Approval
2. Projett Highlights Progressive Design BuildA. Funds Available($79,000.000)
B Project Budget with GMP Prue Proposal
BAWA Board Meeting
BWP-GMP 69,782,881 January 21,2026
Material Testing 600,000
Pulsed Bed Clarifier 2.092 798
Recommended Owner Contingency 2434,091
m -':
of sit«p,• +. ,,,..
y 47,R
Fiscal Services 382,000
OA wan CM S3.473.578
Project Budget 818,185.328
C Schedule
1) Limited Notice to Proceed-January 7.2026
e '
21 Pulsed Bed Clarifier Proposal-February 18,2026
4) Phase 2 Substantial&
ComFinal -May - my 1 U, '4) Phase 2 Acceptance Final Completer-July 19.2028 J-/
5) BAWA is anticipated to need additional water by 2028
D. Outstandr g Agency Reviews
1) TWDB Environmental Review/Design Package
Project Budget Schedule
Cost Category Cost Direct Purchase of Pulse Bed Clarifier gives a
Limited Notice to Proceed-January 7,2026
GMP 69,782,861 savings of-$200,000
Material Testing is estimated at 1%of
Phase 2 Kick-Off-February 2,2026
Material Testing 600,000
construction value Groundbreaking-March 23,2026
Pulsed Bed clarifier 2,092,798
Owner's Contingency used unforeseen Phase 2 Substantial Completion-May 22,2028
Recommended Owner $2,434,091 conditions,force majeure,etc.(included in Phase 2 Acceptance&Final Completion-July 19,2028
Contingency TWDB loans)
Fiscal services 382,000
BAWA is anticipated to need additional water by 2028
Owner's Advisor fee includes construction
oA with CMl 3,473578 management and inspection.
Project Budget 78,765,328
Remaining Approvals:
TWDB Design Builder Agreement
TWDB Design Package
TWDB Environmental Review
Nat
GMP Proposal Phase 1 Baseline Schedule
GMP Category Cost 10 different bid packages comprises the
direct construction cost TWDB SWIFT Abridged Application Submittal-Due February 3,2025(Submitted Jan 31,2025)
Direct Construction Cost 547,350,183 Draft PreliminaryDesign 30% Due March 2025(Received Mar 04,Allowances are used for items that are not g ( ) 2025)
BWP Allowances 425,000 yet finalized at time of bidding: TWDB DWSRF Emerging Contaminants Application-Due April 4,2025(Submitted Apr 01,2025)
Additional Groundwater Dewatering
Contingencies 53,822,015 Adverse weather Conditions
Base Cost Estimate-April 2025
Pretreat Shoring,Additional G5T Baffles,Existing 60%Design Package-June 13,2025
Phase 2 Design&Construction Admin 53,798,071 Operating Support
70%Design Package-August 8,2025
Bonds&Insurance 2,532,559
Contingencies are used for design&
estimating gaps(bid at 70%design)and TWDB Design Submittal-September 8,2025
Design Builder Fee 5,358,324 construction unforeseen costs. Tied to
TCEQ Design Submittal-September 03,2025
anticipated risk events identified in the risk
Phase 1 Services 56,496,709 register.90%Design Package-October 17,2025
Total Design Builder GMP 69,782,861
Assumes TCEQ and TWDB approval prior to Guaranteed Maximum Price Proposal—October 31,2025
anticipated NTP date.
2024 2025 20
0 N D J F M A M J J A S 0 N D
t a.
Original Plant Construction(Design-Bid-Build)Phase 1 Baseline Schedule
Design Start
Date 20,4
MIS n 53.8 Fii,$5s TWDB SWIFT Abridged Application Submittal-Due February 3,2025(Submitted Jan 31,2025)
Mthonl M Ilv
Draft Preliminary Design(30%)-Due March 2025(Received Mar 04,2025)
TWDB DWSRF Emerging Contaminants Application-Due April 4,2025(Submitted Apr 01,2025)
Bin-2017 Construction
I556.7 Completion Base Cost Estimate-April 2025
2021 355.2
Current Plant Expansion(Progressive Design Build)Milliorv$78.7 60%Design Package-June 13,2025
Mi1OOnl
70%Design Package-August 8,2025
PDB Notice to Scheduled
Proceed- GMP- Construction TWDB Design Submittal-September 8,2025
Sept.2024 Octobe,2025 Completion-
57B.BMallon) 78.7Mellon) July2028 TCEQ Design Submittal—September 03,2025
90%Design Package—October 17,2025
Guaranteed Maximum Price Proposal—October 31,2025
MOdel-Apnt
20251377.2
I 2024 2025 2u2r{,
Million)
N o J F M it J J A s N J0 -
oNl
TWDB Next Step LayoutLaout
If
July 2025 it
o TWDB Board approved the funding.
August 2025
w JP}{
o BWP submitted the design package including plans,specifications and front-end documents
to TWDB for review. i' roApprovalofFinancingAgreementonAugust27,2025 with City Council approval on August
r,
f
28,2025.1•+ .
October 2025
o TWDB will provide interest rates on October 2,2025.1 f l I
o Special BAWA meeting to approve the sale of Bonds to TWDB.
I
o City Council confirm bond sale on October 9,2025.
November 2025
may
o Closing date schedule for November 14,2025.
J t tt ,';." co%
Progressive Design Build Procurement Progressive Design Build
Phase 1:Getting to Guaranteed Maximum Price Phase 2:Finalizing the Project THE PDB PROCUREMENT PROCESS
Design Design/Construction
Progressive
Design-Buda
1 Partnering Workshop fm.thzeDennn ipnei
I Alternative Analysis Workshops 11111111=11111111D nrsa•"'
I Permitting Plan I
Main Portion of Construction 1
imsamangsmaimumn,
1 Field Investigations
owner,oA/De:en Bu id team Collaboration on i,st.c'
I 60-90%Design Phase ,
I Cost and Schedule Modeling i I a1.fyPt.f811Ce I IIIIIIIIIII
I GMP Development 4" I Mart”Wrest mei liar mg I 111.""' •ew^••• ""e'
CONSTRUCTION MANAOSR
Baytown Water Work Partners Project Experience
we..
BAWA East Surface Water Treatment Plant Start-Up
r,;,O City of Baytown Wastewater Treatment Plants and Lift Stations SCADA Project Package 2
A° Ma IWyAR. City of Houston Northeast Water Purification Plant
Colorado Springs Utilities Southern Delivery System Water Treatment Plant(10 MGD Expansion)
Pyramid Peak Water Treatment Plant Expansion(15 MGD Expansion)
M,„Mil1111ff San Jacinto River Authority(30 MOD Water Treatment Plant)
dr COMM Me
f""ru,7 City of Houston CRMP—Northside Wet Weather Facility
AAdrCI_a
MW_s
1
ACTALMMMR•W{YtNAROM AIO11Aw
PHASE 2 Phase 2 has a heavy focus on the construction of your surface treatment
plant,while keeping design leaders engaged.This collaboration ensures your A.
praJec!is completed on limo and with{n budget.